BLD-Final | 6/28/2016 | 7/1/2016 | 7/1/2016 | A | FAIL |
Phil Shearer
|
|
|
Cameron Phone #: ###-####. Need Zoning sign off
|
BLD-Energy code compliance | 2/11/2016 | 2/12/2016 | 2/12/2016 | A | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 1/29/2016 | 1/29/2016 | 1/29/2016 | P | PART |
Tony Young
|
|
|
Matt Phone #: ###-####,, need mechanical 1st,, then ok to insulate,, need fire blocks,, need seal package
|
BLD-Footing | 11/30/2015 | 12/1/2015 | 12/1/2015 | P | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####,, insulation and ftg trench ok
|
BLD-Footing | 11/18/2015 | 11/19/2015 | 11/19/2015 | A | PART |
Dave Hannah
|
|
|
Matt Phone #: ###-####ok to pour frost wall
|
Issue PAID IN FULL permit | | | 11/13/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 11/12/2015 | | |
|
|
|
|
Routing Walk-In (Zoning) | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 11/12/2015 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/12/2015 | | 11/12/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 11/12/2015 | | 11/12/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
Case Summary (BLD) | | | 11/12/2015 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 11/12/2015 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/12/2015 | | DONE |
|
|
|
CON15-00268 NEEDS TO BE ISSUED AND FEE PAID FOR THE ESC ON THIS PROJECT
|
Zoning Approval | 8/9/2016 | 8/9/2016 | | | FAIL |
|
|
|
Vinyl, sliding windows are not allowed per certificate of appropriateness conditions of approval.
|
Application received | | 11/12/2015 | | | |
|
|
|
|