PubWorks Occupancy Approval | 9/11/2017 | 9/11/2017 | 9/11/2017 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 9/8/2017 | 9/8/2017 | 9/8/2017 | P | PASS |
Dave Hannah
|
|
|
for perm occ
|
Permanent Occupancy | | | 9/8/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/7/2017 | 9/7/2017 | 9/7/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspections complete, fire alarm inspections complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Final | 9/5/2017 | 9/6/2017 | 9/7/2017 | P | PART |
Dave Hannah
|
|
|
until 203// Amy Phone #: ###-#### ok for temp occ
|
BLD-Aging Inspection | 8/25/2017 | 8/25/2017 | 8/31/2017 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | PART |
Dave Hannah
|
|
|
Jason Phone #: ###-#### 201and 202 ok for temp occ
|
Zoning Approval | 8/14/2017 | 8/14/2017 | 8/14/2017 | | DONE |
Andrea Tuning
|
|
|
|
Fees Due Hold | 6/21/2017 | | 8/14/2017 | | DONE |
Christina Prado
|
|
|
|
Temporary Occupancy | 6/20/2017 | 9/18/2017 | 6/20/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 6/17/2017 | | 6/20/2017 | | DONE |
Rita DeYoung
|
|
|
|
BLD-Final | 6/16/2017 | 6/19/2017 | 6/19/2017 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Final | 6/15/2017 | 6/16/2017 | 6/16/2017 | P | PART |
Dave Hannah
|
|
|
Amy Phone #: ###-#### ok for temp occ needs to finish units 111 12 113 and 211 12 213
|
FIRE-Final Inspection | 6/16/2017 | 6/16/2017 | 6/16/2017 | P | PART |
Jim Page
|
|
|
Life fire safety inspection complete for TCO requested area's (Main builing, living area's for live/work units, parking levels 1 and 2, lobby area's for levels 1 and 2 condo units and common area's for levels 3, 4, 5 and 6. Townhomes are not part of the TCO, townhome life fire safety inspection to be completed at a later date). Fire alarm inspection complete for TCO area's (monitoring verified, monitoring to be active at end of business day 16JUNE2017, all occupied TCO area's to be actively monitored at end of work day after 16JUNE2017, fire alarm system cannot be placed out of servicefor more than work day hours) fire sprinkler inspection complete for TCO area's, active fire sprinkler protection for entire building to include townhomes, fire extinguishers in place with current inspection tags for TCO area's, knox box is in place by main entry on river street side of building.
|
BLD-Conference | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | PASS |
Dave Hannah
|
|
|
Amy Phone #: ###-####
|
Fees Due Hold | 6/16/2017 | | 6/16/2017 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 6/15/2017 | | 6/15/2017 | | DONE |
Brittany Hill
|
|
|
|
Zoning Approval Temp | 6/14/2017 | 6/14/2017 | 6/14/2017 | | DONE |
Andrea Tuning
|
|
|
|
Fees Due Hold | 6/6/2017 | | 6/14/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Other | 6/5/2017 | 6/6/2017 | 6/6/2017 | A | DONE |
Dave Hannah
|
|
|
Review documentation from MTI Phone #: ###-#### Inspection requested via web by Ami Tracy
|
Fees Due Hold | 6/3/2017 | | 6/5/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Other | 6/1/2017 | 6/2/2017 | 6/2/2017 | P | DONE |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ami Tracy
|
Fees Due Hold | 6/2/2017 | | 6/2/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Conference | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ami Tracy
|
Fees Due Hold | 6/1/2017 | | 6/1/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/31/2017 | | 5/31/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/25/2017 | | 5/30/2017 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 5/24/2017 | | 5/24/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/20/2017 | | 5/23/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/19/2017 | | 5/19/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/18/2017 | | 5/18/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/17/2017 | | 5/17/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/16/2017 | | 5/16/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Energy code compliance | 5/12/2017 | 5/15/2017 | 5/15/2017 | A | PASS |
Dave Hannah
|
|
|
Garden Shed on 3rd Floor Patio Phone #: ###-#### Inspection requested via web by Ami Tracy
|
Fees Due Hold | 5/13/2017 | | 5/15/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/12/2017 | | 5/12/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/11/2017 | | 5/11/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/10/2017 | | 5/10/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/6/2017 | | 5/9/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/5/2017 | | 5/5/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/4/2017 | | 5/4/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/3/2017 | | 5/3/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 5/2/2017 | | 5/2/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/29/2017 | | 5/1/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/28/2017 | | 4/28/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/27/2017 | | 4/27/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/26/2017 | | 4/26/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/25/2017 | | 4/25/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/22/2017 | | 4/24/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/21/2017 | | 4/21/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/20/2017 | | 4/20/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/19/2017 | | 4/19/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/18/2017 | | 4/18/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/15/2017 | | 4/17/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/13/2017 | | 4/14/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Conference | 4/11/2017 | 4/12/2017 | 4/12/2017 | A | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ami Tracy Inspection cancelled from web by: Ami Tracy
|
Fees Due Hold | 4/12/2017 | | 4/12/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/11/2017 | | 4/11/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/8/2017 | | 4/10/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/7/2017 | | 4/7/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/6/2017 | | 4/6/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/5/2017 | | 4/5/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/4/2017 | | 4/4/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 4/1/2017 | | 4/3/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/31/2017 | | 3/31/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/30/2017 | | 3/30/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/29/2017 | | 3/29/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/28/2017 | | 3/28/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/25/2017 | | 3/27/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/24/2017 | | 3/24/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/23/2017 | | 3/23/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/22/2017 | | 3/22/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/21/2017 | | 3/21/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/18/2017 | | 3/20/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/17/2017 | | 3/17/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/16/2017 | | 3/16/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/15/2017 | | 3/15/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/14/2017 | | 3/14/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/11/2017 | | 3/13/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/10/2017 | | 3/10/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Energy code compliance | 3/8/2017 | 3/9/2017 | 3/9/2017 | A | PASS |
Dave Hannah
|
|
|
6th Floor Fire Proofing Phone #: ###-#### Inspection requested via web by Ami Tracy
|
Fees Due Hold | 3/9/2017 | | 3/9/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/8/2017 | | 3/8/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/7/2017 | | 3/7/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/3/2017 | | 3/6/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Energy code compliance | 3/2/2017 | 3/3/2017 | 3/3/2017 | A | CANC |
Dave Hannah
|
|
|
6th Floor Phone #: ###-#### Inspection requested via web by Ami Tracy
|
Fees Due Hold | 3/2/2017 | | 3/2/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 3/1/2017 | | 3/1/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 2/28/2017 | | 2/28/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 2/25/2017 | | 2/27/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 2/24/2017 | | 2/24/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 2/23/2017 | | 2/23/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 2/22/2017 | | 2/22/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 2/18/2017 | | 2/21/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Energy code compliance | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | PART |
Jim Sly
|
|
|
First floor town homes Phone #: ###-#### Inspection requested via web by Ami Tracy Units 111, 112, 113.
|
Fees Due Hold | 2/17/2017 | | 2/17/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 2/16/2017 | | 2/16/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Framing/Rough-in | 1/18/2017 | 1/19/2017 | 1/20/2017 | A | PART |
Dave Hannah
|
|
|
Level 2 Framing Phone #: ###-#### Inspection requested via web by Ami Tracy ok to one side last two areas
|
Fees Due Hold | 1/19/2017 | | 1/19/2017 | | DONE |
Brittany Hill
|
|
|
|
BLD-Energy code compliance | 1/10/2017 | 1/11/2017 | 1/11/2017 | A | PASS |
Dave Hannah
|
|
|
Elevator Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Framing/Rough-in | 12/16/2016 | 12/19/2016 | 12/19/2016 | A | PASS |
Dave Hannah
|
|
|
5th Floor framing Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Wall cover | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | DEFR |
Jim Storey
|
|
|
5th Floor Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Conference | 12/5/2016 | 12/6/2016 | 12/6/2016 | A | PART |
Dave Hannah
|
|
|
6th Floor Framing Phone #: ###-#### Inspection requested via web by Ami Tracy ok to insulate
|
BLD-Framing/Rough-in | 11/22/2016 | 11/28/2016 | 11/28/2016 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Framing/Rough-in | 11/21/2016 | 11/22/2016 | 11/22/2016 | A | PASS |
Dave Hannah
|
|
|
Framing Inspection Phone #: ###-#### Inspection requested via web by Ami Tracy first second floors ok to one side int walls and cover ext walls 4orth floor ok to cover walls
|
BLD-Framing/Rough-in | 11/16/2016 | 11/17/2016 | 11/21/2016 | A | PASS |
Dave Hannah
|
|
|
Level 4 Insulation Phone #: ###-#### Inspection requested via web by Ami Tracy
|
Fees Due Hold | 11/16/2016 | | 11/16/2016 | | DONE |
Rita DeYoung
|
|
|
working with applicant to pay fees
|
OVERRIDE | | | 11/15/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 11/8/2016 | 11/8/2016 | 11/15/2016 | | PASS |
Carl Westfall
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/15/2016 | | DONE |
Rita DeYoung
|
|
|
Plan Mod. on eplan
|
Routing PW Sewer Design | 11/9/2016 | | 11/15/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PLUMBING | 11/9/2016 | | 11/15/2016 | | PASS |
Bill VanDegrift
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/15/2016 | | DONE |
|
|
|
DO NOT RE-ISSUE-- PLAN MOD ONLY
|
Routing - PLAN CHECK | 11/9/2016 | | 11/9/2016 | | PASS |
Carl Westfall
|
|
|
|
Plan Modification Accepted | | | 11/8/2016 | | DONE |
|
|
|
Plan Mod as requested by Architecture firm
|
Fees Due Hold | 10/21/2016 | | 10/21/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 10/20/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 9/23/2016 | 9/23/2016 | 10/20/2016 | | PASS |
Carl Westfall
|
|
|
Afton plan mod
|
CHANGE STATUS TO (ISS) | | | 10/20/2016 | | DONE |
|
|
|
plan mod ONLY - okay to issue / check with Rita DeYoung for info
|
Routing PW Sewer Rating | 10/19/2016 | | 10/20/2016 | | PASS |
Rachael Beierle
|
|
|
rated per unit not fixtures. no change in permit fee.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/20/2016 | | DONE |
|
|
|
plan mod ONLY - check with Rita DeYoung for more info
|
Routing - PLAN CHECK | 10/18/2016 | | 10/19/2016 | | PASS |
Carl Westfall
|
|
|
1st plan mod approved
|
Plan resubmittals received | | | 10/18/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/26/2016 | | 9/28/2016 | | FAIL |
Carl Westfall
|
|
|
See changemarks on the drawings. Need enlarged floor plans, elevations, etc. for Unit 112 (Type A) and for Unit 304 (Type B).
|
Plan resubmittals requested | | | 9/28/2016 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 9/23/2016 | | DONE |
Christina Prado
|
|
|
Revise floor plan of unit #304
|
Issue PAID IN FULL permit | | | 3/11/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/11/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/1/2016 | | |
|
|
|
|
Routing - PLAN CHECK | 2/29/2016 | | 3/1/2016 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/1/2016 | | DONE |
Christina Prado
|
|
|
**MET** Need ACHD ***MET 3-2-16*** RP, GC Form & Revised Certificate of value for issuance
|
Plan assigned to (CJW) | 11/19/2015 | | 3/1/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) THE AFTON (Dec 29 - 30 days) (ePlanReview)
|
Plan resubmittals requested | | | 2/29/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/29/2016 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/23/2016 | | 2/26/2016 | | PASS |
Carl Westfall
|
|
|
CH2MHill Jared Bauder
|
Routing - MECHANICAL | 2/23/2016 | | 2/24/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 2/19/2016 | | 2/23/2016 | | FAIL |
Carl Westfall
|
|
|
Two items not resolved.
|
Plan resubmittals received | | | 2/19/2016 | | DONE |
|
|
|
Resubmittal received on Friday, Feb. 19. Some drawings did not version right. After fixing the problem the routing was started on the following Tuesday, Feb. 23.
|
Plan resubmittals requested | | | 2/11/2016 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/3/2016 | | 2/11/2016 | | FAIL |
Carl Westfall
|
|
|
CH2MHill Jared Bauder
|
Routing - MECHANICAL | 2/3/2016 | | 2/9/2016 | | FAIL |
Troy James
|
|
|
Talked to mechanical engineer
|
Routing - PLUMBING | 2/3/2016 | | 2/5/2016 | | PASS |
Bill VanDegrift
|
|
|
Move redlines
asse 1070 mixing valve required at public lavs
|
Routing PW Street Lights | 2/3/2016 | | 2/4/2016 | | PASS |
Mike D Hedge
|
|
|
|
Routing - FIRE | 2/3/2016 | | 2/4/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing - PLAN CHECK | 1/28/2016 | | 2/4/2016 | | FAIL |
Carl Westfall
|
|
|
Some items still need to be resolved
|
Routing - Erosion and Sediment | 2/3/2016 | | 2/3/2016 | | PASS |
Evan Jenkins
|
|
|
Please see ESC15-01184 for ESC Conditions/Approval
|
Plan resubmittals received | | | 1/28/2016 | | DONE |
Carl Westfall
|
|
|
Plans Examiner out of town on the 28 and 29. The 30th was Saturday and the 31st was Sunday. More than 200 sheets were revised and many were not named correctly. Took some time to get them ready for routing.
|
Route to Impact Fee Review | 12/29/2015 | 1/1/2016 | 12/30/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 12/29/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 12/29/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/19/2015 | | 12/29/2015 | | FAIL |
Carl Westfall
|
|
|
Please see the plan review report
|
Routing PW Street Lights | 12/17/2015 | | 12/17/2015 | | FAIL |
Mike D Hedge
|
|
|
|
Routing PW Environmental | 11/20/2015 | | 12/14/2015 | | PASS |
Rick Christenson
|
|
|
Future food establishments must verify connection to 1500 gallon grease interceptor.
|
Routing - MECHANICAL | 11/19/2015 | | 12/3/2015 | | FAIL |
Troy James
|
|
|
|
Routing Off Site - STRUCTURAL | 11/19/2015 | | 11/30/2015 | | FAIL |
Carl Westfall
|
|
|
CH2MHill - Jared Bauder
|
Routing - Design Review | 11/19/2015 | | 11/25/2015 | | PASS |
Josh Wilson
|
|
|
Ok per Modification filed under DRH15-00459.
|
Routing - PLUMBING | 11/19/2015 | | 11/25/2015 | | PASS |
Daryl Spivey
|
|
|
1) lav mixing valve must be ASSE 1070 listed
2) WC-1 and WC-2 are tank type toilets
|
Routing PW Sewer Rating | 11/20/2015 | | 11/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - FIRE | 11/19/2015 | 11/19/2015 | 11/20/2015 | | FAIL |
Katie Marron
|
|
|
Comments attached to case and emailed to architect.
|
Routing - PLANNING Land Div | 11/19/2015 | | 11/20/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 11/19/2015 | | 11/20/2015 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/19/2015 | | 11/20/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 11/19/2015 | | 11/20/2015 | | FAIL |
Evan Jenkins
|
|
|
Erosion and Sediment Control Plan and Site Map Required For Approval.
Evan Jenkins 794.3958
|
Pending Assignment by TLW | 11/19/2015 | | 11/19/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 11/18/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Plan Reviewer's activity | | | 11/17/2015 | | DONE |
Javier Guzman
|
|
|
engineering is missing signiture on stamp Angela B said ok to take in and approve, she said (If the structural sheets are ok and it is just the calcs that need the signature I would go ahead and take it in. We should be able to easily get that and get it uploaded.)
|
Application received | | | 11/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 16 2015 1:28PM
|