BLD-Final | 5/6/2016 | 5/9/2016 | 5/9/2016 | P | PASS |
Tony Young
|
|
|
Call 30 minutes before // Ed Phone #: ###-####
|
DOC - Permit Finaled | 5/9/2016 | 5/9/2016 | 5/9/2016 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Energy code compliance | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 2/25/2016 | 2/26/2016 | 2/26/2016 | P | PASS |
Tony Young
|
|
|
Call half hour before // Ed Phone #: ###-####
|
BLD-Framing/Rough-in | 2/24/2016 | 2/25/2016 | 2/25/2016 | P | PART |
Tony Young
|
|
|
Call half hour before // Ed Phone #: ###-####,, needs a mech permit and inspection.. verify seal package and fire blocking at energy,, ok to insulate
|
BLD-Conference | 2/8/2016 | 2/9/2016 | 2/9/2016 | A | PASS |
Tony Young
|
|
|
would like call ahead; Jenkins Phone #: ###-####,, ?s on design method,, ok pending architect
|
BLD-Final | 1/20/2016 | 1/20/2016 | 1/20/2016 | P | CANC |
Tony Young
|
|
|
Wayne Phone #: ###-####
|
BLD-Footing | 1/11/2016 | 1/12/2016 | 1/12/2016 | A | PART |
Jim Sly
|
|
|
Annie Phone #: ###-#### Foundation wall....OK.
|
BLD-Footing | 1/7/2016 | 1/7/2016 | 1/7/2016 | P | PASS |
Tony Young
|
|
|
Annie-pour time 2:00 Phone #: ###-####,, addition ok
|
BLD-Foundation | 12/29/2015 | 12/30/2015 | 12/30/2015 | A | PART |
Tony Young
|
|
|
would like call ahead; Annie Phone #: ###-####,, interior walls under existing ok,, ok to pour slab
|
BLD-Footing | 12/29/2015 | 12/29/2015 | 12/29/2015 | P | PART |
Tony Young
|
|
|
would like call ahead; Annie Phone #: ###-####,, interior ftgs,, ok
|
BLD-Footing | 12/21/2015 | 12/21/2015 | 12/21/2015 | P | PASS |
Mike Jordan
|
|
|
Annie-pour time 2:00 Phone #: ###-####// please call before
|
Routing Walk-In (Zoning) | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 12/10/2015 | 12/10/2015 | 12/10/2015 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 12/10/2015 | | 12/10/2015 | | PASS |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 12/10/2015 | | DONE |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 12/10/2015 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/10/2015 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 12/10/2015 | | DONE |
|
|
|
|
1st review completed | | | 12/10/2015 | | DONE |
David Ferguson
|
|
|
|
Application received | | 12/10/2015 | | | |
|
|
|
|