Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-04208
StatusIssued
Name IRISH QUALITY BUILDERS
Site Address 817 E BANNOCK ST
Project Name 
Customer NumberDRH15-00345
ePlanReviewNo
Description
Proposed addition of a basement and main level floor on both sides of an existing home. 1912 square feet of basement and 1982 square feet of main level for 3894 total square feet of living space added to an existing single level home of 1953 square feet (5847 total square feet). Home is in Historic District. Existing Kitchen is to be removed. New Kitchen, 2 Living rooms, dining, 3 bedrooms, 1 and 1/2 baths, fitness, recreation and storage rooms to be added. Prescriptive Energy Code is proposed on plans. A new detached 550 square foot garage with alley access is proposed. Separate electrical, mechanical, plumbing and erosion permits are required. All work is to be done according to notes, plans, engineering, Planning and Development and local codes. **BJM**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection8/2/20168/2/20168/5/2016 PEND
DetailsDave Hannah
BLD-Aging Inspection8/3/20168/3/20168/5/2016 PEND
DetailsDave Hannah
BLD-Energy code compliance3/21/20163/21/20163/21/2016PPASS
DetailsDave Hannah
Brett Phone #: ###-####
BLD-Framing/Rough-in3/14/20163/15/20163/17/2016PPASS
DetailsDave Hannah
Brad Phone #: ###-####
BLD-Framing/Rough-in3/16/20163/16/20163/16/2016PPASS
DetailsDave Hannah
early as poss this afternoon// Brett Phone #: ###-####
Plan Modification Accepted  3/1/2016 DONE
new manual j report
Routing - MECHANICAL3/1/2016 3/1/2016 PASS
DetailsTroy James
resubmitted manual j report
BLD-Foundation2/18/20162/19/20162/19/2016PPASS
DetailsDave Hannah
Eric Phone #: ###-####
BLD-Footing2/17/20162/18/20162/18/2016APASS
DetailsDave Hannah
Eric Phone #: ###-####
BLD-Wall Bracing2/16/20162/16/20162/18/2016PPART
DetailsDave Hannah
Brett Phone #: ###-#### eastside building ok to cover ext
BLD-Foundation1/29/20162/1/20162/1/2016APASS
DetailsDave Hannah
Eric Phone #: ###-####
BLD-Conference1/28/20161/29/20161/29/2016APASS
DetailsDave Hannah
DAve-next door neighbor says the home does not meet the set backs. Can you please verify setbacks and let Mike Halitsky know the results? thanks you allsetbacks are as per plans
BLD-Footing1/22/20161/25/20161/25/2016PPASS
DetailsDave Hannah
Eric Phone #: ###-####
BLD-Foundation1/15/20161/15/20161/15/2016PPASS
DetailsDave Hannah
Eric Phone #: ###-####
BLD-Footing1/11/20161/11/20161/11/2016PPASS
DetailsMike Jordan
Eric Phone #: ###-####. East basement footing only ok.
OVERRIDE  12/9/2015  
Routing Walk-In (BLD)11/19/201511/19/201512/9/2015ADONE
DetailsBrian McGowan
Will need manual J submitted and routed thru Mechanical.
Inspection Record Card- Bld  12/9/2015 DONE
Telephone call  12/9/2015 DONE
Spoke with Matthew and informed him that his permit is ready to be picked up and the fee amount that is due. Asked him if he is acting as the RP or if the GC Company had someone who has taken the class and is going to be the RP. He stated that he would be as the homeowner
Issue PAID IN FULL permit  12/9/2015 DONE
Routing - PLAN CHECK12/9/2015 12/9/2015 PASS
DetailsDavid Ferguson
PLANS/APPL TAKEN TO FRONT DESK  12/9/2015 DONE
DetailsBrian McGowan
Permit Ready to Issue  12/9/2015 DONE
All Met
Case Summary (BLD)  12/8/2015 DONE
DetailsBrian McGowan
Routing - MECHANICAL11/19/2015 12/8/2015 PASS
DetailsTroy James
Routing - PLAN CHECK12/7/2015 12/8/2015 PASS
DetailsBrian McGowan
Routing - PLANNING11/24/2015 12/7/2015 PASS
DetailsMatthew A Halitsky
Engineering submitted 12-1-2015 per Brian M.

Per revised plans (DRH15-00345).
Routing - PLAN CHECK11/24/2015 12/4/2015 FAIL
DetailsBrian McGowan
Information and engineering required. Plan has been been given to PLANNING for review.
Plan resubmittals received  12/1/2015 DONE
resubmittals received 2 sets of retaining wal calcs, manuals, & sheets A5.1, A5, A3, A2 took to Brian McGowan
1st review completed  11/24/2015 FAIL
DetailsBrian McGowan
Engineering needed and Planning review
Routing Walk-In (BLD)11/18/201511/18/201511/19/2015PDONE
DetailsDavid Ferguson
Routing Walk-In (Zoning)11/18/201511/18/201511/18/2015PPASS
DetailsColleen T Carroll
Application received 11/18/2015