Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-04057
StatusFinaled
Name IDAHO TOWER CONSTRUCTION CO
Site Address 2940 S VICTORY VIEW WAY
Project NameAT&T Manpole Cell Tower
Customer Number 
ePlanReviewNo
Description
(AT&T MANPOLE CELL TOWER – Victory & Five Mile) Permit for the modifications to the existing manpole cell tower with work to include installation of (3) new antennas one per each sector, (3) new RRH antennas, (2) new BCEM Cards, (4) SFP’s inside the existing cabinet, (2) new battery strings inside BBU, (3) 15 amp breakers for one each RRH, and (2) new converters inside existing DC power plant. No changes to the height of the tower. Structural engineering and plans provided. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice3/11/20163/11/20164/16/2019 DONE
DetailsJim Storey
This permit finaled on the web by Dwayne Robinson
BLD-Final3/10/20163/10/20163/11/2016PPASS
DetailsJim Storey
Call for access Phone #: 2082842822 >> Inspection requested via mobile web by Matt Booth
DOC - Permit Finaled3/11/20163/11/20163/11/2016PPASS
DetailsJim Storey
Issue PAID IN FULL permit  11/23/2015 DONE
Inspection Record Card- Bld  11/23/2015 DONE
Plan assigned to (JG)11/6/201511/6/201511/9/2015 PASS
DetailsJavier Guzman
11/12 L1 AT&T Cell Tower
Routing - PLAN CHECK  11/9/2015 PASS
DetailsJavier Guzman
1st review completed  11/9/2015 DONE
DetailsJavier Guzman
Case Summary (BLD)  11/9/2015 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  11/9/2015 DONE
Inspection Record Card- Bld  11/9/2015 DONE
Permit Ready to Issue  11/9/2015 DONE
requirements met
Telephone call  11/9/2015 DONE
called Steven- told him permit is ready for pick up and fees due- requested email- sent email
Routing - FIRE11/6/201511/6/201511/6/2015 PASS
DetailsKatie Marron
No comments
Routing - PLANNING11/6/2015 11/6/2015 PASS
DetailsLeon Letson
CAA15-00227
Plans ACCEPTED BY PLAN TECH  11/6/2015 DONE
Intake Approval  11/6/2015 PASS
as per Javier Guzman
Recd Pcfee & Taken To Pln CK  11/6/2015 DONE
Application received 11/4/2015