BLD-Final | 5/18/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Jim Sly
|
|
|
Clarence Phone #: ###-####
|
DOC - Permit Finaled | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | PASS |
Jim Sly
|
|
|
Clarence Phone #: ###-####
|
BLD-Framing/Rough-in | 2/5/2016 | 2/8/2016 | 2/8/2016 | P | PASS |
Jim Sly
|
|
|
Clarence Phone #: ###-####
|
Plan Modification Accepted | | | 1/20/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/20/2016 | | 1/20/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Energy code compliance | 1/7/2016 | 1/7/2016 | 1/7/2016 | P | PART |
Jim Sly
|
|
|
shear // Clarence Phone #: ###-#### Exterior shear nailing only OK.
|
BLD-Foundation | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | PASS |
Jim Sly
|
|
|
Chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/2/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/2/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/30/2015 | | |
|
|
|
|
Plan resubmittals received | | | 11/30/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/30/2015 | | 11/30/2015 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/30/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/30/2015 | | DONE |
|
|
|
all requirements met
|
Plan assigned to (LEG) Tisha | 11/13/2015 | | 11/30/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 11/23; architect sealed, need corrections
|
Routing - PLAN CHECK | 11/13/2015 | | 11/23/2015 | | FAIL |
Tisha Gallop
|
|
|
|
1st review completed | | | 11/23/2015 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 11/17/2015 | | 11/17/2015 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 11/13/2015 | | 11/17/2015 | | FAIL |
Troy James
|
|
|
emailed corrections
|
Routing - PUBLIC WORKS | 11/13/2015 | | 11/16/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 11/13/2015 | | 11/13/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 11/13/2015 | | 11/13/2015 | | PASS |
Emily Dixon
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/13/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 11/13/2015 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/13/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 11/3/2015 | | FAIL |
|
|
|
need res check and manuals
|
Application received | | | 10/29/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2015 6:07PM
|