DOC - Permit Finaled | | | 9/19/2017 | | DONE |
|
|
|
|
BLD-Final | 8/17/2017 | 8/17/2017 | 8/22/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 6/16/2016 | 6/17/2016 | 6/17/2016 | A | PASS |
Dave Hannah
|
|
|
Inspection request for wood blocking in units. Phone #: ###-#### Inspection requested via web by Carl Benjamin talked about backing in walls
|
BLD-Conference | 6/8/2016 | 6/9/2016 | 6/9/2016 | A | PASS |
Dave Hannah
|
|
|
Myrtle Tower 4th floor deck inspection. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Conference | 6/6/2016 | 6/7/2016 | 6/7/2016 | A | PASS |
Dave Hannah
|
|
|
Capitol Tower 4th floor decking Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Other | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PASS |
Dave Hannah
|
|
|
Podium Deck Penetration 3hr Fireproofing. Discuss Cementious Fireproofing at floors 3 thru 6. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Framing/Rough-in | 5/17/2016 | 5/18/2016 | 5/18/2016 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Concrete | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | PEND |
Dave Hannah
|
|
|
Myrtle 3rd floor deck inspection request. Phone #: ###-#### Inspection requested via web by Carl Benjamin ok after spec sign off
|
BLD-Other | 4/18/2016 | 4/19/2016 | 4/20/2016 | A | PASS |
Dave Hannah
|
|
|
3rd Floor Metal Deck inspection. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Foundation | 2/24/2016 | 2/25/2016 | 2/26/2016 | P | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
Issue PAID IN FULL permit | | | 2/16/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/16/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 2/10/2016 | | |
|
|
|
|
Plan resubmittals received | | | 2/10/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/10/2016 | | 2/10/2016 | | PASS |
Tim L. Woodard
|
|
|
Approved latest resubmittals. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/10/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan assigned to (TLW) | 11/30/2015 | | 2/10/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/26/2016 | | 1/29/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Route to Impact Fee Review | 1/26/2016 | 1/29/2016 | 1/26/2016 | | PASS |
Stephanie Jensen
|
|
|
|
Routing - Design Review | 11/30/2015 | | 1/26/2016 | | PASS |
Sarah Schafer
|
|
|
Approved in E-Plan Review.
|
Plan resubmittals received | | | 1/26/2016 | | DONE |
Tim L. Woodard
|
|
|
Recieved in e-plan. TLW
|
Routing Off Site - STRUCTURAL | 1/19/2016 | | 1/19/2016 | | PASS |
Angela Brosious
|
|
|
Structural resubmittals approved by Jared Bauder with CH2M.
|
1st review completed | | | 12/24/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 11/30/2015 | | 12/24/2015 | | FAIL |
Tim L. Woodard
|
|
|
Corrections in e-plan review. TLW
|
Routing Off Site - STRUCTURAL | 11/30/2015 | | 12/9/2015 | | FAIL |
Tim L. Woodard
|
|
|
Corrections in eplan and emailed to architect. TLW
|
Routing - FIRE | 11/30/2015 | 11/30/2015 | 12/8/2015 | | PASS |
Katie Marron
|
|
|
Report attached to case.
|
Routing - MECHANICAL | 11/30/2015 | | 12/4/2015 | | PASS |
Troy James
|
|
|
No mechanical to review
|
Routing - PLUMBING | 11/30/2015 | | 12/2/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING Land Div | 11/30/2015 | | 12/2/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Solid Waste | 12/2/2015 | | 12/2/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing PW Street Lights | 12/2/2015 | | 12/2/2015 | | PASS |
Mike D Hedge
|
|
|
Street lighting to follow in next permit.
|
Routing PW Drainage | 12/1/2015 | | 12/1/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 11/30/2015 | | 12/1/2015 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 11/30/2015 | | 12/1/2015 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 11/30/2015 | | 12/1/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
**Project Management-Angie Brosious**This permit is for construction of the cold dark shell and core for a new six story 90,000 s.f. boutique hotel. Work to be performed under this permit include construction of exterior skin and all structural bearing components.
|
Intake Approval | | | 11/30/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 11/30/2015 | | 11/30/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 11/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 18 2015 2:56PM
|