Second Notice | | 8/22/2016 | 8/31/2016 | | DONE |
|
|
|
This permit finaled on the web by Stephanie Boomgarden
|
First Notice | | 8/1/2016 | 8/12/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Permanent Occupancy | | | 7/22/2016 | | DONE |
|
|
|
|
BLD-Final | 7/21/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
Dave Hannah
|
|
|
Jason Phone #: ###-####
|
BLD-Final | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | PART |
Dave Hannah
|
|
|
Brandon Phone #: ###-#### ok for temp occ needs mec perm occ and sales cou nter installed
|
Zoning Approval | 6/22/2016 | 6/22/2016 | 6/22/2016 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 6/20/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, commercial hood suppression system inspection complete. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 6/13/2016 | 6/14/2016 | 6/14/2016 | A | PASS |
Dave Hannah
|
|
|
t-bar; Brandon Phone #: ###-####
|
BLD-Energy code compliance | 5/11/2016 | 5/11/2016 | 5/12/2016 | P | PASS |
Dave Hannah
|
|
|
Insulation // Brandon Phone #: ###-####
|
BLD-Framing/Rough-in | 5/10/2016 | 5/10/2016 | 5/11/2016 | P | PASS |
Dave Hannah
|
|
|
Brandon Phone #: ###-####
|
Print Occupancy Form | | | 4/15/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/15/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 4/4/2016 | | |
|
|
|
|
Plan assigned to (AJS) | 1/21/2016 | 1/21/2016 | 4/4/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - Manfred's
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/4/2016 | | DONE |
|
|
|
***ALL MET*** Needs; GC Form, Rev Cert of Value, RP
|
Routing - PLAN CHECK | 3/31/2016 | | 4/4/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 3/31/2016 | | 4/1/2016 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Design Review | 3/31/2016 | | 3/31/2016 | | PASS |
Josh Wilson
|
|
|
Ok per revised elevations on file with CZC16-00005
|
Routing - PLUMBING | 3/28/2016 | | 3/30/2016 | | CANC |
Bill VanDegrift
|
|
|
plumbing sheets revised
waiting for another revised set from engineer
|
Routing - PLAN CHECK | 3/21/2016 | | 3/30/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
pending planning approval
|
Routing - Design Review | 3/21/2016 | | 3/28/2016 | | FAIL |
Josh Wilson
|
|
|
Revised elevations do not match those approved with CZC16-00005.
|
Routing - MECHANICAL | 3/28/2016 | | 3/28/2016 | | PASS |
Troy James
|
|
|
redlined plans
|
Routing PW Environmental | 1/22/2016 | | 2/12/2016 | | PASS |
Rick Christenson
|
|
|
Grease Trap shown.
|
1st review completed | | | 2/12/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 1/21/2016 | | 2/12/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 1/21/2016 | | 1/28/2016 | | PASS |
Troy James
|
|
|
redlined plans
|
Routing - PLUMBING | 1/21/2016 | | 1/26/2016 | | PASS |
Bill VanDegrift
|
|
|
pipe condensate to indirect waste receptor
|
Routing - Design Review | 1/21/2016 | | 1/25/2016 | | PASS |
Josh Wilson
|
|
|
Ok per CZC16-00005
|
Routing - FIRE | 1/21/2016 | 1/21/2016 | 1/22/2016 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing - Erosion and Sediment | 1/21/2016 | | 1/22/2016 | | PASS |
Evan Jenkins
|
|
|
(MANFRED'S) Remodel for a 772sq ft kitchen and pick-up facility within an existing building. This is an independent space in the building shared with Woodland Empire Craft Brewing. Work to include structurally reinforcing the roof structure to support rooftop equipment, new Type I hood, kitchen equipment, concrete landing and ramp, walk-in cooler, interior finish, interior walls, mechanical work, plumbing work and electrical work.
|
Routing - Addressing | 1/21/2016 | | 1/22/2016 | | PASS |
Laura Hunter
|
|
|
Added suite number
|
Routing - PUBLIC WORKS | 1/21/2016 | | 1/22/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 1/21/2016 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Plan Reviewer's activity | | | 1/20/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
recieved call from Shawn at Trout Architects. The engineer is out of the office this week. Shawn will email me the engineering next week to up load.
|
Intake Approval | | | 1/13/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Items that are missing are indicated on the submittal check list.
|
Application received | | | 12/22/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 22 2015 11:30AM
|
Pending Assignment by JCB | 1/21/2016 | | | | |
Jason Blais
|
|
|
|