Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD15-04391
StatusFinaled
Name SCHUERMAN FREDERICK M
Site Address 12542 W FAIRVIEW AVE
Project NameSockeye Brewery - Boiler Room
Customer NumberDRH15-00446 DRH12-00207
ePlanReviewNo
Description
(SOCKEYE BREWERY BOILER ROOM ADDITION AND EXTERIOR CONCRETE SLAB TO SUPPORT FERMENTATION TANKS) (DRH15-00446 MODIFICATION TO DRH12-00207) The fire sprinkler system is used for building area increase and for fire area. To construct a 206 square foot building addition at the Northwest corner of an existing 15,050 square foot building (11,946 square feet inside) to function as a boiler room. The foundation and the interior slab on grade for that addition were done under permit BLD15-04448. A new 829 square foot exterior concrete slab will be placed to support steel fermentation tanks that are about 20 feet tall. The new slab will be placed directly over an existing sloped concrete slab on grade. The new slab will range from 6 inches thick to 16 inches thick and will be reinforced to support the gravity and lateral loads induced by the tanks (compression, sliding, uplift, etc.). The attachments of the tanks to the concrete slab are required to be capable of resisting seismic and wind loads as determined by the Project Structural Engineer and in accordance with his design. In addition, an existing concrete slab will be expanded and a new exterior concrete stairway constructed. A new glycol chiller will be installed on top of that expanded concrete slab in conjunction with this permit. Six foot tall chain-link security fences will be constructed around the tank area and the chiller area. Compliant egress is required from these areas. A new sloped vehicular ramp will also be constructed. Special Inspection is required for epoxy anchors. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. All equipment shall be listed and labeled per the adopted Electrical Code with approval from the PDS Electrical Inspection Section. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 1/16/20172/13/2017 DONE
DetailsChristina Prado
Mailed 2/13/17, with letter
Third Notice 12/18/20161/11/2017 DONE
sent with a letter
Third Notice 11/26/201612/13/2016 DONE
Third Notice 10/15/201611/21/2016 DONE
Second Notice 9/23/201610/10/2016 DONE
mailed 10-11-16
First Notice 8/29/20169/13/2016 DONE
DetailsCandy A. Nichols
Permanent Occupancy  8/19/2016 DONE
BLD-Final8/18/20168/18/20168/18/2016PPASS
DetailsJim Sly
Dave Phone #: ###-####
Zoning Approval8/18/20168/18/20168/18/2016 PASS
DetailsJosh Wilson
BLD-Final8/16/20168/17/20168/17/2016ANR
DetailsJim Sly
Dave Phone #: ###-####
Need Zoning Final.
FIRE-Final Inspection8/15/20168/16/20168/16/2016APASS
DetailsTroy Cobbley
life safety passed
BLD-Aging Inspection8/5/20168/5/20168/8/2016 PEND
DetailsJim Sly
WIP
BLD-Foundation3/24/20163/24/20163/24/2016PPASS
DetailsJim Sly
rebar; Dave Phone #: ###-####
BLD-Wall Bracing2/11/20162/12/20162/12/2016PPASS
DetailsJim Sly
Dave Phone #: ###-####
BLD-Framing/Rough-in2/11/20162/12/20162/12/2016PPASS
DetailsJim Sly
Dave Phone #: ###-####
Issue PAID IN FULL permit  2/11/2016 DONE
Print Occupancy Form  2/11/2016 DONE
Plan assigned to (CJW)12/11/201512/11/20152/10/2016 PASS
DetailsCarl Westfall
(1st done) SOCKEYE (Jan 21 - 30 days) (Dec 31 - 15 days)
Routing Off Site - STRUCTURAL2/3/2016 2/10/2016 PASS
DetailsCarl Westfall
(2-3-16) Routed response to Chris Merrill via Email.

(2-10-16) Structural approved
PLANS/APPL TAKEN TO FRONT DESK  2/10/2016 DONE
Permit Ready to Issue  2/10/2016 DONE
***ALL REQUIREMENTS MET 2-11-16 /CEV

need GC and rev cert of val-please remind customer that they will need to call the inspections for P&Z and PW
Print Occupancy Form  2/10/2016 DONE
Telephone call  2/10/2016 DONE
Spoke with Bill informing him the permit is ready and we would need a GC Form and Revised Cert of Value filled out by the GC for issuance.
Routing - PLAN CHECK2/2/2016 2/4/2016 PASS
DetailsCarl Westfall
(2-4-16) Completed the IBC plan review. Waiting for the Consultant Structural Engineer to finish his 3rd review.
(2-10-16) Consultant Structural Engineer approved drawings.
Plan resubmittals received  2/2/2016 DONE
Routing - PLAN CHECK1/29/2016 2/2/2016 PEND
DetailsCarl Westfall
Routing - PUBLIC WORKS1/22/2016 1/29/2016 PASS
DetailsRachael Beierle
Routing PW Sewer Rating1/22/2016 1/29/2016 PASS
DetailsRachael Beierle
Routing - PUBLIC WORKS1/28/2016 1/29/2016 PASS
DetailsRachael Beierle
Routing PW Drainage1/25/2016 1/28/2016 PASS
DetailsJason C. Taylor
No review required as all draiange has been accounted for with previous construction approved under ODI 3050. Jason Taylor ###-####
Routing Off Site - STRUCTURAL1/15/2016 1/27/2016 FAIL
DetailsCarl Westfall
Chris Merrill with Stapley
Plan resubmittals requested  1/27/2016 DONE
Consultant Structural Engineer's review sent to Bill Matter
Plan resubmittals received  1/26/2016 DONE
Three copies of sheets SD1, A1.0, A2.0, and A3.0 taken to Carl W
Routing - PLAN CHECK1/15/2016 1/22/2016 FAIL
DetailsCarl Westfall
Did not resolve the issues noted in the 1st review. Called and talked to the Architect. He said he would revise and resubmit.
Telephone call  1/15/2016 DONE
called Network Global- they're picking up plans Tuesday for outside engineering to go to Stapleys per Carl Westfall
Routing - PLAN CHECK1/11/2016 1/15/2016 DONE
DetailsCarl Westfall
Waiting for resubmittals
Plan resubmittals received  1/15/2016 DONE
DetailsChristina Prado
Received three copies of Structural response letter, revised structural calcs and four sets of plan sheets marked SD1 & A1.0; Plans stamped and taken back to CJW for further review
Route to Impact Fee Review1/11/20161/14/20161/12/2016 PASS
DetailsCindy M. Gould
Routing - FIRE1/7/2016 1/11/2016 PASS
DetailsScott Arellano
Comments attached to plans
1st review completed  1/11/2016 FAIL
Failed Plan Check, Structural and Public Works/Sewer.
Routing - PLAN CHECK12/21/2015 1/7/2016 FAIL
DetailsCarl Westfall
Revised drawings required. Plan review report Emailed to Architect.
Routing Off Site - STRUCTURAL12/11/2015 12/29/2015 FAIL
DetailsCarl Westfall
Stapley - Chris Merrill

Copy of Consultant Structural Engineer's Plan Review Report was forwarded to Bill Matter on December 30, 2015.
Routing PW Environmental12/15/2015 12/23/2015 PASS
DetailsRick Christenson
Valve in tank area approved for diversion from storm water to sanitary sewer.
Routing - Erosion and Sediment12/18/2015 12/21/2015 PASS
DetailsEvan Jenkins
Sockeye Brewery boiler room

Reference ESC14-00678 for Coverage
Routing - PLUMBING  12/21/2015 PASS
DetailsDaryl Spivey
additional cross connection protection may be required
Routing - MECHANICAL12/21/2015 12/21/2015 PASS
DetailsTroy James
Field verify equipment installed per manufacturer
Routing - PLANNING12/16/2015 12/17/2015 PASS
DetailsJosh Wilson
Routing - Design Review12/16/2015 12/17/2015 PASS
DetailsJosh Wilson
Routing PW Sewer Rating12/15/2015 12/16/2015 FAIL
DetailsBeverly Mountain
Contacting owner for new brewing consumptions
Routing - PUBLIC WORKS12/15/2015 12/16/2015 FAIL
DetailsJennifer Bruner
Please see Sewer Rating.
Routing - Addressing12/11/2015 12/14/2015 PASS
DetailsLaura Hunter
Routing - PLANNING Land Div12/14/2015 12/14/2015 PASS
DetailsDave Abo
Parcel C of ROS 9994
Intake Approval  12/11/2015 PASS
DetailsJavier Guzman
Plans ACCEPTED BY PLAN TECH  12/11/2015 DONE
Recd Pcfee & Taken To Pln CK  12/11/2015 DONE
Application received 12/11/2015