BLD-Final | 1/23/2017 | 1/24/2017 | 1/24/2017 | A | PASS |
Jim Storey
|
|
|
Jason ###-####.
Plans were approved to reflect the change in siding on page A2.0, Key note 2.04 Inspection requested via web by jason epperson
|
Plan assigned to (JG) | 1/11/2017 | 1/11/2017 | 1/18/2017 | | PASS |
Javier Guzman
|
|
|
Plan Mod Red Robin Gourmet Burgers, Pend DR
|
Routing - Design Review | 1/17/2017 | | 1/18/2017 | | PASS |
Andrea Tuning
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/18/2017 | | DONE |
|
|
|
plan mod ONLY - DO NOT RE-ISSUE
|
CHANGE STATUS TO (ISS) | | | 1/18/2017 | | DONE |
|
|
|
Plan Mod
|
Route to Impact Fee Review | 1/15/2017 | 1/18/2017 | 1/17/2017 | | PASS |
Cindy M. Gould
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 1/17/2017 | | 1/17/2017 | | PASS |
Javier Guzman
|
|
|
|
Plan Modification Accepted | | | 1/11/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod requested to update the siding materials on the building, see DRH16-00539 for zoning approval
|
BLD-Final | 1/9/2017 | 1/10/2017 | 1/10/2017 | A | NR |
Mike Jordan
|
|
|
Request for final inspection. Phone #: ###-#### Inspection requested via web by jason epperson. Contractor has received DRH approval letter for exterior work. Architect of record will need to upload a plan modification in Eplan review for the additional work done. After plan review has been completed, then a zoning final will need to be scheduled and completed. A building final may then be scheduled and any further inspections if required on the exterior work will be determined at that time. I also contacted the general contractor (Jason Eperson) and left him a voice mail detailing the next required steps. I aslo received a letter from the engineer of record approving work done on soffits.
|
BLD-Other | 10/18/2016 | 10/19/2016 | 10/19/2016 | A | PART |
Mike Jordan
|
|
|
Before 10AM - railings and ceiling inspection - Ed Phone #: ###-####. All issues regarding the handrails have been resolved. Aslo inspected soffitt framing above grid. Noted the framing has not been done in accordance with city approved plans. After speaking with contractor, it was noted that work either needs to be corrected or a letter from the engineer of record accepting the in place work. Main area of concern is new soffit has been supported from the bottom chords of the existing roof trusses. Engineer to justify that the bottom chords can support the additional wieght.
|
BLD-Conference | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | DONE |
Mike Jordan
|
|
|
Meet with Ed at 11:30am to discuss handrail issues... Met with handrail fabricator to go over correction notice items.
|
BLD-Final | 9/16/2016 | 9/19/2016 | 9/19/2016 | A | FAIL |
Mike Jordan
|
|
|
Ed Phone #: ###-####. Noted that new exterior work has been completed on building (new siding, paint and signage). This work was not in original scope of work and will require a resubmitttal to zoning for reveiw. Provide code compliant handrails. Provide access to inspect new soffit framing and partition to verify compliance with code and engineering. Correction notice was issued.
|
BLD-Final | 9/13/2016 | 9/16/2016 | 9/16/2016 | A | CANC |
Bob Archibald
|
|
|
Ed to meet onsite. Plans are in managers office. Phone #: ###-#### Inspection requested via web by jason epperson. Contractor will reschedule for 9/17
|
FIRE-Final Inspection | 9/7/2016 | 9/8/2016 | 9/8/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 8/29/2016 | 8/30/2016 | 8/30/2016 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site and I also noted atleast one exit sign that needs repaired.
|
FIRE-Final Inspection | 8/25/2016 | 8/29/2016 | 8/29/2016 | A | CANC |
Troy Cobbley
|
|
|
Looking to schedule Life Safety Inspection. The sprinkler contractor will meet on site. Fidel-###-####
Plans are in Managers office. Phone #: ###-#### Inspection requested via web by jason epperson
|
BLD-Conference | 8/23/2016 | 8/24/2016 | 8/24/2016 | A | DONE |
Mike Jordan
|
|
|
Spoke with Jason Epperson (contractor) They will get city approved plans on site, schedule life/safety final and building final.
|
BLD-Final | 8/19/2016 | 8/22/2016 | 8/23/2016 | A | FAIL |
Mike Jordan
|
|
|
Inspection requested via web by jason epperson. Called contractors main office yesterday and left message. I have not received a call back. Stop by and spoke to resteraunt manager this morning. Left business card to have manager call me back.
|
Issue PAID IN FULL permit | | | 4/21/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/21/2016 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/21/2015 | 12/21/2015 | 1/27/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 12/30 L2 Red Robin Gourmet Burgers ePlan
|
Routing - PLAN CHECK | 1/27/2016 | | 1/27/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/27/2016 | | DONE |
Christina Prado
|
|
|
**All requirements met 4/18/16 C_P
Need GC form & Revised certificate of value for issuance
|
Routing - PLAN CHECK | 12/21/2015 | | 12/29/2015 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
1st review completed | | | 12/29/2015 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 12/21/2015 | 12/21/2015 | 12/21/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Intake Approval | | | 12/21/2015 | | PASS |
David Ferguson
|
|
|
|
Routing - Addressing | 12/21/2015 | | 12/21/2015 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/21/2015 | | 12/21/2015 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 12/14/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 14 2015 5:21PM
|