BLD-Final | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, no appliances allowed in upstairs above garage,, NOT AN ADU
|
DOC - Permit Finaled | 8/10/2016 | 8/10/2016 | 8/10/2016 | P | PASS |
Tony Young
|
|
|
c of o issued,, see prior notes on living space above garage
|
BLD-Final | 8/5/2016 | 8/9/2016 | 8/9/2016 | P | DEFR |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Final | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | NR |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, just needs driveway and landings,, no plans on site though,, upstairs of garage has habital space with rough in componets for cook stove and exhaust and gas stub out,, also sink drain stub,, all should have been inspected for rough in,,, owner said it is possible that they may apply for ADU at a later date..
|
BLD-Conference | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | CANC |
Tony Young
|
|
|
Dan Phone #: ###-#### >> Inspection requested via web by Daniel Appel Inspection cancelled from web by: Daniel Appel
|
BLD-Wall cover | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Energy code compliance | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 5/13/2016 | 5/16/2016 | 5/16/2016 | A | PART |
Tony Young
|
|
|
Please call Dan Would like to be onsite Phone #: ###-#### Inspection requested via web by Daniel Appel,, c/n listed on Dans paper,, ok to insulate
|
BLD-Framing/Rough-in | 5/13/2016 | 5/13/2016 | 5/13/2016 | P | DEFR |
Jim Storey
|
|
|
Please call Dan Would like to be onsite Phone #: ###-#### Inspection requested via web by Daniel Appel out of time
|
Plan Modification Accepted | | | 5/12/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 5/12/2016 | | 5/12/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Conference | 4/29/2016 | 5/2/2016 | 5/1/2016 | A | CANC |
Tony Young
|
|
|
Advice on HTT5 locations Phone #: ###-#### >> Inspection requested via web by Daniel Appel Inspection cancelled from web by: Daniel Appel
|
BLD-Wall Bracing | 4/27/2016 | 4/28/2016 | 4/28/2016 | A | PART |
Jim Sly
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel All Exterior shear nailing only......OK.
|
BLD-Conference | 4/27/2016 | 4/28/2016 | 4/27/2016 | A | CANC |
Tony Young
|
|
|
Call Dan Phone #: ###-#### >> Inspection requested via web by Daniel Appel Inspection cancelled from web by: Daniel Appel
|
BLD-Wall Bracing | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | NR |
Jim Sly
|
|
|
Please call Dan when 30 minutes out. He would like to be onsite during inspection. Phone #: ###-#### Inspection requested via web by Daniel Appel Need to complete blocking and exterior fastening. Builder to locate nailing table for brace panels on plan.
|
BLD-Wall Bracing | 4/25/2016 | 4/27/2016 | 4/26/2016 | A | CANC |
Tony Young
|
|
|
Dan Phone #: ###-#### >> Inspection requested via web by Daniel Appel Inspection cancelled from web by: Daniel Appel
|
BLD-Foundation | 4/5/2016 | 4/6/2016 | 4/6/2016 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Foundation | 4/4/2016 | 4/5/2016 | 4/5/2016 | P | NR |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 4/1/2016 | 4/4/2016 | 4/4/2016 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 4/1/2016 | 4/1/2016 | 4/1/2016 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, work in progress
|
Inspection Record Card- Bld | | | 2/8/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/8/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 1/13/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 1/4/2016 | 1/4/2016 | 1/13/2016 | | DONE |
Brian McGowan
|
|
|
due 1/14. Failed. Room over Garage has a full Kitchen proposed. No ADU was approved or filed for.
|
Routing - PLAN CHECK | 1/13/2016 | | 1/13/2016 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/13/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - MECHANICAL | 1/12/2016 | | 1/12/2016 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 1/7/2016 | | FAIL |
Brian McGowan
|
|
|
The Living space over the Garage contains a Kitchen, no ADU application or approval has been received.
|
Routing - MECHANICAL | 12/31/2015 | | 1/7/2016 | | FAIL |
Troy James
|
|
|
sent email to idaho hvac with correction
|
Routing - PLAN CHECK | 12/31/2015 | | 1/7/2016 | | FAIL |
Brian McGowan
|
|
|
Proposed home has and ADU over Garage. No application or approval has been provided.
|
Routing - Addressing | 12/31/2015 | | 1/4/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/31/2015 | | 1/4/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 12/31/2015 | | 1/4/2016 | | PASS |
Colleen T Carroll
|
|
|
Remove kitchen above garage or get an Accessory Dwelling Unit approval.
|
Plan assigned to (LEG) Tisha | 12/31/2015 | | 1/4/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Application received | | | 12/31/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 31 2015 11:21AM
|
Intake Approval | | | 12/31/2015 | | FAIL |
|
|
|
Missing ResCheck
|
Intake Approval | | | 12/31/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/31/2015 | | DONE |
|
|
|
|