FIRE-Final Inspection | 2/1/2016 | 2/2/2016 | 2/2/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 2/1/2016 | 2/2/2016 | 2/2/2016 | A | PASS |
Mike Jordan
|
|
|
Julio Phone #: ###-####. Ok for perm occ. No plumbing or mech. permits are required.
|
BLD-Final | 1/29/2016 | 2/1/2016 | 2/1/2016 | P | NR |
Mike Jordan
|
|
|
Julio Phone #: ###-####. Fire/life/safety failed.
|
FIRE-Final Inspection | 1/29/2016 | 2/1/2016 | 2/1/2016 | A | FAIL |
Troy Cobbley
|
|
|
Repair the existing emergency lighting and provide additional emergency lighting in the west office area.
|
BLD-Framing/Rough-in | 1/4/2016 | 1/5/2016 | 1/5/2016 | A | PASS |
Mike Jordan
|
|
|
Julio Phone #: ###-####
|
BLD-Framing/Rough-in | 12/8/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Interior steel stud framed walls for new offices and breakroom only ok.
|
BLD-Framing/Rough-in | 12/7/2015 | 12/8/2015 | 12/8/2015 | P | NR |
Mike Jordan
|
|
|
Julao Phone #: ###-####.. Needs electrical rough in inspection.
|
Issue PAID IN FULL permit | | | 11/19/2015 | | DONE |
|
|
|
|
Plan assigned to (JG) | 11/5/2015 | 11/5/2015 | 11/16/2015 | | PASS |
Javier Guzman
|
|
|
11/18 L2 CBIZ M&S CONSULTING SERVICE, LLC TI
|
Routing - PLAN CHECK | 11/5/2015 | | 11/16/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 11/12/2015 | | 11/16/2015 | | PASS |
Jennifer Bruner
|
|
|
approved per Review Sheet by Bev Mountain
|
1st review completed | | | 11/16/2015 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 11/16/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/16/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/16/2015 | | DONE |
|
|
|
need GC and Rev Cert of Val
|
Telephone call | | | 11/16/2015 | | DONE |
Christina Prado
|
|
|
Called Architect to advise review is complete and we need GC & revised cert of value for issuance
|
Routing - Addressing | 11/6/2015 | | 11/12/2015 | | PASS |
Jason C. Taylor
|
|
|
New suites added. JCT
|
Routing - Addressing | 11/5/2015 | | 11/6/2015 | | FAIL |
Jason C. Taylor
|
|
|
Cannot verify addresses. Requested suite map for building from architect. JCT
|
Routing - PUBLIC WORKS | 11/6/2015 | | 11/6/2015 | | FAIL |
Jennifer Bruner
|
|
|
Please see ADDRESSING
|
Plans ACCEPTED BY PLAN TECH | | | 11/5/2015 | | DONE |
|
|
|
|
Intake Approval | | | 11/5/2015 | | PASS |
Javier Guzman
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/5/2015 | | DONE |
|
|
|
|
Application received | | 11/5/2015 | | | |
|
|
|
|