BLD-Final | 11/18/2016 | 11/21/2016 | 11/22/2016 | P | PASS |
Jim Sly
|
|
|
Dan-please call to meet Phone #: ###-####
|
DOC - Permit Finaled | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 9/1/2016 | 9/1/2016 | 9/2/2016 | P | PASS |
Jim Sly
|
|
|
Ira Phone #: ###-####
|
BLD-Framing/Rough-in | 8/29/2016 | 8/30/2016 | 8/30/2016 | P | PASS |
Jim Sly
|
|
|
Ira Phone #: ###-####
|
Plan Modification Accepted | | | 8/23/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/23/2016 | | 8/23/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 8/4/2016 | 8/4/2016 | 8/4/2016 | P | PASS |
Jim Sly
|
|
|
Bob Phone #: ###-####
|
BLD-Foundation | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | PASS |
Jim Sly
|
|
|
Bob Phone #: ###-####
|
BLD-Footing | 7/13/2016 | 7/14/2016 | 7/14/2016 | A | PASS |
Jim Sly
|
|
|
Bob Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/5/2016 | | DONE |
|
|
|
|
Expiration Notice | 6/17/2016 | 7/11/2016 | 6/17/2016 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 2/1/2016 | | |
|
|
|
|
Plan assigned to (DAF) | 1/22/2016 | 1/22/2016 | 2/1/2016 | | DONE |
David Ferguson
|
|
|
due 1/28 - Failed - need header sizes
|
Telephone call | | | 2/1/2016 | | DONE |
|
|
|
Spoke with Bryan informing him that the permit is ready and the fees due. Also informed him that we would need an RP for the ESC and he said he would speak with Ira
|
Plan resubmittals received | | | 2/1/2016 | | DONE |
|
|
|
received two copies of 11x17 calculations- gave to Dave
|
Routing - PLAN CHECK | 2/1/2016 | | 2/1/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 2/1/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 2/1/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/1/2016 | | DONE |
|
|
|
need RP
|
1st review completed | | | 1/29/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 1/21/2016 | | 1/29/2016 | | FAIL |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 1/14/2016 | | 1/22/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 1/19/2016 | | 1/21/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/19/2016 | | 1/19/2016 | | PASS |
Sue Cummings
|
|
|
Zoning Code rerquires 2 parking spaces per dwelling NOT located in the front 20' setback. The driveway needs to be poured 60' into the lot during construction OR 40' into the lot if it is18' wide
|
Routing - Addressing | 1/14/2016 | | 1/19/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/19/2016 | | 1/19/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/14/2016 | | DONE |
|
|
|
|
Intake Approval | | | 1/14/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/14/2016 | | DONE |
|
|
|
|
Application received | | 1/14/2016 | | | |
|
|
|
|