BLD-Final | 6/10/2016 | 6/10/2016 | 6/10/2016 | P | PASS |
Phil Shearer
|
|
|
Garage code Inspection requested via web by Erby Gonzales
|
DOC - Permit Finaled | 6/10/2016 | 6/10/2016 | 6/10/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | NR |
Phil Shearer
|
|
|
Garage open for access Inspection requested via web by Erby Gonzales
|
BLD-Wall Bracing | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PASS |
Phil Shearer
|
|
|
WUI drywall at soffit inspection Inspection requested via web by Erby Gonzales
|
BLD-Energy code compliance | 3/17/2016 | 3/17/2016 | 3/17/2016 | A | PASS |
Phil Shearer
|
|
|
Floor system LVL paperwork on site Inspection requested via web by Erby Gonzales
|
BLD-Framing/Rough-in | 3/17/2016 | 3/17/2016 | 3/17/2016 | P | PASS |
Phil Shearer
|
|
|
Floor system LVL paperwork on site Inspection requested via web by Erby Gonzales
|
BLD-Energy code compliance | 3/15/2016 | 3/15/2016 | 3/15/2016 | A | NR |
Phil Shearer
|
|
|
Inspection requested via web by Erby Gonzales
|
BLD-Framing/Rough-in | 3/14/2016 | 3/14/2016 | 3/14/2016 | A | PART |
Phil Shearer
|
|
|
Plans on site Inspection requested via web by Erby Gonzales. Truss bracing, provide engineering the change from beam tofloor truss. OK to insulate
|
BLD-Conference | 2/18/2016 | 2/18/2016 | 2/18/2016 | P | PASS |
Phil Shearer
|
|
|
Shear inspection, plans on site Inspection requested via web by Erby Gonzales
|
BLD-Foundation | 1/14/2016 | 1/15/2016 | 1/15/2016 | A | PASS |
Phil Shearer
|
|
|
Sergio Phone #: ###-####
|
BLD-Footing | 1/13/2016 | 1/13/2016 | 1/13/2016 | P | PART |
Phil Shearer
|
|
|
Sergio Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/25/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/25/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/24/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 11/10/2015 | 11/10/2015 | 11/24/2015 | | DONE |
Brian McGowan
|
|
|
due 11/17 (LOMR) ePlan. 1st review passed but I failed it in ePlan to get the manual j resubmitted.
|
Routing PW Flood Plain | 11/3/2015 | | 11/24/2015 | | CANC |
Jim Wyllie
|
|
|
Map revision on file per Jim Wyllie
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2015 | | DONE |
Christina Prado
|
|
|
all requirements met
|
Routing - MECHANICAL | 11/23/2015 | | 11/23/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 11/16/2015 | | 11/16/2015 | | PASS |
David Ferguson
|
|
|
|
1st review completed | | | 11/12/2015 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/3/2015 | | 11/12/2015 | | PASS |
Brian McGowan
|
|
|
|
Plan assigned to (LEG) Tisha | 11/3/2015 | | 11/10/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 11/3/2015 | | 11/5/2015 | | FAIL |
Troy James
|
|
|
1. Need to show construction quality as semi tight.
2. ceiling height in the den doesn't match the submitted plans.
|
Routing - PLANNING | 11/3/2015 | | 11/3/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 11/3/2015 | | 11/3/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 11/3/2015 | | 11/3/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/3/2015 | | DONE |
|
|
|
|
Intake Approval | | | 11/3/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/3/2015 | | DONE |
|
|
|
|
Application received | | | 10/29/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2015 11:43AM
|