BLD-Aging Inspection | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PEND |
Dave Hannah
|
|
|
still needs zoning finals
|
BLD-Aging Inspection | 9/28/2016 | 9/28/2016 | 9/29/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 9/27/2016 | 9/27/2016 | 9/29/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 5/11/2016 | 5/12/2016 | 5/16/2016 | P | FAIL |
Dave Hannah
|
|
|
Pat Phone #: ###-#### zoning failed
|
Zoning Approval | 5/12/2016 | 5/12/2016 | 5/12/2016 | | FAIL |
Matthew A Halitsky
|
|
|
Garage does not meet setbacks. Variance required.
|
BLD-Energy code compliance | 3/29/2016 | 3/29/2016 | 3/29/2016 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 3/25/2016 | 3/28/2016 | 3/29/2016 | A | PASS |
Dave Hannah
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 3/23/2016 | 3/23/2016 | 3/24/2016 | P | PEND |
Dave Hannah
|
|
|
Pat Phone #: ###-#### framing ok but need to know how we are going to vent roof ok to insulate
|
CHANGE STATUS TO (ISS) | | | 3/23/2016 | | DONE |
|
|
|
Plan Mod
|
OVERRIDE | | | 3/18/2016 | | |
|
|
|
|
Telephone call | | | 3/18/2016 | | DONE |
|
|
|
called Eva to let know permit is ready and how much is owed-left message on her phone
|
Routing - MECHANICAL | 3/17/2016 | | 3/18/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 3/18/2016 | | 3/18/2016 | | PASS |
Brian McGowan
|
|
|
Mechanical approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/18/2016 | | DONE |
|
|
|
Please do not re issue-plans in walk in drawer
|
BLD-Wall Bracing | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Jim Sly
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 2/1/2016 | 2/2/2016 | 2/2/2016 | A | PASS |
Dave Hannah
|
|
|
Shop in the back // Adam Phone #: ###-####
|
BLD-Conference | 1/19/2016 | 1/20/2016 | 1/30/2016 | A | DONE |
Dave Hannah
|
|
|
Pat// please call 1hr. before Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/6/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 1/5/2016 | | |
|
|
|
|
Telephone call | | | 1/5/2016 | | DONE |
|
|
|
called Eva to let know permit is ready and how much is owed-left message on her phone
|
Routing - PLAN CHECK | 12/24/2015 | | 1/5/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 1/5/2016 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 1/5/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/5/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/5/2016 | | DONE |
|
|
|
requirements met
|
1st review completed | | | 12/24/2015 | | FAIL |
Brian McGowan
|
|
|
Required more information on structure and stairs
|
Routing - PLAN CHECK | 12/24/2015 | | 12/24/2015 | | FAIL |
Brian McGowan
|
|
|
Required more information on stairs
|
Routing Walk-In (Zoning) | 12/23/2015 | 12/23/2015 | 12/23/2015 | P | DONE |
Brent Moore
|
|
|
|
Routing Walk-In (BLD) | 12/23/2015 | 12/23/2015 | 12/23/2015 | P | CANC |
Tisha Gallop
|
|
|
taken in by BJM
|
Application received | | 12/23/2015 | | | |
|
|
|
|