DOC - Permit Finaled | | | 7/26/2018 | | DONE |
|
|
|
Scope of work completed under BLD16-01058
|
Zoning Approval | 6/28/2018 | 6/28/2018 | 6/28/2018 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Ceiling Grid Inspection | 2/7/2018 | 2/8/2018 | 2/8/2018 | A | PART |
Jim Sly
|
|
|
above grid inspection units 309-319, 209-219 Phone #: ###-#### Inspection requested via web by shaun carley Third Floor only......OK.
|
BLD-Concrete | 4/25/2017 | 4/25/2017 | 4/25/2017 | P | PEND |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Michael West WIP.
|
BLD-Concrete | 11/30/2016 | 12/1/2016 | 12/1/2016 | P | PASS |
Phil Shearer
|
|
|
PT deck Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Concrete | 11/17/2016 | 11/18/2016 | 11/18/2016 | A | PASS |
Phil Shearer
|
|
|
PT Deck Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Concrete | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Phil Shearer
|
|
|
Foundation stem walls Inspection requested via web by Michael West
|
BLD-Concrete | 10/5/2016 | 10/5/2016 | 10/5/2016 | P | PEND |
Phil Shearer
|
|
|
Building 1 Slab reinforcing South half. Phone #: ###-#### Inspection requested via web by Michael West. Pending MTI inspection
|
BLD-Concrete | 9/26/2016 | 9/27/2016 | 9/27/2016 | P | PASS |
Phil Shearer
|
|
|
Walls and footings Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Footing | 9/12/2016 | 9/13/2016 | 9/13/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Foundation | 9/9/2016 | 9/9/2016 | 9/12/2016 | P | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Michael West ok after spec insp sign off
|
BLD-Footing | 9/6/2016 | 9/6/2016 | 9/6/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Michael West
|
BLD-Foundation | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PASS |
Phil Shearer
|
|
|
Foundation walls and columns. Concrete scheduled for 9:45 am. Phone #: ###-#### Inspection requested via web by Michael West. Pending MTI inspection
|
BLD-Footing | 7/26/2016 | 7/26/2016 | 7/26/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Michael West. Bldg 1 footing on gridline b from grids 1 to 5 and on gridline 1 from grids a to E. also elevator pit floor ok. Work in progress on south footings, ok to place when special inspection has passed.
|
Issue PAID IN FULL permit | | | 5/23/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/23/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 4/1/2016 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/21/2016 | | 4/1/2016 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/1/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/1/2016 | | DONE |
Christina Prado
|
|
|
All requirements met 5/18/16
Need ACHD & RP as of 5/10/16 // C_P
need ACHD, RP, GC & rev cert of val
|
Plan assigned to (TLW) | 1/8/2016 | | 4/1/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/7/2016 | | 3/11/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLUMBING | 3/7/2016 | | 3/11/2016 | | PASS |
Daryl Spivey
|
|
|
vent vapor chamber of the flammable liquids interceptor, see red lines
|
Routing Off Site - STRUCTURAL | 3/7/2016 | | 3/11/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing PW Drainage | 3/7/2016 | | 3/10/2016 | | PASS |
Jim Wyllie
|
|
|
Approved in Eplan review. TLW
|
Routing PW Flood Plain | 3/7/2016 | | 3/10/2016 | | PASS |
Jim Wyllie
|
|
|
Approved in E-Plan. TLW
|
Plan resubmittals received | | | 3/7/2016 | | DONE |
|
|
|
|
Route to Impact Fee Review | 2/9/2016 | 2/12/2016 | 2/10/2016 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 2/9/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/8/2016 | | 2/9/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLANNING Land Div | 1/8/2016 | | 2/9/2016 | | PASS |
Tim L. Woodard
|
|
|
Approved in E-Plan. TLW
|
Routing - PUBLIC WORKS | 1/8/2016 | | 2/9/2016 | | PASS |
Tim L. Woodard
|
|
|
Approved in E-Plan
|
Routing Off Site - STRUCTURAL | 1/8/2016 | | 2/2/2016 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing PW Environmental | 1/11/2016 | | 2/2/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - Design Review | 1/8/2016 | | 1/13/2016 | | PASS |
Josh Wilson
|
|
|
Ok per DRH15-00490
|
Routing - FIRE | 1/8/2016 | 1/8/2016 | 1/12/2016 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PLUMBING | 1/8/2016 | | 1/11/2016 | | FAIL |
Daryl Spivey
|
|
|
1) vent interceptors
2) United Water shows two services to buildings 1 and 2, plans do not match
3) water service can not be in an elevator shaft
4) mechanical engineer stamp required on all plumbing drawings
|
Routing PW Drainage | 1/11/2016 | | 1/11/2016 | | FAIL |
Jim Wyllie
|
|
|
GRD 15-00089 needs to be approved prior to approving this permit. Jim Wyllie / ###-####
|
Routing PW Flood Plain | 1/11/2016 | | 1/11/2016 | | FAIL |
Jim Wyllie
|
|
|
GRD 15-00089 needs to be approved prior to approvall of this permit. Jim Wyllie / ###-####
|
Routing PW Solid Waste | 1/11/2016 | | 1/11/2016 | | PASS |
Megan Durrell
|
|
|
|
Routing - Erosion and Sediment | 1/8/2016 | | 1/11/2016 | | PASS |
Andy J. Long
|
|
|
ESC site plan and SWPPP narrative submitted and approved. Valid PD designated, RP not yet determined. Site prep/pre-construction BMP meeting & inspection required. Call ###-####
|
Routing - Addressing | 1/8/2016 | | 1/11/2016 | | PASS |
Laura Hunter
|
|
|
|
Pending Assignment by TLW | 1/8/2016 | | 1/8/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 1/5/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 12/22/2015 | | FAIL |
Javier Guzman
|
|
|
Please provide the following, Incomplete submittals will not be accepted:
• Shallow Injection Well Inventory form Drainage plans with seepage beds must submit a “Shallow Injection Well Inventory” form from the Idaho Department of Water Resources available at: http://www.idwr.idaho.gov/RulesStatutesForms/WellConstruction/WellFormsRules.htm#Inj
• Site Drainage Report stamped and signed by an Idaho licensed design professional including descriptive narrative and calculations
• Planning & Zoning letter(s) of approval – i.e. Conditional Use Permit (CUP), Design Review Permit (DRH) and/or other approval documents
• Verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff
• Code Analysis/Building Data on front sheet of plans which includes: Code year, occupancy group(s), construction type(s), floor areas for all floors & building total floor area, building height, fire suppression system (specify NFPA code applicable), fire alarm or smoke control system.
|
Application received | | | 12/18/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2015 3:04PM
|