BLD-Final | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
DOC - Permit Finaled | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 7/26/2016 | 7/26/2016 | 7/26/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Framing/Rough-in | 7/22/2016 | 7/25/2016 | 7/25/2016 | A | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart. Truss bracing, Draft stop in floor trusses.
|
BLD-Wall Bracing | 6/2/2016 | 6/3/2016 | 6/3/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Wall Bracing | 5/19/2016 | 5/19/2016 | 5/19/2016 | A | PART |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart. OK to start sheetrock
|
BLD-Conference | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | DONE |
Phil Shearer
|
|
|
As early as possible Phone #: 4078920 >> Inspection requested via mobile web by Juan
|
BLD-Foundation | 3/30/2016 | 3/30/2016 | 3/30/2016 | P | PASS |
Phil Shearer
|
|
|
As early as possible Phone #: 4078920 >> Inspection requested via mobile web by Juan
|
BLD-Footing | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Phil Shearer
|
|
|
2:30 Phone #: ###-#### Inspection requested via web by tony L
|
BLD-Footing | 3/23/2016 | 3/24/2016 | 3/24/2016 | P | CANC |
Phil Shearer
|
|
|
4:00 Phone #: ###-#### Inspection requested via web by tony L
|
Issue PAID IN FULL permit | | | 3/16/2016 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/16/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 3/16/2016 | | 3/16/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
Plan assigned to (BJM) | 12/23/2015 | 12/23/2015 | 1/11/2016 | | DONE |
Brian McGowan
|
|
|
due 1/12 L2 townhouse
|
1st review completed | | | 1/11/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 1/11/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/11/2016 | | DONE |
|
|
|
all requirements met
|
Inspection Record Card- Bld | | | 1/11/2016 | | DONE |
|
|
|
|
Telephone call | | | 1/11/2016 | | DONE |
|
|
|
Told Amy when she was here that all 3 permits are ready
|
Routing - PLAN CHECK | 12/31/2015 | | 1/11/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 12/29/2015 | | 12/31/2015 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 12/31/2015 | | DONE |
|
|
|
Two copies of Sheets 2.0, 3.0, 4.0, 4.1, 5.0, 7.0, 7.2, 8.0 and 9.0 taken to Brian M
|
Routing - PLANNING | 12/23/2015 | | 12/29/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - Addressing | 12/22/2015 | | 12/23/2015 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/23/2015 | | 12/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan assigned to (LEG) Tisha | 12/22/2015 | | 12/23/2015 | | DEFR |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/22/2015 | | DONE |
|
|
|
|
Intake Approval | | | 12/22/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/22/2015 | | DONE |
|
|
|
|
Application received | | 12/22/2015 | | | |
|
|
|
|