Print Statement | | | 2/6/2018 | | DONE |
Christina Prado
|
|
|
|
Print Statement | | | 2/6/2018 | | DONE |
|
|
|
|
Third Notice | | 11/19/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Second Notice | | 10/22/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
First Notice | | 10/1/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
PubWorks Occupancy Approval | 9/21/2017 | 9/21/2017 | 9/21/2017 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 9/21/2017 | | DONE |
|
|
|
|
BLD-Final | 9/15/2017 | 9/15/2017 | 9/18/2017 | P | PASS |
Dave Hannah
|
|
|
Pending PW and ACHD sign off
|
Print Occupancy Form | | | 9/15/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/15/2017 | | DONE |
|
|
|
|
BLD-Conference | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PEND |
Dave Hannah
|
|
|
Sending this per Alex - Please contact Travis to see where they are at with coming in for either a TCO or CO... Pending items - ADA doors, state elevator insp, PW insp and ACHD sign off....Travis @ ###-####
|
BLD-Conference | 8/17/2017 | 8/17/2017 | 8/24/2017 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 4/3/2017 | 4/3/2017 | 4/3/2017 | | PASS |
Sarah Schafer
|
|
|
|
BLD-Conference | 2/21/2017 | 2/22/2017 | 2/27/2017 | A | DONE |
Dave Hannah
|
|
|
ADA conference Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 2/21/2017 | 2/21/2017 | 2/21/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | CANC |
Mike Jordan
|
|
|
ADA door clearance conference Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 2/14/2017 | 2/15/2017 | 2/15/2017 | A | PASS |
Dave Hannah
|
|
|
Laundry chute cover Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Final | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PART |
Dave Hannah
|
|
|
5th and 6th floors TCO Phone #: ###-#### Inspection requested via web by Mike Beeson 5th and 6th floor ok for temp occ
|
FIRE-Final Inspection | 2/8/2017 | 2/8/2017 | 2/8/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, final fire alarm inspection is complete, fire extinguishers are in place with current inspection tags, knox box is in place and emergency egress lighting has been tested/inspected. Final life fire safety inspection passed/complete.
|
FIRE-Supply Line Cover | 2/7/2017 | 2/8/2017 | 2/8/2017 | P | CANC |
Jim Page
|
|
|
Inspection request is for life fire safety final, this inspection request cancelled and the correct inspection request generated.
|
BLD-Conference | 2/4/2017 | 2/6/2017 | 2/6/2017 | A | PASS |
Dave Hannah
|
|
|
Review ADA, and laundry shoot cover Phone #: ###-#### Inspection requested via web by Mike Beeson 5th and 6th floor shaft ok
|
BLD-Concrete | 2/3/2017 | 2/6/2017 | 2/6/2017 | A | CANC |
Dave Hannah
|
|
|
out of time friday 301
|
BLD-Conference | 2/3/2017 | 2/3/2017 | 2/3/2017 | P | DEFR |
Jim Storey
|
|
|
regarding ADA Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 2/1/2017 | 2/2/2017 | 2/2/2017 | A | PEND |
Dave Hannah
|
|
|
Discuss sign offs for 5th and 6th floors ; Review Laundry shoot framing Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 1/23/2017 | 1/24/2017 | 1/24/2017 | A | PEND |
Dave Hannah
|
|
|
walk through Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PASS |
Dave Hannah
|
|
|
Wall cover Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Final | 1/12/2017 | 1/13/2017 | 1/13/2017 | P | PART |
Dave Hannah
|
|
|
TCO 1-4 Phone #: ###-#### Inspection requested via web by Mike Beeson ok for tco.1-4
|
BLD-Wall cover | 1/12/2017 | 1/13/2017 | 1/13/2017 | A | CANC |
Dave Hannah
|
|
|
Wall cover Phone #: ###-#### Inspection requested via web by Mike Beeson
|
FIRE-Final Inspection | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PART |
Jim Page
|
|
|
Final inspection for TCO of levels i through 4 complete, fire sprinklers are complete through level 5, fire alarms are complete through level 4 with active fire alarms in the corridors of level 5, fire extinguishers are in place with current inspection tags, knox box is in place, remainder of building will be inspected at a later date.
|
BLD-Wall cover | 1/12/2017 | 1/12/2017 | 1/13/2017 | P | NR |
Dave Hannah
|
|
|
Cover for last two penthouse suite''s on 6. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 1/11/2017 | 1/11/2017 | 1/13/2017 | P | NR |
Dave Hannah
|
|
|
Floor 1-4 Phone #: ###-#### Inspection requested via web by Mike Beeson
|
FIRE-Supply Line Cover | 1/11/2017 | 1/11/2017 | 1/11/2017 | P | CANC |
Jim Page
|
|
|
A voicemail was left on the point of contacts cell phone, Mike at ###-####, this inspection request is cancelled, fire alarms for levels 4 and 5 plus rooms on level 3 have not been tested/inspected, this needs to be completed before life sfatey inspection can be performed for TCO of levels 1-4. Need to verify if fire sprinkler inspections have been completed for levels 1 through 5 for TCO before life safety inspection as well.
|
BLD-Conference | 1/9/2017 | 1/10/2017 | 1/10/2017 | A | PEND |
Dave Hannah
|
|
|
Pre-walk for floors 1-4 and floors above egress. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 1/5/2017 | 1/6/2017 | 1/6/2017 | A | PASS |
Dave Hannah
|
|
|
Fire caulk corridor lid on 6th floor on Capitol and framing Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 12/30/2016 | 12/30/2016 | 12/31/2016 | P | PASS |
Dave Hannah
|
|
|
6th floor Captiol light gauge, site egress event night Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 12/28/2016 | 12/28/2016 | 12/28/2016 | P | PASS |
Dave Hannah
|
|
|
Egress in lobby and alley cleared. 6th floor myrtle cover in hallway Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 12/27/2016 | 12/27/2016 | 12/28/2016 | P | PASS |
Dave Hannah
|
|
|
Insulation for the last two rooms on 6th floor Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 12/22/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Dave Hannah
|
|
|
Walk on floors 1-3 egress and signage for limited TCO event on the 31st. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
FIRE-Final Inspection | 12/20/2016 | 12/20/2016 | 12/20/2016 | P | PART |
Jim Page
|
|
|
Partial final life fire safety inspection for TCO complete for levels 1 and 2, fire sprinkler inspection complete (fire sprinklers are active) for fire pump room as well as levels 1, 2 and 3 fire sprinklers including wet standpipes for both east and west stairwells, fire alarm inspection complete for levels 1, 2 and 3 (was instructed at time of alarm inspection that fire panel will be monitored for the requested occupied area's) including automatic function for stairwell pressurization. Temporary fire extinguishers are in place for levels 1, 2 and 3, permanent extinguishers will be put in place at a later date, knox box is in place, final inspection for commercial hood fire suppression system complete. Partial final inspection for TCO inspection complete.
|
FIRE-Supply Line Cover | 12/20/2016 | 12/20/2016 | 12/20/2016 | P | CANC |
Jim Page
|
|
|
Inspection request is for TCO inspection for levels 1,2 and 3, this inspection request is cancelled and the correct inspection request will be generated.
|
BLD-Other | 12/19/2016 | 12/19/2016 | 12/20/2016 | A | PART |
Dave Hannah
|
|
|
Walk floors 1-3 Phone #: ###-#### Inspection requested via web by Mike Beeson ok to train house cleaning staff on 1st and second floors they will be wearing saftey vest and hard hats and have gone thruogh safty orintaion.
|
BLD-Wall cover | 12/14/2016 | 12/15/2016 | 12/16/2016 | P | PASS |
Dave Hannah
|
|
|
Cover on 6 Myrtle, Phone #: ###-#### Inspection requested via web by Mike Beeson fur down soffits
|
BLD-Ceiling Grid Inspection | 12/14/2016 | 12/14/2016 | 12/14/2016 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson first floor ok
|
BLD-Framing/Rough-in | 12/12/2016 | 12/12/2016 | 12/13/2016 | P | PART |
Dave Hannah
|
|
|
6th floor Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 12/8/2016 | 12/9/2016 | 12/12/2016 | A | NR |
Dave Hannah
|
|
|
fire caulking, cover on 6th Myrtle Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 12/2/2016 | 12/2/2016 | 12/9/2016 | P | PASS |
Dave Hannah
|
|
|
6th floor insulation Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 12/7/2016 | 12/8/2016 | 12/8/2016 | A | PASS |
Dave Hannah
|
|
|
Ceiling grid and fire caulking Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 12/6/2016 | 12/6/2016 | 12/6/2016 | P | FAIL |
Dave Hannah
|
|
|
ceiling grid Phone #: ###-#### Inspection requested via web by Mike Beeson 2nd floor
|
BLD-Conference | 12/4/2016 | 12/5/2016 | 12/5/2016 | P | CANC |
Dave Hannah
|
|
|
Grid inspections, partial garage, 1st and 2nd floors Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Dave Hannah
|
|
|
Shafts on 5th Phone #: ###-#### Inspection requested via web by Mike Beeson
|
FIRE-Hydro test above ground | 11/21/2016 | 11/22/2016 | 11/22/2016 | A | DONE |
Jim Page
|
|
|
Inspection request was a fire conference, fire conference is complete.
|
BLD-Framing/Rough-in | 11/21/2016 | 11/21/2016 | 11/22/2016 | A | PASS |
Dave Hannah
|
|
|
5th floor Capitol Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 11/21/2016 | 11/21/2016 | 11/22/2016 | P | PASS |
Dave Hannah
|
|
|
5th floor Capitol Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | PASS |
Dave Hannah
|
|
|
Fire caulk on 5, shaft walls Phone #: ###-#### Inspection requested via web by Mike Beeson and corradors ok to cover
|
BLD-Conference | 11/14/2016 | 11/14/2016 | 11/14/2016 | A | PART |
Mike Jordan
|
|
|
Cover on 6 Phone #: ###-#### Inspection requested via web by Mike Beeson. Ceiling, ok to rock 4ft from top.
|
BLD-Wall cover | 11/9/2016 | 11/10/2016 | 11/14/2016 | A | PART |
Dave Hannah
|
|
|
5th floor Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 11/9/2016 | 11/10/2016 | 11/14/2016 | P | CANC |
Dave Hannah
|
|
|
6th floor Pre lid and exterior walls Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 11/8/2016 | 11/8/2016 | 11/8/2016 | A | PASS |
Dave Hannah
|
|
|
5th floor shaft walls Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 11/7/2016 | 11/7/2016 | 11/7/2016 | A | NR |
Dave Hannah
|
|
|
Shaft walls and fire collars on 5 Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 11/3/2016 | 11/4/2016 | 11/4/2016 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson 5th floor shafths
|
BLD-Wall cover | 11/3/2016 | 11/4/2016 | 11/4/2016 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson 4th floor
|
BLD-Framing/Rough-in | 11/2/2016 | 11/3/2016 | 11/4/2016 | A | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 11/1/2016 | 11/2/2016 | 11/2/2016 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson 4th floor hall way ceilings ok to cover mertal side and 6th floor hallway
|
BLD-Conference | 10/31/2016 | 11/1/2016 | 11/1/2016 | A | PASS |
Dave Hannah
|
|
|
AM inspection on Collars, fire caulking and insulation Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 10/27/2016 | 10/28/2016 | 10/31/2016 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 10/25/2016 | 10/26/2016 | 10/26/2016 | A | PEND |
Dave Hannah
|
|
|
Review Fire caulking (Hilti engineered judgement) Spec''s Phone #: ###-#### Inspection requested via web by Mike Beeson
|
Telephone call | | | 10/26/2016 | | DONE |
|
|
|
Reminded fire protection contractor the pump has to be connected to an emergency gernerator on this project due to a code alternate. Also left a message for the field inspector.
|
BLD-Conference | 10/24/2016 | 10/25/2016 | 10/25/2016 | A | PART |
Dave Hannah
|
|
|
Re-try fire caulk inspection and shafts on 4th floor. Phone #: ###-#### Inspection requested via web by Mike Beeson east wing ok
|
BLD-Wall cover | 10/24/2016 | 10/24/2016 | 10/24/2016 | P | CANC |
Dave Hannah
|
|
|
Fire Caulk on 4th lid Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 10/24/2016 | 10/24/2016 | 10/24/2016 | P | NR |
Dave Hannah
|
|
|
4th floor Myrtle cover Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 10/21/2016 | 10/24/2016 | 10/24/2016 | A | NR |
Dave Hannah
|
|
|
Fire Caulk on 4th lid Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 10/20/2016 | 10/20/2016 | 10/21/2016 | P | PASS |
Dave Hannah
|
|
|
Shaft walls on 4th Myrtle Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 10/14/2016 | 10/14/2016 | 10/14/2016 | A | PASS |
Phil Shearer
|
|
|
Framing on lid on 3, fire caulking on 3 above lids. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 10/12/2016 | 10/13/2016 | 10/13/2016 | P | PASS |
Jim Storey
|
|
|
Insulation on exterior walls on 5th floor.exterior and shafts as noted on plan Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Ceiling Grid Inspection | 10/11/2016 | 10/12/2016 | 10/12/2016 | P | NR |
Jim Storey
|
|
|
Insulation on 5th floor and cover on 3rd floor. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Ceiling Grid Inspection | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | CANC |
Jim Storey
|
|
|
Cover on 2nd floor Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 10/10/2016 | 10/11/2016 | 10/11/2016 | P | NR |
Dave Hannah
|
|
|
Cover on 3 and 4, Insulation on 5 Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Wall cover | 10/4/2016 | 10/5/2016 | 10/5/2016 | A | PASS |
Dave Hannah
|
|
|
shaft wall and fire caulking floors 2 and 3 Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 10/3/2016 | 10/3/2016 | 10/4/2016 | P | PASS |
Dave Hannah
|
|
|
2nd floor shaft wall and fire caulking Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 9/30/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Dave Hannah
|
|
|
Fire caulking on 3 for cover.
Phone #: ###-#### Inspection requested via web by Mike Beeson myrdel side ok
|
BLD-Wall cover | 9/27/2016 | 9/28/2016 | 9/29/2016 | P | PART |
Dave Hannah
|
|
|
1st floor hard lids, 3rd floor walls and walk 4th floor Phone #: ###-#### Inspection requested via web by Mike Beeson. First floor hard lids ok 3rd fl fail
|
BLD-Framing/Rough-in | 9/26/2016 | 9/27/2016 | 9/27/2016 | P | PART |
Dave Hannah
|
|
|
cover on the 3rd Phone #: ###-#### Inspection requested via web by Mike Beeson 3rd floor fail first floor lobby ok
|
BLD-Framing/Rough-in | 9/16/2016 | 9/19/2016 | 9/19/2016 | A | PASS |
Dave Hannah
|
|
|
Capitol side insulation on 4th floor and third floor framing Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 9/14/2016 | 9/15/2016 | 9/15/2016 | A | PART |
Dave Hannah
|
|
|
Insulation and framing Phone #: ###-#### Inspection requested via web by Mike Beeson ext walls myrtle end insulation ok ok to cover walls room side
|
BLD-Framing/Rough-in | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | DEFR |
Jim Storey
|
|
|
Insulation and framing Phone #: ###-#### Inspection requested via web by Mike Beeson to dave am out of time
|
BLD-Other | 9/6/2016 | 9/7/2016 | 9/8/2016 | A | PART |
Dave Hannah
|
|
|
Fire caulking, approved to cover from Mechanical. Need approval to rock 2nd floor complete. Phone #: ###-#### Inspection requested via web by Mike Beeson eastwing ok to cover walls
|
BLD-Framing/Rough-in | 9/6/2016 | 9/6/2016 | 9/6/2016 | A | PEND |
Dave Hannah
|
|
|
2nd floor, 3rd floor, 6th and roof Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Energy code compliance | 8/23/2016 | 8/24/2016 | 8/30/2016 | P | PASS |
Dave Hannah
|
|
|
Rock-wool and fire proofing on second floor and short conference talk Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Energy code compliance | 8/17/2016 | 8/17/2016 | 8/17/2016 | P | PASS |
Mike Jordan
|
|
|
Exterior insulation on floors 2 and 3 Myrtle Phone #: ###-#### Inspection requested via web by Mike Beeson. Floors 2 and 3, exterior walls (east half) ok to sheet rock only. Furred out fireplace framing to remaing uncovered at this time.
|
BLD-Framing/Rough-in | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Wesley Harrison
|
BLD-Energy code compliance | 8/4/2016 | 8/5/2016 | 8/5/2016 | P | PEND |
Dave Hannah
|
|
|
Fireproofing Phone #: ###-#### Inspection requested via web by Mike Beeson second floor ok
|
BLD-Framing/Rough-in | 7/29/2016 | 8/1/2016 | 8/5/2016 | A | PART |
Dave Hannah
|
|
|
Framing for 6th deck on Myrtle, cover for lids on 3rd floor corridor and Monokote on 2nd, MTI approved just a visual to make sure you are OK with coverage. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 7/22/2016 | 7/25/2016 | 7/26/2016 | P | PASS |
Dave Hannah
|
|
|
5th floor decking, checking framing below. Maybe we can review Mono-kote progress on floor 2 while your here. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Conference | 7/18/2016 | 7/18/2016 | 7/18/2016 | A | PART |
Dave Hannah
|
|
|
Lid inspection, partial insulation at 2nd floor Myrtle side. Sheathing Phone #: ###-#### Inspection requested via web by Mike Beeson elec walls 2&3 floors ok to prerock top of walls and ceilings 2nd floor east wing and ok to insulate 3rd fl e wing
|
BLD-Conference | 7/15/2016 | 7/15/2016 | 7/15/2016 | P | CANC |
Jim Storey
|
|
|
Just need ok to cover 2nd floor lid on Myrtle side, not walls. All MEP inspections above lid have been signed off. Phone #: ###-#### Inspection requested via web by Mike Beeson out of time
|
BLD-Framing/Rough-in | 7/5/2016 | 7/6/2016 | 7/6/2016 | P | PART |
Dave Hannah
|
|
|
This is for our structural framing for the 5th floor deck pour. MTI has inspected all Forte''s welds with no deficiencies. Phone #: ###-#### Inspection requested via web by Mike Beeson east half
|
BLD-Conference | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
Print Occupancy Form | | | 6/15/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/7/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/7/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/12/2016 | | DONE |
|
|
|
MET Needs; sewer fees paid prior to issuance
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2016 | | DONE |
|
|
|
|
Routing PW Street Lights | 3/30/2016 | | 4/11/2016 | | PASS |
Mike D Hedge
|
|
|
Approved in E-Plan Review. TLW
|
Plan assigned to (TLW) | 1/24/2016 | | 4/11/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/30/2016 | | 4/11/2016 | | PASS |
Tim L. Woodard
|
|
|
Approved with defered submittal on Jacuzzi Transfer Wall. TLW
|
Routing - MECHANICAL | 3/30/2016 | | 4/6/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/30/2016 | | 4/6/2016 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing PW Street Lights | 4/4/2016 | | 4/4/2016 | | PASS |
Tom Marshall
|
|
|
Resub approved per Tom.
|
Routing - FIRE | 3/30/2016 | 3/30/2016 | 3/30/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing - PLAN CHECK | 1/24/2016 | | 3/1/2016 | | FAIL |
Tim L. Woodard
|
|
|
Refer to Changemarks on drawings. TLW
|
1st review completed | | | 3/1/2016 | | DONE |
|
|
|
|
Routing - PLUMBING | 1/24/2016 | | 2/5/2016 | | FAIL |
Daryl Spivey
|
|
|
P11 sewer service location does not match utility plan
Show interceptor, piping and venting
P91 and P92 separate riser diagrams to provide clarity and show sizing
P41 P91 and P92 provide suds relief for risers with suds producing fixtures
P81 backflow preventers are not allowed to be installed in walls where water damage will occur
P93 and P94 clarify pipe sizing and routing to bathroom groups
|
Routing - MECHANICAL | 1/24/2016 | | 2/4/2016 | | FAIL |
Troy James
|
|
|
|
Routing PW Drainage | 1/25/2016 | | 2/2/2016 | | PASS |
Jason C. Taylor
|
|
|
See BLD15-03525 for drainage approval. JCT
|
Routing PW Geothermal | 1/25/2016 | | 1/28/2016 | | PASS |
Jon R. Gunnerson
|
|
|
No Geothermal
|
Routing - FIRE | 1/24/2016 | 1/24/2016 | 1/27/2016 | | PASS |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing PW Solid Waste | 1/25/2016 | | 1/27/2016 | | PASS |
Megan Durrell
|
|
|
Shared concerns over access to trash room under building and noise impacts of services on hotel guests. Approved.
|
Routing PW Street Lights | 1/25/2016 | | 1/25/2016 | | FAIL |
Mike D Hedge
|
|
|
Historic street lighting required but not on the plans.
|
Routing - Addressing | 1/24/2016 | | 1/25/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/24/2016 | | 1/25/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 1/24/2016 | | 1/25/2016 | | PASS |
Sarah Schafer
|
|
|
DRH15-00337 - Approved per DR.
|
Intake Approval | | | 1/24/2016 | | PASS |
|
|
|
|
Pending Assignment by TLW | 1/24/2016 | | 1/24/2016 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 1/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 15 2016 4:13PM
|