FIRE-Conference | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | DONE |
Troy Cobbley
|
|
|
Permit did not originally require life safety, sprinkler or alarm sign offs. I had that changed by the permit technicians due to new sprinklers, and what appears to be fire alarm without a permit.
|
Meeting | | | 8/2/2016 | | DONE |
|
|
|
as per Troy Cobbley permit needs Fire/Life Safety inspection, Fire Alarm, Fire Sprinkler
|
BLD-Conference | 6/16/2016 | 6/16/2016 | 6/16/2016 | A | DONE |
Jim Sly
|
|
|
WIP.
|
BLD-Footing | 1/25/2016 | 1/26/2016 | 1/26/2016 | A | PART |
Jim Sly
|
|
|
Dave Phone #: ###-#### Should be Foundation wall insp. Wall OK.
|
BLD-Footing | 1/22/2016 | 1/25/2016 | 1/25/2016 | P | PASS |
Jim Sly
|
|
|
Dave Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/15/2016 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 1/15/2016 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 12/17/2015 | 12/17/2015 | 12/24/2015 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 12/24/2015 | | PASS |
|
|
|
The application for the foundation and slab on grade early start permit was officially received on December 24, 2015. No plan intake review was required.
|
Intake Approval | | | 12/24/2015 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/24/2015 | | 12/24/2015 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/24/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/24/2015 | | DONE |
Christina Prado
|
|
|
Need GC form & Revised certificate of value
|
Application received | | 12/17/2015 | | | |
|
|
|
|