BLD-Final | 8/23/2016 | 8/24/2016 | 8/24/2016 | A | PASS |
Tony Young
|
|
|
Status. Inspection report provided.,, ok per J.T.
|
DOC - Permit Finaled | 8/24/2016 | 8/24/2016 | 8/24/2016 | P | PASS |
Tony Young
|
|
|
|
BLD-Conference | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | S |
Tony Young
|
|
|
Status?
|
Extend Permit 90/180 days | 7/1/2016 | 7/5/2016 | 7/5/2016 | A | PEND |
Tony Young
|
|
|
Project completed? Special inspection report provided? status review
|
BLD-Conference | 6/27/2016 | 7/1/2016 | 7/1/2016 | P | PEND |
Dave Hannah
|
|
|
Project completed? Special inspection report provided? status review
|
BLD-Other | 6/27/2016 | 6/27/2016 | 6/27/2016 | P | PEND |
Tony Young
|
|
|
Project completed? Special inspection report provided?,, left a card to call me,, nothing called in so far
|
BLD-Foundation | 4/13/2016 | 4/14/2016 | 4/15/2016 | P | CANC |
Tony Young
|
|
|
Call prior to going Phone #: 4078920 >> Inspection requested via mobile web by Juan,, wrong permit
|
BLD-Footing | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | CANC |
Tony Young
|
|
|
As early as possible Phone #: 4078920 >> Inspection requested via mobile web by Juan// called in wrong permit number
|
Issue PAID IN FULL permit | | | 2/26/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 2/24/2016 | | |
|
|
|
|
Telephone call | | | 2/24/2016 | | DONE |
|
|
|
called ABC- told receptionist that permit is ready and fees due
|
Routing PW Grading-Hillside | 2/23/2016 | | 2/24/2016 | | PASS |
Jason C. Taylor
|
|
|
Received all required engineering documents as request. Approval is for lower repairs only. No repairs on the upper level is allowed. JCT
|
Plan assigned to (LEG) Tisha | 1/26/2016 | | 2/24/2016 | | DONE |
Tisha Gallop
|
|
|
1st review 2/2 walk - in failed Jason Taylor
|
Inspection Record Card- Bld | | | 2/24/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/24/2016 | | 2/24/2016 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/24/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/24/2016 | | DONE |
|
|
|
need RP all other requirements met
|
Case Summary (BLD) | | | 2/23/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/23/2016 | | DONE |
|
|
|
resubmittals recieved forensic investigation report-took to Tisha
|
Telephone call | | | 2/2/2016 | | DONE |
|
|
|
called and spoke with Cassandra at ABC Seamless for plan corrections required.
|
Routing - PLAN CHECK | 2/1/2016 | | 2/2/2016 | | FAIL |
Tisha Gallop
|
|
|
per comments from PW Grading-Hilliside
|
1st review completed | | | 2/2/2016 | | FAIL |
|
|
|
|
Routing - Erosion and Sediment | 2/1/2016 | | 2/1/2016 | | PASS |
Evan Jenkins
|
|
|
Foundation Work on SFH: very little earth disturbance anticipated.
|
Routing PW Grading-Hillside | 1/26/2016 | | 2/1/2016 | | FAIL |
Jason C. Taylor
|
|
|
Need additional information from geotechncial engineer. Called Applicant and owner to discuss why we need additional information. Geotechncial Engineer needs to find out how the how the home has settled and verify that current plan is accepatble. Jason Taylor ###-####
|
Telephone call | | | 1/28/2016 | | DONE |
|
|
|
called Steve the GC after talking to Jason Tayler to let him know Jason Taylor is going to have a meeting with the building official about issues with the plans-Steve said ok
|
Routing - PLANNING | 1/26/2016 | | 1/26/2016 | | PASS |
Josh Wilson
|
|
|
Ok per R-1B
|
Plans ACCEPTED BY PLAN TECH | | | 1/26/2016 | | DONE |
|
|
|
|
Intake Approval | | | 1/26/2016 | | PASS |
|
|
|
as per Jason Taylor
|
Recd Pcfee & Taken To Pln CK | | | 1/26/2016 | | DONE |
|
|
|
|
Routing Walk-In (PW Hillside) | 1/22/2016 | 1/22/2016 | 1/22/2016 | A | FAIL |
Jason C. Taylor
|
|
|
NEEDS GEOTECH AND STRUCTURAL REVIEW. INTAKE AND ROUTE TO HILLSIDE. JCT
|
Routing Walk-In (PW Hillside) | 1/5/2016 | 1/5/2016 | 1/12/2016 | P | FAIL |
Jason C. Taylor
|
|
|
|
Routing Walk-In (BLD) | 1/5/2016 | 1/5/2016 | 1/5/2016 | A | CANC |
Tisha Gallop
|
|
|
no contact
|
Application received | | 1/5/2016 | | | |
|
|
|
|