Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-04009
StatusFinaled
Name SHY-BEE INC
Site Address 2415 N 24TH ST
Project NameBarker Garage
Customer NumberCZC16-00018
ePlanReviewYes
Description
24'x24' Footprint with 576 square foot Garage on ground level and 446 +/- square foot ADU above, 36 square foot landing/deck above with exterior staircase. Project to meet all Planning and Zoning requirements priopr to beginning. Separate electrical, plumbing permits are required. Prescriptive Energy Code is proposed with ductless heating. All work to be done according to approved plans, notes and local codes. **BJM**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/29/20167/5/20167/5/2016APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Tim Scheibe
DOC - Permit Finaled7/5/20167/5/20167/5/2016PPASS
DetailsTony Young
c of c/o issued,, placed in drawer upstairs
Letter of compliance/Occupancy  7/5/2016 DONE
BLD-Final6/29/20166/29/20166/29/2016PPEND
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Tim Scheibe
BLD-Final6/28/20166/29/20166/29/2016APART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Tim Scheibe,, ok pending plumbing finals and hand/guard rail fix
BLD-Conference6/27/20166/28/20166/28/2016PPART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Tim Scheibe,, need guardrails and handrail per code,, also needs zoning final,, walk through only
Plan assigned to (BJM)2/23/20162/23/20163/29/2016 DONE
DetailsBrian McGowan
Failed 2-24-16 No structure, elevation or details were provided.
Plan modification was canceled. No shed will be added.
CHANGE STATUS TO (ISS)  3/29/2016 DONE
Contractor called to cancel Plan modification. No shed will be added. Permit to revert to original, approved submittal. **BJM**
Routing - PLAN CHECK2/23/2016 2/24/2016 FAIL
DetailsBrian McGowan
No structure, elevation or details were provided.
BLD-Framing/Rough-in2/23/20162/23/20162/23/2016PPASS
DetailsTony Young
Tim Phone #: ###-####
Plan Modification Accepted  2/23/2016 DONE
DetailsChristina Prado
Adding 84sq ft to original proposed shed
CHANGE STATUS TO (REV)  2/23/2016 DONE
DetailsChristina Prado
Plan Mod to add sq footage to existing structure
BLD-Framing/Rough-in2/19/20162/22/20162/22/2016APART
DetailsTony Young
Tim Phone #: ###-####,, frame issues ok,, still need mech. rough in on vents,, etc.,, gas line has been approved,, ok to insulate
BLD-Framing/Rough-in2/16/20162/17/20162/17/2016PFAIL
DetailsTony Young
###-#### Tim,, c/n posted,, need to reinspect
Override - Parcel Holds  2/16/2016  
BLD-Wall Bracing1/13/20161/13/20161/13/2016PPASS
DetailsJim Sly
Tim Phone #: ###-####
BLD-Foundation12/24/201512/24/201512/28/2015PDONE
DetailsTony Young
Pat Phone #: ###-####
BLD-Footing12/23/201512/23/201512/24/2015PPART
DetailsTony Young
Pat Phone #: ###-####
Plan assigned to (BJM)11/30/201511/30/201512/14/2015 DONE
DetailsBrian McGowan
Residential Barker Garage. 1st Review Complete, Failed. Additional drawings and information required. 11-30-15
PLANS/APPL TAKEN TO FRONT DESK  12/14/2015 DONE
Permit Ready to Issue  12/14/2015 DONE
need RP
Issue PAID IN FULL permit  12/14/2015 DONE
Inspection Record Card- Bld  12/14/2015 DONE
Routing - PLAN CHECK12/11/2015 12/11/2015 PASS
DetailsTisha Gallop
per BJM
Routing - PLAN CHECK12/10/2015 12/10/2015 PASS
DetailsBrian McGowan
Routing - PUBLIC WORKS11/25/2015 12/9/2015 PASS
DetailsRachael Beierle
Routing - PLANNING11/25/2015 12/9/2015 PASS
DetailsSusan Riggs
Provide a minimum 5' deep concrete apron at 18' Garage door.

The required parking pad located on the south side of the ADU/garage, shall consist of wheel strips, pavers, asphalt or concrete. Wheel strips shall be a minimum of 24" in width. Pavement and/or wheel strips shall extend to the alley way.

Maintain a 3'-0" landscape strip between
Routing - Addressing12/8/2015 12/8/2015 PASS
DetailsLaura Hunter
Plan assigned to (JG)11/25/201511/25/201511/30/2015 DEFR
DetailsBrian McGowan
Residential Barker Garage
Routing - PLAN CHECK11/25/2015 11/30/2015 FAIL
DetailsBrian McGowan
Additional information and drawings required.
1st review completed  11/30/2015 FAIL
DetailsBrian McGowan
Additional information and drawings required.
Route to Impact Fee Review11/25/201511/28/201511/27/2015 PASS
DetailsCindy M. Gould
Routing - MECHANICAL11/25/2015 11/27/2015 PASS
DetailsTroy James
Ductless wall unit. Manual j report not required.
Routing - Addressing11/25/2015 11/25/2015 FAIL
DetailsLaura Hunter
Needs a PW address request form for additional address
Intake Approval  11/25/2015 PASS
Application received  10/30/2015 DONE
Application submitted via PDS Online on Oct 30 2015 7:43AM
Intake Approval  10/30/2015 FAIL
Needs Planning & Zoning approval before submittal
Routing - PUBLIC WORKS     
Be sure and route to PW for additional fees. bam This is an ADU
Routing - PLANNING2/23/2016    
DetailsSusan Riggs