Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-04310
StatusIssued
Name TBL CONSTRUCTION
Site Address 718 W RANCH RD
Project Name 
Customer Number 
ePlanReviewNo
Description
WUI Zone A, Class A roof required. Scope of work is to add 144 sq. ft. to existing garage, construct a 306 sq. ft. 3rd car garage/storage area, add a 186 sq. ft. covered patio and 144 sq. ft. of new living space behind the existing garage. Work shall be performed per the approved drawings, engineered plans and local codes. **DAF** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection6/30/20166/30/20167/5/2016 PEND
DetailsTony Young
BLD-Aging Inspection6/29/20166/29/20167/5/2016 PEND
DetailsTony Young
BLD-Energy code compliance2/15/20162/16/20162/16/2016PPASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
BLD-Wall cover2/12/20162/16/20162/16/2016APASS
DetailsTony Young
Tim is available by phone Phone #: ###-#### Inspection requested via web by Timothy Beaudoin,, soffit ok
BLD-Energy code compliance2/15/20162/16/20162/16/2016APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
BLD-Framing/Rough-in2/11/20162/12/20162/12/2016APART
DetailsTony Young
Tim is available by phone Phone #: ###-#### Inspection requested via web by Timothy Beaudoin,, ok to insulate,, cover,, ok to start soffit area
BLD-Wall Bracing2/3/20162/3/20162/4/2016PPART
DetailsDave Hannah
Mike urwin is on site. Garage is ready for shear inspection. Please talk to Mike if there are any issues. Thank you. Tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin ok to rap but needs to nail garage fronts
BLD-Foundation12/29/201512/29/201512/29/2015PPASS
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron,, tenting and heaters on site for cold weather
BLD-Footing12/23/201512/24/201512/24/2015APASS
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
PubWorks Subgrade Approval12/23/201512/23/201512/23/2015 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Plan assigned to (DAF)12/15/201512/15/201512/15/2015 DONE
DetailsDavid Ferguson
Routing - PLAN CHECK12/15/2015 12/15/2015 PASS
DetailsDavid Ferguson
Payment Received  12/15/2015  
Case Summary (BLD)  12/15/2015 DONE
DetailsDavid Ferguson
Case Summary (BLD)  12/15/2015 DONE
DetailsDavid Ferguson
Inspection Record Card- Bld  12/15/2015 DONE
DetailsDavid Ferguson
PLANS/APPL TAKEN TO FRONT DESK  12/15/2015 DONE
Permit Ready to Issue  12/15/2015 DONE
Inspection Record Card- Bld  12/15/2015 DONE
Issue PAID IN FULL permit  12/15/2015 DONE
Routing Walk-In (BLD)12/14/201512/14/201512/14/2015ADONE
DetailsJason C. Taylor
Routing Walk-In (PW Hillside)12/14/201512/14/201512/14/2015APASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Routing Walk-In (BLD)12/14/201512/14/201512/14/2015AFAIL
DetailsDavid Ferguson
Need floor plans for other levels and address WUI construction requirements.
Routing Walk-In (Zoning)12/2/201512/2/201512/2/2015ADONE
DetailsSue Cummings
Routing Walk-In (BLD)12/2/201512/2/201512/2/2015PFAIL
DetailsJavier Guzman
need ingineering for new footing and route to Hillside Jason Taylor and other items needed i wrote a few items needed on plans see documents for items needed
1st review completed  12/2/2015 DONE
DetailsJavier Guzman
Application received 12/2/2015