Third Notice | | 9/26/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Third Notice | | 8/15/2017 | 9/21/2017 | | DONE |
|
|
|
Mailed 9/22
|
Third Notice | | 7/17/2017 | 8/10/2017 | | DONE |
|
|
|
Mailed 8-11-17
|
Third Notice | | 6/17/2017 | 7/12/2017 | | DONE |
|
|
|
Mailed 7-13-17
|
Second Notice | | 5/20/2017 | 6/12/2017 | | DONE |
|
|
|
Mailed 6-13-17
|
First Notice | | 4/16/2017 | 5/10/2017 | | DONE |
|
|
|
Mailed 5-11
|
BLD-Final | 4/5/2017 | 4/6/2017 | 4/6/2017 | P | PASS |
Jim Sly
|
|
|
David Phone #: ###-#### OK for Perm Occ.
|
Zoning Approval | 4/6/2017 | 4/6/2017 | 4/6/2017 | | DONE |
Andrea Tuning
|
|
|
|
Permanent Occupancy | | | 4/6/2017 | | DONE |
Christina Prado
|
|
|
|
Temporary Occupancy | 3/8/2017 | 6/6/2017 | 3/8/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Final | 3/1/2017 | 3/2/2017 | 3/2/2017 | A | PART |
Jim Sly
|
|
|
David Phone #: ###-#### OK for Temp Occ. OK for Perm Occ when Zoning signs off for Perm Occ.
|
BLD-Final | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | NR |
Jim Sly
|
|
|
David Phone #: ###-#### Need Public Works.
|
PubWorks Occupancy Approval | 3/1/2017 | 3/1/2017 | 3/1/2017 | | DONE |
Tiffany Lowery
|
|
|
|
OVERRIDE | | | 2/28/2017 | | |
|
|
|
|
Zoning Approval Temp | 2/28/2017 | 2/28/2017 | 2/28/2017 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH15-00317 with bond in place for asphalt, landscape, hydroseed and bike racks.
|
Permit Ready to Issue | | | 2/28/2017 | | DONE |
|
|
|
please do not RE ISSUE
|
(F) Reprint permit | | | 2/28/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/28/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/24/2017 | 2/27/2017 | 2/27/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Documentation was provided where the fire dept approved the new fire hydrant location. Plan modifications have been submitted to get the deletion of the north door approved. I let the contractor know that the door hardware on the south/rear exit door is to be single action and will be verified by the building inspector.
|
Plan assigned to (CDM) | 2/27/2017 | 2/27/2017 | 2/27/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/27/2017 | | 2/27/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Design Review | 2/27/2017 | | 2/27/2017 | | PASS |
Katelyn Menuge
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2017 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 2/27/2017 | | DONE |
|
|
|
took in plan mod app-scanned and uploaded to e plan review-assigned to Carl M
|
FIRE-Final Inspection | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for the fire extinguishers and lower to less than 5', provide documentation for fire hydrant location approval, provide documentation for deletion of north facing exit door, mount missing exit sign and then test all exit signs and emergency lights.
|
BLD-Ceiling Grid Inspection | 2/1/2017 | 2/2/2017 | 2/1/2017 | A | PASS |
Jim Sly
|
|
|
David Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/30/2017 | 1/30/2017 | 1/30/2017 | P | PASS |
Jim Sly
|
|
|
Acoustic ceiling, please call ahead to meet on-site - David Phone #: ###-####
|
BLD-Energy code compliance | 10/24/2016 | 10/25/2016 | 10/25/2016 | A | PASS |
Jim Sly
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 10/12/2016 | 10/12/2016 | 10/12/2016 | P | PART |
Jim Sly
|
|
|
Jason Phone #: ###-#### C/N.........Arch to resubmit for approval.....Omit North Exterior door and install window. Fireblock interconnections between Vertical and Horizontal spaces. Mech needs to sign off floor dampers. OK to insulate walls only.
|
BLD-Conference | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | DONE |
Jim Sly
|
|
|
David Phone #: ###-####
|
BLD-Concrete | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | PASS |
Jim Sly
|
|
|
Steam wall // David Phone #: ###-#### OK pending MTIspecial insp, tests and approvals.
|
BLD-Footing | 5/3/2016 | 5/4/2016 | 5/4/2016 | A | PART |
Jim Sly
|
|
|
David Phone #: ###-#### Crawl footing OK pending MTI special insp, tests and approvals.
|
BLD-Other | 4/27/2016 | 4/27/2016 | 4/27/2016 | P | PART |
Jim Sly
|
|
|
davis - basement wall Phone #: ###-#### Basement wall OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 4/22/2016 | 4/25/2016 | 4/25/2016 | A | PART |
Jim Sly
|
|
|
David Phone #: ###-#### Basement footing only......OK pending MTI special inspections, tests and approvals.
|
BLD-Footing | 4/21/2016 | 4/22/2016 | 4/22/2016 | A | CANC |
Jim Sly
|
|
|
David Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/1/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/1/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/14/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 11/30/2015 | 11/30/2015 | 3/14/2016 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2016 | | DONE |
|
|
|
|
Routing - PLANNING | 3/14/2016 | | 3/14/2016 | | PASS |
Leon Letson
|
|
|
|
Permit Ready to Issue | | | 3/14/2016 | | DONE |
Christina Prado
|
|
|
Need ACHD, RP, GC Form & Revised Certificate of Value for issuance/// ONLY NEEDS ACHD as of 3-29-16 KRS- revised certificate of value is not needed GC was the applicant
|
Routing - PLAN CHECK | 3/2/2016 | | 3/14/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 3/2/2016 | | 3/14/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 3/2/2016 | | 3/10/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2016 | | 3/2/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLAN CHECK | 2/16/2016 | | 2/25/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 2/17/2016 | | 2/24/2016 | | PASS |
Rick Christenson
|
|
|
Must Complete Environmental Dental Application. Contact Brett Morrison @ ###-####
|
Routing PW Sewer Design | 2/24/2016 | | 2/24/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Update Site Plan per requirements of Mike Sheppard in Public Works in conjunction with the record of survey.
|
Routing - FIRE | 2/16/2016 | 2/16/2016 | 2/17/2016 | | PASS |
Scott Arellano
|
|
|
Revised report attached to case.
|
Routing - PUBLIC WORKS | 2/16/2016 | | 2/17/2016 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 1/6/2016 | 1/9/2016 | 1/7/2016 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 1/6/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/30/2015 | | 1/6/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 11/30/2015 | | 1/6/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 12/9/2015 | | 12/9/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Show or provide utility easement in favor of 4809 Fairview for the portion of the sewer service that crosses that property.
|
Routing PW Drainage | 12/7/2015 | | 12/7/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING Land Div | 11/30/2015 | | 12/3/2015 | | FAIL |
Leon Letson
|
|
|
Pending recording of Property Line Adjustment (ROS15-00102),
|
Routing - PLUMBING | 11/30/2015 | | 12/2/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing PW Solid Waste | 12/2/2015 | | 12/2/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - FIRE | 11/30/2015 | 11/30/2015 | 12/1/2015 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect
|
Routing PW Street Lights | 12/1/2015 | | 12/1/2015 | | PASS |
Mike D Hedge
|
|
|
No new street lighting required.
|
Routing - Addressing | 11/30/2015 | | 12/1/2015 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/30/2015 | | 12/1/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 11/30/2015 | | 12/1/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
(BREWSTER DENTAL) Construct new 3,875 square foot dental office.
|
Routing - MECHANICAL | 11/30/2015 | | 12/1/2015 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 11/30/2015 | | 12/1/2015 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 11/30/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 11/30/2015 | | 11/30/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 11/9/2015 | | FAIL |
Javier Guzman
|
|
|
Please provide the following (Incomplete submittals will not be accepted):
• Form #304 – Registered Design Professional
• Form #310 – Statement of Special Inspections must be completed by the design engineer for items listed in plan sheet S0.0
• Structural plan sheet must be uploaded as individual sheets not as a packet
• Stair details showing tread and riser requirements
|
Application received | | | 11/5/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 5 2015 3:33PM
|