BLD-Final | 3/14/2016 | 3/15/2016 | 3/15/2016 | P | DONE |
Mike Jordan
|
|
|
Install new pole sign. All Primary power by others Phone #: ###-#### Inspection requested via web by Ken Olsen
|
DOC - Permit Finaled | 3/15/2016 | 3/15/2016 | 3/15/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 3/10/2016 | 3/10/2016 | 3/10/2016 | A | CANC |
Mike Jordan
|
|
|
Please schedule for 11:30 am as we are trying to schedule a concrete pour. Phone #: ###-#### Inspection requested via web by Ken Olsen. Wron inspection, disregard this entry.
|
BLD-Footing | 3/7/2016 | 3/10/2016 | 3/10/2016 | A | PASS |
Mike Jordan
|
|
|
Please schedule for 11:30 am as we are trying to schedule a concrete pour. Phone #: ###-#### Inspection requested via web by Ken Olsen
|
BLD-Footing | 3/3/2016 | 3/7/2016 | 3/7/2016 | A | CANC |
Mike Jordan
|
|
|
Please Schedule for 11:30 am as we are trying to schedule a concrete pour. Travis is the on site contact @ ###-#### Phone #: ###-#### >> Inspection requested via web by Ken Olsen Inspection cancelled from web by: Ken Olsen
|
Plan assigned to (AJS) | 1/13/2016 | 1/13/2016 | 1/22/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Jackes Fitness Sign
|
Routing - PLAN CHECK | 1/22/2016 | | 1/22/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/22/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/22/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/13/2016 | | 1/13/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 1/13/2016 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 1/13/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 1/11/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 11 2016 3:14PM
|
First Notice | 3/15/2016 | 3/15/2016 | | | |
Mike Jordan
|
|
|
|