Second Notice | | 8/20/2016 | 9/13/2016 | | DONE |
Candy A. Nichols
|
|
|
|
First Notice | | 7/23/2016 | 8/10/2016 | | DONE |
|
|
|
Sent 8-11-16
|
BLD-Final | 7/13/2016 | 7/13/2016 | 7/13/2016 | A | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 7/13/2016 | 7/13/2016 | 7/13/2016 | | CANC |
Jim Storey
|
|
|
|
Zoning Approval | 7/13/2016 | 7/13/2016 | 7/13/2016 | | DONE |
Sarah Schafer
|
|
|
Approval per SMS 7/13/16, City of Boise cannot hold up approval due to ITD concerns. All requirements met for Zoning approval
|
Permanent Occupancy | | | 7/13/2016 | | DONE |
Christina Prado
|
|
|
|
PubWorks Occupancy Approval | 5/17/2016 | 5/17/2016 | 5/17/2016 | | DONE |
Tiffany Lowery
|
|
|
|
Temporary Occupancy | 5/16/2016 | 8/14/2016 | 5/16/2016 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 5/13/2016 | 5/13/2016 | 5/13/2016 | P | PART |
Jim Storey
|
|
|
Please note this inspection is pending the Zoning and Landscape acceptance for Temporary Occupancy as related to ITD resolutions regarding entrance at Broadway. I will update as information comes available. Any questions please feel free to call at anytime. Currently we would like to set this inspection for 2:00 pm if available. Thank You,
Ron Oswald Phone #: ###-#### Inspection requested via web by Ron Oswaldtemp ok - as per Jim Story Final pending P & Z final and Pub Works-please call in final when P & Z & PW inpsection is complete
|
Zoning Approval Temp | 5/13/2016 | 5/13/2016 | 5/13/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 5/11/2016 | 5/12/2016 | 5/12/2016 | P | NR |
Jim Storey
|
|
|
Please schedule for after 2:30 pm, all other required inspections are happening in the am and at 2:00 pm with Land and development. Thank You Phone #: ###-#### Inspection requested via web by Ron Oswald
|
FIRE-Final Inspection | 5/11/2016 | 5/11/2016 | 5/11/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, commercial hood suppression system inspection complete (FIR16-00148), fire alarm inspection complete (FIR16-00144) , fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 4/28/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Energy code compliance | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PASS |
Jim Storey
|
|
|
Art Phone #: ###-####
|
BLD-Energy code compliance | 3/29/2016 | 3/29/2016 | 3/29/2016 | P | PART |
Jim Storey
|
|
|
We are currently installing wall insulation and I would like to inquire about the 6 Mil. Plastic facing if we need to inspect fiber first then cover?
Thank You Phone #: ###-#### Inspection requested via web by Ron Oswald
|
BLD-Framing/Rough-in | 3/17/2016 | 3/18/2016 | 3/18/2016 | P | PASS |
Jim Storey
|
|
|
Inspection requested via web by Ron Oswaldexterior and roof ok to cover cooller area ok to cover and instal cooller
|
BLD-Foundation | 2/11/2016 | 2/12/2016 | 2/12/2016 | A | PASS |
Jim Storey
|
|
|
I requested this inspection for today via the phone app and somehow it did not log in. If possible can we get a early am at around 8:30 to 9:00 am as we have a placement scheduled for 9:30 am. Phone #: ###-#### Inspection requested via web by Ron Oswald pending si report
|
BLD-Footing | 2/8/2016 | 2/9/2016 | 2/9/2016 | A | PASS |
Jim Storey
|
|
|
Building footing inspection. Will also have MTI inspection services for record and observation of concrete placement. Phone #: ###-#### Inspection requested via web by Ron Oswald rebar and ft ok pending si reports
|
Plan assigned to (CDM) | 12/23/2015 | 12/23/2015 | 2/8/2016 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing Off Site - STRUCTURAL | 2/1/2016 | | 2/8/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/8/2016 | | DONE |
Christina Prado
|
|
|
**All requirements met 2/8/16//C_P
Need GC form & REvised certificate of value for issuance
|
Routing PW Drainage | 2/8/2016 | | 2/8/2016 | | PASS |
Brian Murphy
|
|
|
Per approval in ePlan
|
Print Occupancy Form | | | 2/8/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/8/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/1/2016 | | 2/5/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Solid Waste | 2/1/2016 | | 2/2/2016 | | PASS |
Megan Durrell
|
|
|
|
Routing - PLANNING | 2/1/2016 | | 2/1/2016 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PUBLIC WORKS | 2/1/2016 | | 2/1/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Route to Impact Fee Review | 1/13/2016 | 1/16/2016 | 1/19/2016 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 1/13/2016 | | FAIL |
|
|
|
|
Routing PW Sewer Design | 12/23/2015 | | 1/13/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
48 hours notice will be required to Boise Public Works prior to any sewer work in S. Broadway Ave. Any change in sewer service location will also require a tap permit.
|
Routing Off Site - C.D.H | 12/23/2015 | | 1/12/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 12/23/2015 | | 1/12/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 12/23/2015 | | 1/12/2016 | | PASS |
Carl D Madsen
|
|
|
Per Eplan
|
Routing - PLAN CHECK | 12/23/2015 | | 1/12/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 12/23/2015 | | 1/12/2016 | | PASS |
Rick Christenson
|
|
|
1500 Gallon Exterior Grease Interceptor Shown.
|
Routing - MECHANICAL | 12/23/2015 | | 12/30/2015 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 12/23/2015 | | 12/28/2015 | | PASS |
Andy J. Long
|
|
|
ESC site map and SWPPP narrrative approved. Valid PD and RP. ESC site preparation meeting inspection required. Call ###-####
Please see approval under ESC16-00033 for full site
|
Routing - FIRE | 12/23/2015 | 12/23/2015 | 12/24/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Solid Waste | 12/23/2015 | | 12/24/2015 | | FAIL |
Megan Durrell
|
|
|
Trash enclosure does not meet requirements - minimum 12'x12' interior dimensions. http://curbit.cityofboise.org/media/2299/CommercialEnclosureRequirements.pdf
|
Routing - PLUMBING | 12/23/2015 | | 12/24/2015 | | PASS |
Daryl Spivey
|
|
|
additional cross connection protection may be required
|
Routing - PLANNING | 12/23/2015 | | 12/23/2015 | | PASS |
Brent Moore
|
|
|
CUP15-00071
|
Routing - PLANNING Land Div | 12/23/2015 | | 12/23/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 12/23/2015 | | 12/23/2015 | | PASS |
Laura Hunter
|
|
|
|
Pending Assignment by TLW | 12/23/2015 | | 12/23/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Street Lights | 12/23/2015 | | 12/23/2015 | | PASS |
Mike D Hedge
|
|
|
No new street lighting required.
|
Routing - Design Review | 12/23/2015 | | 12/23/2015 | | FAIL |
Andrea Tuning
|
|
|
DRH15-00354
|
Intake Approval | | | 12/21/2015 | | PASS |
|
|
|
|
Intake Approval | | | 12/17/2015 | | FAIL |
Javier Guzman
|
|
|
Please provide the following, Incomplete submittals will not be accepted:
• Form #310 – Statement of Special Inspections front page must be completely filled out
• Drainage System Operation & Maintenance Plan stamped and signed by Idaho licensed design professional
• Plan sheet P3 does not exist per checklist please provide a Plumbing fixture schedule
|
Application received | | | 12/2/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 2 2015 3:24PM
|
Routing PW Drainage | 12/23/2015 | | 1/6/2015 | | FAIL |
Brian Murphy
|
|
|
SWALE SIDE SLOPES 3 TO 1
|