Print Statement | | | 11/7/2016 | | DONE |
|
|
|
|
First Notice | | 9/26/2016 | 10/17/2016 | | DONE |
|
|
|
Mailed 10-18-16
|
Permanent Occupancy | | | 9/16/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/15/2016 | | DONE |
|
|
|
|
BLD-Final | 9/14/2016 | 9/14/2016 | 9/14/2016 | P | PASS |
Jim Sly
|
|
|
Jerry Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 9/12/2016 | 9/13/2016 | 9/13/2016 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are in place with current inspection tags, stairs for mezzanine level have been deleted, fire extinguisher designated for mezzanine not required. Final life fire safety inspection passed/complete.
|
BLD-Final | 9/12/2016 | 9/12/2016 | 9/12/2016 | P | FAIL |
Mike Jordan
|
|
|
Jerry Phone #: ###-####. Remove dead bolt from back door, provide flusher on toilet on turning side and need life/safety final.
|
BLD-Framing/Rough-in | 5/12/2016 | 5/13/2016 | 5/13/2016 | A | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Framing/Rough-in | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | FAIL |
Mike Jordan
|
|
|
Daniel Phone #: ###-####. Foam all holes in top plate penetrations inwood framing, provide the min. 4ft. 6inch. clearance in the restroom vestibule. Corection notice posted.
|
Issue PAID IN FULL permit | | | 1/29/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/29/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 1/19/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 12/8/2015 | 12/8/2015 | 1/19/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) MAD SWEDE BREWERY (Jan 4 - 20 days) Level 3 TI - ePlanReview
|
Routing - FIRE | 1/16/2016 | | 1/19/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/19/2016 | | DONE |
Christina Prado
|
|
|
Need RP, ***MET*** GC form & Revised certificate of vlaue for issuance
|
Routing - PLAN CHECK | 1/15/2016 | | 1/16/2016 | | PASS |
Carl Westfall
|
|
|
Drawings approved
|
Plan resubmittals received | | | 1/15/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/8/2016 | | 1/11/2016 | | FAIL |
Carl Westfall
|
|
|
Project was not routed because issues were not resolved. Needs to be routed to Fire when resubmitted.
|
Plan resubmittals requested | | | 1/11/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/8/2016 | | DONE |
|
|
|
|
1st review completed | | | 1/6/2016 | | DONE |
Carl Westfall
|
|
|
|
Plan resubmittals requested | | | 1/6/2016 | | DONE |
|
|
|
|
Routing PW Environmental | 12/11/2015 | | 1/5/2016 | | PASS |
Rick Christenson
|
|
|
See eplan for comments.
|
Routing - PLAN CHECK | 12/8/2015 | | 1/5/2016 | | FAIL |
Carl Westfall
|
|
|
During the processing time from submission to 1st review done, Christmas Day and New Years Day occured. The time frame of 20 days was met if those 2 days are not counted.
|
Routing - MECHANICAL | 12/8/2015 | | 12/11/2015 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 12/8/2015 | | 12/11/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 12/11/2015 | | 12/11/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - FIRE | 12/8/2015 | 12/8/2015 | 12/10/2015 | | FAIL |
Scott Arellano
|
|
|
Report attached to case and emailed to architect.
|
Routing - Erosion and Sediment | 12/8/2015 | | 12/9/2015 | | PASS |
Evan Jenkins
|
|
|
|
Routing PW Solid Waste | 12/8/2015 | | 12/9/2015 | | PASS |
Megan Durrell
|
|
|
|
Plan Reviewer's activity | | | 12/8/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD for any further impact fees.
|
Routing - PLUMBING | 12/8/2015 | | 12/8/2015 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required
|
Routing - Addressing | 12/8/2015 | | 12/8/2015 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 12/8/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Westfall and plan review fees paid.
|
Pending Assignment by JCB | 12/8/2015 | | 12/8/2015 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 12/7/2015 | | PASS |
Carl Westfall
|
|
|
Plan intake review approved
|
Application received | | | 11/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 30 2015 10:02AM
|