Case Summary (BLD) | | | 3/31/2017 | | DONE |
|
|
|
|
Telephone call | | | 8/16/2016 | | DONE |
|
|
|
customer called said he paid final values on 8/2/16-i removed the open 3rd notice so he would not get another notice
|
Third Notice | | 7/19/2016 | 8/11/2016 | | DONE |
|
|
|
|
Print Statement | | | 7/18/2016 | | DONE |
|
|
|
|
Second Notice | | 6/20/2016 | 7/14/2016 | | DONE |
|
|
|
Mailed 7-15-16
|
First Notice | | 5/21/2016 | 6/10/2016 | | DONE |
|
|
|
Mailed 6-13-16
|
BLD-Final | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PASS |
Mike Jordan
|
|
|
Darrell/ please call 30 min prior Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy | | | 5/11/2016 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 4/28/2016 | 4/28/2016 | 4/28/2016 | P | PASS |
Mike Jordan
|
|
|
Call before // Darrell Phone #: ###-####
|
BLD-Framing/Rough-in | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Mike Jordan
|
|
|
would like a call two hours before you head out there // Darrell Phone #: ###-####. Received letter from architect stating that the indoor fancoil unit installed and supported by the roof truss system is acceptable. Will have letter scanned into case.
|
BLD-Framing/Rough-in | 3/4/2016 | 3/7/2016 | 3/7/2016 | A | DONE |
Mike Jordan
|
|
|
would like call ahead; Darrell Phone #: ###-####
|
BLD-Framing/Rough-in | 3/4/2016 | 3/4/2016 | 3/4/2016 | P | PASS |
Mike Jordan
|
|
|
Darrell Phone #: ###-####. Interior wood framed walls only. No grid. Stiil need engineering for HVAC support of floor joist.
|
BLD-Framing/Rough-in | 3/1/2016 | 3/2/2016 | 3/2/2016 | P | FAIL |
Mike Jordan
|
|
|
would like call ahead; Darrell Phone #: ###-####. Foam all top plate penetrations in wood stud wall. Provide engineering to show that bottom chords of roof joist will support the suspended HVAC ubit.
|
CHANGE STATUS TO (ISS) | | | 3/1/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/1/2016 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 2/10/2016 | 2/10/2016 | 2/26/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
plan mod review completed
|
Routing - MECHANICAL | 2/25/2016 | | 2/26/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 2/26/2016 | | 2/26/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/26/2016 | | DONE |
|
|
|
****requirements met CAN****Need Revised Cert of Value DO NOT RE ISSUE PLAN MOD
|
Print Occupancy Form | | | 2/26/2016 | | DONE |
|
|
|
|
Telephone call | | | 2/26/2016 | | DONE |
|
|
|
called Darrell to let know permit is ready and how much is owed-please do not re-issue-print new permit-have customer sign
|
Plan resubmittals received | | | 2/25/2016 | | DONE |
|
|
|
received two copies of sheet A-3.0- gave to Adele
|
Routing - PLAN CHECK | 2/11/2016 | | 2/16/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
pending mechanical
|
Routing - MECHANICAL | 2/11/2016 | | 2/11/2016 | | FAIL |
Troy James
|
|
|
emailed corrections to applicant
|
Plan Modification Accepted | | | 2/10/2016 | | DONE |
|
|
|
plan mod received 2 sets of sheet A-3.0 & air system sizing summary-took to Adele
|
Issue PAID IN FULL permit | | | 1/11/2016 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 12/31/2015 | 12/31/2015 | 1/6/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 1/5/2016 | | 1/6/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 1/6/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/6/2016 | | DONE |
|
|
|
NEED GC form and certificate of value from GC
|
Print Occupancy Form | | | 1/6/2016 | | DONE |
|
|
|
|
Telephone call | | | 1/6/2016 | | DONE |
|
|
|
called Jerrod- let him know building permit was ready and need GC form and Certificate of value-- also let him know Early start is ready, fees due, and need GC form
|
1st review completed | | | 1/6/2016 | | DONE |
Jason Blais
|
|
|
|
Routing - PUBLIC WORKS | 12/31/2015 | | 1/5/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 12/31/2015 | | 1/4/2016 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/31/2015 | | DONE |
|
|
|
|
Intake Approval | | | 12/31/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/31/2015 | | DONE |
|
|
|
|
Application received | | 12/31/2015 | | | |
|
|
|
|