Permit Information
Permit NumberBLD15-03994
StatusFinaled
Name TKE CONSTRUCTION
Site Address 1411 W FRANKLIN ST
Project NameJJ Shaw Office Space
Customer Number 
ePlanReviewYes
Description
(JJ SHAW OFFICE – HOUSE CONVERSION) (CUP15-00055, CVA15-00032, DRH15-00263) This building does not have a fire sprinkler system. To convert a 3,160 square foot (4,218 square feet including the basement) former single-family dwelling to an office. The most recent use was as an R-3 Occupancy bed and breakfast. All residential uses within the main building are required to be abandoned. This building has 3 stories and a basement. Work is to include upgrading an existing restroom to be accessible to the disabled to the maximum extent that is technically feasible. Exterior work includes a new concrete landing, concrete retaining walls, concrete stairway, a van accessible parking space, and a wheelchair lift at the back entrance. A handrail will be installed on each side of the existing front exterior stairway. The windows and door at the front porch will be removed to restore the porch to its historic appearance. Generally, according to the 2012 IEBC, if the building complies with the IRC (R-3 Occupancy) for egress, building height, number of stories, building area, exterior wall fire rating and opening protection, and shafts (i.e. 3 stories are allowed to be open to each other) then the building can be converted to a B Occupancy without any upgrades required to those features. New work is required to comply with the 2012 IBC. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 4/22/20165/11/2016 DONE
Mailed 5-12-16
First Notice 4/8/20164/12/2016 DONE
Mailed 4-13-16
BLD-Final3/28/20163/29/20163/29/2016APASS
DetailsDave Hannah
Tom Phone #: ###-####// please call for access
Permanent Occupancy  3/29/2016 DONE
BLD-Final3/18/20163/21/20163/25/2016APEND
DetailsDave Hannah
would like call ahead; Tom Phone #: ###-#### needs zoning and fire finals and handrail
BLD-Conference3/24/20163/24/20163/25/2016ADONE
DetailsDave Hannah
would like call ahead; Tom Phone #: ###-####
FIRE-Final Inspection3/21/20163/22/20163/22/2016APASS
DetailsJim Page
No fire sprinklers, smoke detectors are stand alone and not monitored, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
Zoning Approval3/22/20163/22/20163/22/2016 DONE
DetailsMatthew A Halitsky
BLD-Foundation1/15/20161/19/20161/19/2016APASS
DetailsMike Jordan
Mike Phone #: ###-####
BLD-Footing1/13/20161/14/20161/14/2016APASS
DetailsTony Young
Zack Phone #: ###-####
Issue PAID IN FULL permit  12/9/2015 DONE
Print Occupancy Form  12/9/2015 DONE
OVERRIDE  12/7/2015  
Plan assigned to (CJW)11/3/201511/3/201512/7/2015 PASS
DetailsCarl Westfall
(1st done) JJ SHAW OFFICE (Nov 23 - 15 days) Level 3 TI - ePlanReview
Routing - Design Review12/3/2015 12/7/2015 PASS
DetailsMatthew A Halitsky
Matt Halitsky - DRH15-00263

Signed off by Carl Westfall after verifying Matt signed it off in ePlanReview.
PLANS/APPL TAKEN TO FRONT DESK  12/7/2015 DONE
Permit Ready to Issue  12/7/2015 DONE
need RP, GC and rev cert of val
Routing - FIRE12/3/2015 12/3/2015 PASS
DetailsKatie Marron
Revised report attached to case.
Routing - PLAN CHECK12/2/2015 12/3/2015 PASS
DetailsCarl Westfall
Plan resubmittals received  12/2/2015 DONE
Route to Impact Fee Review11/25/201511/28/201511/27/2015 PASS
DetailsCindy M. Gould
Routing - FIRE11/3/201511/3/201511/25/2015 FAIL
DetailsScott Arellano
Report attached to case and emailed to architect.
Routing - PLAN CHECK11/3/2015 11/25/2015 PASS
DetailsCarl Westfall
Drawings approved with redlines
1st review completed  11/25/2015 DONE
Failed historic and fire
Plan resubmittals requested  11/25/2015 DONE
Routing PW Drainage11/4/2015 11/16/2015 PASS
DetailsBrian Murphy
LESS THAN DRAINAGE REQUIRMENTS
Routing - Design Review11/3/2015 11/9/2015 FAIL
DetailsMatthew A Halitsky
Matt Halitsky - DRH15-00263
Routing - PLANNING11/3/2015 11/4/2015 PASS
DetailsDavid Moser
David Moser - CUP15-00055 & CVA15-00032
Routing - Erosion and Sediment11/3/2015 11/4/2015 PASS
DetailsEvan Jenkins
(JJ SHAW OFFICE) Remodel with a change of occupancy from a commercial Bed and Breakfast use to occupancy Group B for office space. Cottage in back on site remains residential use. Project has been approved by Historic and by Planning & Zoning for a parking reduction ADA and site improvements as well as removal of front porch windows.
Routing - Addressing11/3/2015 11/4/2015 PASS
DetailsEmily Dixon
Routing PW Street Lights11/3/2015 11/4/2015 PASS
DetailsMike D Hedge
No new street lighting required.
Routing PW Sewer Rating11/3/2015 11/4/2015 PASS
DetailsJennifer Bruner
Routing - PUBLIC WORKS11/3/2015 11/3/2015 PASS
DetailsJennifer Bruner
Plan Reviewer's activity  11/3/2015 PASS
Plan intake review approved. Drawings received 11-2-15 via ePlanReview.
Intake Approval  11/3/2015 PASS
DetailsJason Blais
Prescreen approved by Carl Westfall and plan review fees paid.
Pending Assignment by JCB11/3/2015 11/3/2015 DONE
DetailsJason Blais
Application received  10/28/2015 DONE
Application submitted via PDS Online on Oct 28 2015 5:04PM