BLD-Final | 5/9/2016 | 5/9/2016 | 5/9/2016 | P | PASS |
Jim Sly
|
|
|
Call Dan for access Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 5/9/2016 | 5/9/2016 | 5/9/2016 | P | PASS |
Jim Sly
|
|
|
|
PubWorks Occupancy Approval | 5/4/2016 | 5/4/2016 | 5/4/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Wall cover | 3/25/2016 | 3/28/2016 | 3/29/2016 | P | PASS |
Jim Sly
|
|
|
Late PM please Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Energy code compliance | 3/25/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Jim Sly
|
|
|
Late PM please Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Jim Sly
|
|
|
Call Dan for Gate access code if it is closed. Phone #: ###-#### Inspection requested via web by Daniel Appel
|
Routing - MECHANICAL | 3/22/2016 | | 3/22/2016 | | PASS |
Chad Schwendiman
|
|
|
revised manual J
|
BLD-Wall Bracing | 3/17/2016 | 3/17/2016 | 3/17/2016 | P | PASS |
Jim Sly
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Foundation | 3/10/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Jim Sly
|
|
|
Jerry Phone #: ###-####
|
BLD-Footing | 3/9/2016 | 3/10/2016 | 3/10/2016 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
PubWorks Subgrade Approval | 3/10/2016 | 3/10/2016 | 3/10/2016 | | DONE |
Jason C. Taylor
|
|
|
* ENTIRE FOOTING NO COLUMNS***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 3/7/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/4/2016 | | |
|
|
|
|
Plan assigned to (DAF) | 2/29/2016 | 2/29/2016 | 3/4/2016 | | DONE |
David Ferguson
|
|
|
due 3/15 L2 Hillside
|
1st review completed | | | 3/4/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2016 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/4/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 3/4/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - PLANNING | 2/23/2016 | | 3/4/2016 | | PASS |
Leon Letson
|
|
|
|
Routing - PLAN CHECK | 2/23/2016 | | 3/4/2016 | | PASS |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 2/23/2016 | | 2/29/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - FIRE | 2/23/2016 | 2/23/2016 | 2/26/2016 | | PASS |
Scott Arellano
|
|
|
No separate comments attached. The existing private electronically operatated security gate shall be fitted with the opticom system for fire department access.
|
Routing PW Grading-Hillside | 2/23/2016 | | 2/25/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 2/23/2016 | | 2/24/2016 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 2/23/2016 | | 2/24/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/23/2016 | | 2/24/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 2/23/2016 | | 2/24/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Permit for the construction of a new 1461 sq. ft., one story single family dwelling with 2 bedrooms, 2 bathrooms, approximately *** sq. ft. of covered patio/porch and a 476 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning.
|
Plans ACCEPTED BY PLAN TECH | | | 2/23/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/23/2016 | | PASS |
Christina Prado
|
|
|
|
Override - Parcel Holds | | | 2/23/2016 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/23/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/18/2016 | | FAIL |
Christina Prado
|
|
|
See corrections in attached failed checklist
|
Application received | | | 1/11/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 11 2016 2:42PM
|