Third Notice | | 2/18/2017 | 3/9/2017 | | DONE |
Christina Prado
|
|
|
mailed 3/10/17
|
Second Notice | | 1/20/2017 | 2/13/2017 | | DONE |
|
|
|
Mailed 2-14-17
|
First Notice | | 12/27/2016 | 1/10/2017 | | DONE |
|
|
|
Mailed 1-11
|
BLD-Final | 12/12/2016 | 12/16/2016 | 12/16/2016 | A | PASS |
Mike Jordan
|
|
|
Please call ahead for access - James Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 12/16/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/8/2016 | 12/12/2016 | 12/12/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The owner is going to change out the exit sign at the main door to a combo exit sign/emergency light. I requested that he verify functionality with the building inspector.
|
Meeting | | | 10/10/2016 | | DONE |
|
|
|
first notice printed out but permit is still in ISS status so i did not send out notice
|
BLD-Final | 9/8/2016 | 9/9/2016 | 9/12/2016 | P | NR |
Mike Jordan
|
|
|
James Phone #: ###-####
|
FIRE-Final Inspection | 9/8/2016 | 9/9/2016 | 9/9/2016 | A | FAIL |
Troy Cobbley
|
|
|
Provide racking permit for storage racks over 8'-0", All storage to remain under 12'-0" (6'-0") or a high pile permit is required, Provide exit sign on second floor, Repair all exit signs and emregency lights, Provide sprinkler protection under the new door and platform.
|
DOC - Permit Finaled | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | CANC |
Mike Jordan
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
CHANGE STATUS TO (ISS) | | | 9/9/2016 | | DONE |
|
|
|
Permit put into FNL status by mistake after letter of complience was issued in error
|
BLD-Final | 8/31/2016 | 9/7/2016 | 9/7/2016 | P | FAIL |
Mike Jordan
|
|
|
James Phone #: ###-####. tenant to provide city approved plans. Per tenant architect is working racking permit to submit for review. Once tenant has approved plans, they will schedule a building conferance. Also noted work in adjacent building. Per tenant architect is working on those plans as well. Noted that mech contractor has pulled his prmit for work in adjacent building.
|
Case Summary (BLD) | | | 9/6/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/6/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | FAIL |
Troy Cobbley
|
|
|
No approved plans or small documents on site. I went over general life safety requirements with the Operations Manager. It appears a racking permit will be required.
James Phone #: ###-####
|
Case Summary (BLD) | | | 7/18/2016 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 7/18/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/18/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/1/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/1/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/28/2016 | | |
|
|
|
|
Plan assigned to (JG) | 3/15/2016 | 3/15/2016 | 3/28/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, Plan Mod Patrick Industries, pending ESC
|
Routing - PLAN CHECK | 3/28/2016 | | 3/28/2016 | | PASS |
Javier Guzman
|
|
|
|
Routing - Erosion and Sediment | 3/28/2016 | | 3/28/2016 | | PASS |
Evan Jenkins
|
|
|
**( PATRICK INDUSTRIES)** //Plan modification to add a mechanical dust collection system at the warehouse area, to remove warehouse restrooms and to enlarge existing 10’ x 10’ exterior overhead door to a 16’ x 16’ exterior overhead door.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2016 | | DONE |
Christina Prado
|
|
|
All requirements met 6/1/16///C_P
need RP and GC
|
Routing - Erosion and Sediment | 3/18/2016 | | 3/22/2016 | | FAIL |
Evan Jenkins
|
|
|
Due to the removing 4,800 sq. ft. of asphalt and pouring in concrete, a Full ESC Narrative and Site Map is Required.
Evan Jenkins 794.3958
|
Routing - PLAN CHECK | 3/18/2016 | | 3/18/2016 | | FAIL |
Javier Guzman
|
|
|
ePlan Need form 310 Special Inspection
|
Routing PW Drainage | 3/18/2016 | | 3/18/2016 | | PASS |
Brian Murphy
|
|
|
No Review required per ePlan sign off by Brian Murphy
|
Routing - Design Review | 3/16/2016 | | 3/18/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS GRADING | 3/16/2016 | | 3/18/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 3/16/2016 | | 3/16/2016 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 3/15/2016 | | 3/15/2016 | | PASS |
Rachael Beierle
|
|
|
Verified with Rick in Enviromental during 1st submission- no PW Enviromental review is needed.
|
Plan Modification Accepted | | | 3/15/2016 | | DONE |
Christina Prado
|
|
|
Revisions requested for changes to overhead door enlargement and fire comments
|
Routing - FIRE | 1/29/2016 | 1/29/2016 | 1/29/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case and emailed architect on advising owner/tenant of racking restrictions unless further building modifications are completed.
|
Plan assigned to (JG) | 1/19/2016 | 1/19/2016 | 1/29/2016 | | PASS |
Javier Guzman
|
|
|
1st review completed, 1/25 L1 Patrick Industries ePlan
|
Routing - PLAN CHECK | 1/29/2016 | | 1/29/2016 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/29/2016 | | DONE |
Christina Prado
|
|
|
Need GC form & certificate of value for issuance
|
Routing - PLAN CHECK | 1/19/2016 | | 1/21/2016 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
1st review completed | | | 1/21/2016 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 1/19/2016 | 1/19/2016 | 1/20/2016 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Intake Approval | | | 1/19/2016 | | PASS |
David Ferguson
|
|
|
|
Routing - Addressing | 1/19/2016 | | 1/19/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/19/2016 | | 1/19/2016 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 1/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 15 2016 10:51AM
|