Permit Information
Permit NumberBLD15-04490
StatusFinaled
Name UNION SQUARE LLC
Site Address 9953 W CABLE CAR ST
Project NameEcho Dance Studio
Customer NumberBLD15-04487
ePlanReviewYes
Description
(ECHO DANCE STUDIO - Shell and Core) High efficiency HVAC submitted as additional efficiency package. Permit to construct a new 7,372 sf empty shell building and site improvements. Scope of work to include footings, foundation, exterior walls, windows, doors, trussed roof system and roofing. Plumbing, mechanical and electrical permits required for trade work. TI submitted under BLD15-04487. Storage accessed with alternating tread device shall be limited to max 250 sq ft. This building is NOT fire sprinklered. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/15/20167/18/20167/18/2016APASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Mike McHargue
Letter of compliance/Occupancy  7/18/2016 DONE
DOC - Permit Finaled  7/18/2016 DONE
Letter of compliance/Occupancy  7/18/2016 DONE
BLD-Final7/14/20167/15/20167/15/2016PNR
DetailsPhil Shearer
TI Final Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Ceiling Grid Inspection7/14/20167/15/20167/15/2016PPASS
DetailsPhil Shearer
TI Final Phone #: ###-#### Inspection requested via web by Mike McHargue
FIRE-Final Inspection7/14/20167/15/20167/15/2016APASS
DetailsTroy Cobbley
Life safety passed. Hardware to the east room to be changed so that people are not directed to a locked door.
Zoning Approval7/15/20167/15/20167/15/2016 PASS
DetailsJosh Wilson
BLD-Energy code compliance5/24/20165/24/20165/24/2016PPASS
DetailsMike Jordan
BLD-Framing/Rough-in5/19/20165/20/20165/20/2016APASS
DetailsMike Jordan
BLD-Framing/Rough-in5/19/20165/19/20165/19/2016PDEFR
DetailsMike Jordan
Shell Framing Inspection Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Wall Bracing4/27/20164/27/20164/27/2016PPASS
DetailsMike Jordan
Exterior Wall Shear Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Wall Bracing4/21/20164/21/20164/21/2016PPASS
DetailsMike Jordan
Roof Sheer and Straps Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Wall Bracing4/19/20164/20/20164/20/2016AFAIL
DetailsMike Jordan
Flat roof sheer nailing, hold downs, column anchor nuts Phone #: ###-#### Inspection requested via web by Mike McHargue. Roof nailing for diaphragm. Needs to renail, fasteners over spaced.
BLD-Concrete3/10/20163/11/20163/11/2016PPASS
DetailsMike Jordan
Interior slab thick-end footings Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Energy code compliance3/3/20163/3/20163/3/2016PPASS
DetailsMike Jordan
Foundation Insulation Early PM if possible Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Energy code compliance3/2/20163/3/20163/3/2016ANR
DetailsMike Jordan
Foundation insulation inspection mid to late morning if possible Phone #: ###-#### Inspection requested via web by Mike McHargue
BLD-Foundation2/29/20162/29/20162/29/2016PPASS
DetailsMike Jordan
Stemwall rebar, late PM if possible Phone #: ###-#### Inspection requested via web by Mike McHargue. Perimeter stemwall and interior column pad footings ok.
BLD-Footing2/26/20162/26/20162/26/2016PPASS
DetailsMike Jordan
Footing rebar inspection, ready at 2PM Phone #: ###-#### Inspection requested via web by Mike McHargue. Permiter footings ok.
BLD-Conference2/25/20162/26/20162/26/2016ADONE
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Mike McHargue
Issue PAID IN FULL permit  2/18/2016 DONE
Print Occupancy Form  2/18/2016 DONE
OVERRIDE  2/17/2016  
Plan assigned to (AJS)12/24/201512/24/20152/17/2016 PASS
DetailsAdele J Schaffeld-Griffin
1st reivew completed New building
Routing - PLUMBING2/16/2016 2/17/2016 PASS
DetailsBill VanDegrift
redlined plan,
1) install rain water piping to service drain to the east
Routing - PLAN CHECK2/16/2016 2/17/2016 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  2/17/2016 DONE
Permit Ready to Issue  2/17/2016 DONE
DetailsChristina Prado
Need ACHD, RP, GC Form & Revised Certificate of value for issuance
Routing - PLAN CHECK2/1/2016 2/10/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL2/1/2016 2/10/2016 PASS
DetailsAdele J Schaffeld-Griffin
Routing PW Sewer Design2/1/2016 2/10/2016 PASS
DetailsKyle S. Rosenmeyer
Routing - MECHANICAL2/3/2016 2/3/2016 PASS
DetailsTroy James
No mechanical plans for shell and core. Mechanical design will be with the T.I. permit.
Routing - MECHANICAL2/1/2016 2/2/2016 FAIL
DetailsTroy James
previous review comment has not been addressed. Sent an email to applicant.
Routing - PLUMBING2/1/2016 2/2/2016 FAIL
DetailsDaryl Spivey
Mark up not addressed on C 1 and does not meet cross sectional venting requirements on P 1.
Route to Impact Fee Review1/21/20161/24/20161/21/2016 PASS
DetailsCindy M. Gould
1st review completed  1/21/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK12/24/2015 1/21/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL12/24/2015 1/20/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Sewer Design12/28/2015 1/13/2016 FAIL
DetailsKyle S. Rosenmeyer
Clarify which sewer service is intended to serve the building. You may want to verfiy that the location of the waste existing the building works with using an existing sewer service.
Routing PW Solid Waste12/28/2015 1/5/2016 PASS
Details
Routing - MECHANICAL12/24/2015 12/31/2015 FAIL
DetailsTroy James
Routing - Design Review12/24/2015 12/30/2015 PASS
DetailsJosh Wilson
Routing PW Sewer Rating12/28/2015 12/29/2015 PASS
DetailsRachael Beierle
Routing - FIRE12/24/201512/24/201512/28/2015 PASS
DetailsKatie Marron
Comments attached to case.
Routing PW Drainage12/28/2015 12/28/2015 PASS
DetailsBrian Murphy
Routing - PLUMBING12/24/2015 12/28/2015 FAIL
DetailsDaryl Spivey
12.56 inches of venting required
civil plan does not show a system on the east side of the building
Routing - PLANNING Land Div12/24/2015 12/28/2015 PASS
DetailsDave Abo
Parcel A of ROS #10045
Routing - Addressing12/24/2015 12/28/2015 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS12/24/2015 12/28/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment12/24/2015 12/28/2015 PASS
DetailsAndy J. Long
ESC site plan and narrative submitted and approved. Valid RP. Site has active construction already in progress. Site prep/pre-construction conference required, call ###-####
Intake Approval  12/24/2015 PASS
Pending Assignment by TLW12/24/2015 12/24/2015 DONE
DetailsTim L. Woodard
Intake Approval  12/23/2015 FAIL
DetailsJavier Guzman
Please provide the following: Incomplete submittals will not be accepted.
• Owners signature on form #304
• Checklist Clarification of Specification Books or incorporated within building plans
• Verification of Legal Lot or Parcel form signed and approved by PDS Subdivision Staff
Application received  12/22/2015 DONE
Application submitted via PDS Online on Dec 22 2015 11:14AM