Permit Information
Permit NumberBLD15-04329
StatusFinaled
Name VISSER BUILDING CO
Site Address 1257 W RIVER ST
Project NameRiver Street - Shell / Structu
Customer Number 
ePlanReviewYes
Description
(RIVER STREET MIXED USE BUILDING - Shell and Super Structure) **Project Management-Angie Brosious** Permit is to construct the shell and super structure for a 4 story 16,581 square foot multi use building. This building will be fire sprinklered in the future for height increase and residential occupancies. Approval contingent upon adhering to the approved plans on file and attached engineering. Work to include: construction of new exterior wood framed walls, construction of new interior exit stairways, construction of roof / floor ceilings, fire rating of the interior exit stairway, exterior coverings, and roof deck. This building will be fire sprinklered in the future for height increase and residential occupancies. Foundation permit pulled under BLD15-04236. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  10/19/2016 DONE
Per CO issuasnce in BLD16-00244 & inspector 425
Zoning Approval9/21/20169/21/20169/21/2016 PASS
DetailsSarah Schafer
BLD-Aging Inspection8/24/20168/24/20168/30/2016 PEND
DetailsDave Hannah
BLD-Aging Inspection8/25/20168/25/20168/29/2016 PEND
DetailsDave Hannah
BLD-Conference5/12/20165/13/20165/13/2016ADONE
DetailsDave Hannah
Bob Phone #: ###-####
BLD-Wall Bracing4/11/20164/11/20164/12/2016PPART
DetailsDave Hannah
Bob Phone #: ###-####first floor stair tower int ok
Case Summary (BLD)  3/9/2016 DONE
Route to Impact Fee Review2/12/20162/15/20162/22/2016 PASS
DetailsCindy M. Gould
Issue PAID IN FULL permit  2/18/2016 DONE
Print Occupancy Form  2/18/2016 DONE
OVERRIDE  2/17/2016  
Routing - PLAN CHECK2/12/2016 2/17/2016 PASS
DetailsTim L. Woodard
Routing - Addressing2/12/2016 2/17/2016 PASS
DetailsTim L. Woodard
Approved in E-Plan. TLW
Routing - Erosion and Sediment2/12/2016 2/17/2016 PASS
DetailsEvan Jenkins
Approved in E-plan. TLW
Routing - Design Review2/17/2016 2/17/2016 PASS
DetailsAndrea Tuning
PLANS/APPL TAKEN TO FRONT DESK  2/17/2016 DONE
Permit Ready to Issue  2/17/2016 DONE
DetailsChristina Prado
**ALL MET 2-18-16** Need RP, GC Form & Revised certificate of value from GC for issuance
Plan assigned to (TLW)12/14/2015 2/17/2016 PASS
DetailsTim L. Woodard
Routing - Design Review2/12/2016 2/16/2016 FAIL
DetailsAndrea Tuning
DRH15-00428
The applicnat did not submit a site plan or landscape plan with this building permit application. These will be required. Also the applicant is required to submit documentation from Solid Waste allowing an offsite trash enclosure. This has not been completed.
Routing - Addressing2/16/2016 2/16/2016 PASS
DetailsLaura Hunter
Routing - Erosion and Sediment2/16/2016 2/16/2016 PASS
DetailsAndy J. Long
ESC plan submitted and approved under ESC15-01529. No duplicate permit necessary for vertical.
Plan resubmittals received  2/12/2016 DONE
DetailsTim L. Woodard
Routing PW Street Lights12/15/2015 1/25/2016 PASS
DetailsMike D Hedge
Approved in E-Plan. TLW
1st review completed  1/25/2016 DONE
Routing Off Site - STRUCTURAL12/14/2015 1/21/2016 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK12/14/2015 1/21/2016 FAIL
DetailsTim L. Woodard
Routing PW Solid Waste1/12/2016 1/12/2016 PASS
DetailsMegan Durrell
Solid Waste & Legal required conditions on the parcels to waive trash/recycling services at this location and to allow sharing with an adjacent property.
Routing - PLUMBING12/14/2015 12/18/2015 PASS
DetailsBill VanDegrift
no plumbing
Routing - FIRE12/14/201512/14/201512/17/2015 PASS
DetailsKatie Marron
Comments attached to case.
Routing - Design Review12/14/2015 12/15/2015 FAIL
DetailsAndrea Tuning
DRH15-00428
The applicnat did not submit a site plan or landscape plan with this building permit application. These will be required. Also the applicant is required to submit documentation from Solid Waste allowing an offsite trash enclosure. This has not been completed.
Routing - Addressing12/14/2015 12/15/2015 FAIL
DetailsLaura Hunter
A better site plan and floor plan is needed for correct addressing
Routing - PUBLIC WORKS12/14/2015 12/15/2015 PASS
DetailsJennifer Bruner
Sewer rating will be completed with future plans.
Routing - Erosion and Sediment12/14/2015 12/15/2015 FAIL
DetailsEvan Jenkins
Full Erosion and Sediment Control Narrative and Site Map Required for Approval: Evan Jenkins 794.3958
Intake Approval  12/14/2015 PASS
Pending Assignment by TLW12/14/2015 12/14/2015 DONE
DetailsTim L. Woodard
Plan Reviewer's activity  12/10/2015 DONE
DetailsJavier Guzman
emailed applicant to fill out the form #310 completely
Application received  12/3/2015 DONE
Application submitted via PDS Online on Dec 3 2015 2:17PM