Permit Information
Permit NumberBLD16-00056
StatusFinaled
Name TAHOE HOMES LLC
Site Address 6119 W TOBI DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit for the construction of a new 2,574 sq. ft., two story (main level 1,142 sq. ft., upper level 1,432 sq. ft.) single family dwelling with 3 bedrooms, 2 and a half bathrooms, approximately 228 sq. ft. of covered patio/porch and a 863 sq. ft. attached garage per the approved plans, ResCheck, ACCA report and any notations. R-1B zoning and setbacks per planning. //leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/3/20166/3/20166/3/2016PPASS
DetailsTony Young
Garage code 1001 Phone #: ###-#### Inspection requested via web by Paul Fedorchuk
DOC - Permit Finaled6/3/20166/3/20166/3/2016PPASS
DetailsTony Young
c of o issued
BLD-Conference6/2/20166/3/20166/3/2016APASS
DetailsTony Young
Garage code 1001 Phone #: ###-#### Inspection requested via web by Paul Fedorchuk
BLD-Energy code compliance3/18/20163/21/20163/21/2016APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Paul Fedorchuk
BLD-Framing/Rough-in3/16/20163/17/20163/17/2016APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Paul Fedorchuk
BLD-Wall Bracing2/24/20162/25/20162/25/2016APASS
DetailsTony Young
Luna Phone #: ###-####
BLD-Foundation2/1/20162/1/20162/1/2016PPART
DetailsTony Young
request time 12:30 Phone #: ###-#### Inspection requested via web by tony L
BLD-Foundation1/29/20162/1/20162/1/2016APART
DetailsTony Young
request time 11:30 Phone #: ###-#### Inspection requested via web by tony L
BLD-Footing1/28/20161/29/20161/29/2016APART
DetailsTony Young
request time 11:30 Phone #: ###-#### Inspection requested via web by tony L// work in progress
Issue PAID IN FULL permit  1/25/2016 DONE
OVERRIDE  1/22/2016  
Inspection Record Card- Bld  1/22/2016 DONE
Telephone call  1/22/2016 DONE
called Tahoe- left message that permits are ready for pick up and fees due
Permit Ready to Issue  1/22/2016 DONE
requirements met
1st review completed  1/21/2016 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/21/2016 DONE
Case Summary (BLD)  1/21/2016 DONE
Plan assigned to (LEG) Tisha1/7/2016 1/21/2016 DONE
DetailsTisha Gallop
1/21
Routing - PLAN CHECK1/12/2016 1/21/2016 PASS
DetailsTisha Gallop
Routing - MECHANICAL1/8/2016 1/12/2016 PASS
DetailsTroy James
Routing - PLANNING1/7/2016 1/8/2016 PASS
DetailsTodd Tucker
Plans ACCEPTED BY PLAN TECH  1/7/2016 DONE
Intake Approval  1/7/2016 PASS
Recd Pcfee & Taken To Pln CK  1/7/2016 DONE
Routing - Addressing1/7/2016 1/7/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS1/7/2016 1/7/2016 PASS
DetailsRachael Beierle
Application received 1/7/2016