Permit Information
Permit NumberBLD15-04236
StatusFinaled
Name VISSER BUILDING CO
Site Address 1257 W RIVER ST
Project NameRiver Street Mixed Use Bldg
Customer Number 
ePlanReviewYes
Description
(RIVER STREET MIXED USE BUILDING - Foundation Permit) //Site work plan modification to change permeable concrete pavers to pervious concrete. 9-8-16 JG// **Project Management-Angie Brosious** Permit is to construct the foundation for a future 4 story 16,581 square foot multi use building. Approval contingent upon adhering to the approved plans on file and attached engineering. Work to include: construction of new concrete footing and foundation, associated site work, associated plumbing, associated electrical, and installation of foundation insulation. This building will be fire sprinklered due to residential uses and allowable height and area. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  10/19/2016 DONE
Per CO issuasnce in BLD16-00244 & inspector 425
Zoning Approval9/21/20169/21/20169/21/2016 PASS
DetailsSarah Schafer
CHANGE STATUS TO (ISS)  9/15/2016 DONE
plan mod fees paid
OVERRIDE  9/8/2016  
Plan assigned to (JG)9/6/20169/6/20169/8/2016 PASS
DetailsJavier Guzman
Plan Modificaiton
Routing - PLAN CHECK9/6/2016 9/8/2016 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  9/8/2016 DONE
Permit Ready to Issue  9/8/2016 DONE
Plan mod fee ONLY - DO NOT RE-ISSUE
Routing - FIRE9/6/20169/6/20169/7/2016 PASS
DetailsKatie Marron
Modifications reviewed. No change in comments required.
Routing - Design Review9/6/2016 9/7/2016 PASS
DetailsAndrea Tuning
Routing - PUBLIC WORKS9/6/2016 9/6/2016 PASS
DetailsRachael Beierle
Routing PW Drainage9/6/2016 9/6/2016 PASS
DetailsBrian Murphy
DRAINAGE MODIFICATION
Plan Modification Accepted  9/1/2016  
Changes to Drainage
BLD-Foundation2/12/20162/12/20162/12/2016PPART
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Ben Sears
Select Walls and column Anchor bolts OK pending STRATA special inspections, tests and approvals.
BLD-Foundation2/9/20162/9/20162/10/2016PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ben Sears
BLD-Footing2/4/20162/4/20162/4/2016PPEND
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Ben Sears ok after s/i sign off
Issue PAID IN FULL permit  1/29/2016 DONE
OVERRIDE  1/11/2016  
Routing PW Environmental1/11/2016 1/11/2016 PASS
DetailsRick Christenson
Per Rick Christianson, approved with condition that if they add a restaurant in the future they install a grease interceptor.
Routing PW Drainage1/11/2016 1/11/2016 PASS
DetailsBrian Murphy
PLANS/APPL TAKEN TO FRONT DESK  1/11/2016 DONE
Permit Ready to Issue  1/11/2016 DONE
DetailsChristina Prado
***ALL REQUIREMENTS MET - NO ACHD< FOUNDATION ONLY** 1/19/16 C_P

***still needs ACHD, GC Form, Rev Cert of Value 1-14-16 /CEV

Need ACHD, RP, GC Form & Revised Certificate of Value for issuance
Plan assigned to (TLW)11/30/2015 1/11/2016 PASS
DetailsTim L. Woodard
1st Review Completed - River Street Mixed Use Building
Routing Off Site - STRUCTURAL1/5/2016 1/5/2016 PASS
DetailsAngela Brosious
resubs for foundation approved per Chris Holladay via email.
Route to Impact Fee Review12/29/20151/1/201612/30/2015 PASS
DetailsCindy M. Gould
Routing PW Environmental12/15/2015 12/28/2015 FAIL
DetailsRick Christenson
If retail space is utilized by restaurant tenant grease abatement must be installed. Plumbing plans need to be submitted showing fixture connections.
Routing PW Solid Waste12/28/2015 12/28/2015 PASS
DetailsMegan Durrell
1st review completed  12/28/2015 FAIL
DetailsTim L. Woodard
Failed Addressing, Fire, Design Review, PW Solid Waste, PW Drainage, Structural, Building and PW Environmental.
Routing - PLANNING Land Div11/30/2015 12/24/2015 PASS
DetailsTim L. Woodard
Approved in E-plan. TLW
Routing - PLAN CHECK11/30/2015 12/24/2015 FAIL
DetailsTim L. Woodard
Routing Off Site - STRUCTURAL11/30/2015 12/18/2015 FAIL
DetailsTim L. Woodard
Routing PW Street Lights12/15/2015 12/15/2015 PASS
DetailsMike D Hedge
Routing PW Drainage12/15/2015 12/15/2015 FAIL
DetailsBrian Murphy
Routing PW Solid Waste12/15/2015 12/15/2015 FAIL
DetailsMegan Durrell
Dedicated space for trash/recycling must be provided on this parcel by either a trash enclosure or trash room.
Routing - Design Review12/15/2015 12/15/2015 PASS
DetailsAndrea Tuning
The applicant is required to submit documentation from Solid Waste allowing an offsite trash enclosure.

Tree required in landscape planter as well.
Routing PW Sewer Design12/9/2015 12/9/2015 PASS
DetailsKyle S. Rosenmeyer
Routing - Design Review11/30/2015 12/4/2015 FAIL
DetailsSarah Schafer
The applicant is required to submit documentation from Solid Waste allowing an offsite trash enclosure.

Tree required in landscape planter as well.

Attached Hold Harmless Agreement. TLW
Routing - FIRE12/2/201512/2/201512/3/2015 PASS
DetailsKatie Marron
Revised report attached to case.
Routing - FIRE11/30/201511/30/201512/2/2015 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing - PLUMBING11/30/2015 12/2/2015 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing11/30/2015 12/1/2015 FAIL
DetailsLaura Hunter
Need address verification. Plans have 1201 W River St, BLD has 604 S 13th St. Which parcel is being constructed?
Routing - PUBLIC WORKS11/30/2015 12/1/2015 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment11/30/2015 12/1/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required prior to Earth Disturbance)

**Project Management-Angie Brosious** Construct a 4 story 16,581 sf mixed use office retail development with residential dormitory: Foundation & Site Work Only
Intake Approval  11/30/2015 PASS
Pending Assignment by TLW11/30/2015 11/30/2015 DONE
DetailsTim L. Woodard
Application received  11/20/2015 DONE
Application submitted via PDS Online on Nov 20 2015 11:33AM