First Notice | | 6/6/2016 | 6/10/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/27/2016 | 5/27/2016 | 5/27/2016 | P | DONE |
Troy Cobbley
|
|
|
|
Permanent Occupancy | | | 5/27/2016 | | DONE |
|
|
|
|
BLD-Final | 5/17/2016 | 5/17/2016 | 5/17/2016 | P | PASS |
Mike Jordan
|
|
|
Jack-final for temp c of o Phone #: ###-####. Temp occ. Will be ok for perm occ. once fire alarm and fire/life/safety sign perm.
|
FIRE-Final Inspection | 5/17/2016 | 5/17/2016 | 5/17/2016 | P | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given with Scott's approval for a maximum of 30 days and only for the moving in of equipment. A final can be given when the project related fire alarm permit is finaled.
|
FIRE-Final Inspection | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire sprinkler permit needs addressed and a fire alarm permit is needed for the duct smoke detectors on the new hvac units.
|
Print Occupancy Form | | | 4/28/2016 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Mike Jordan
|
|
|
Kurt Phone #: ###-####
|
BLD-Footing | 4/7/2016 | 4/8/2016 | 4/8/2016 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Energy code compliance | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Mike Jordan
|
|
|
Kurt Phone #: ###-####. South furred wall ok.
|
BLD-Framing/Rough-in | 3/15/2016 | 3/16/2016 | 3/16/2016 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 3/15/2016 | 3/15/2016 | 3/15/2016 | P | PASS |
Mike Jordan
|
|
|
All h.4 clips installed.
|
BLD-Framing/Rough-in | 3/14/2016 | 3/15/2016 | 3/15/2016 | A | PART |
Mike Jordan
|
|
|
Kurt Phone #: ###-####. Interior full height steel stud demissibng wall ok. Interior 2x4 wood framed furred walls need the H.4 installed at every stud and at every 8ft. horizontal support.
|
Issue PAID IN FULL permit | | | 3/3/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/3/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 2/29/2016 | | |
|
|
|
|
Plan assigned to (TLW) | 2/10/2016 | | 2/29/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLUMBING | 2/25/2016 | | 2/29/2016 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/29/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/29/2016 | | DONE |
Christina Prado
|
|
|
Need RP ***MET 3-2-16***GC Form & Revised certificate of value for issuance
|
Routing - PLAN CHECK | 2/25/2016 | | 2/25/2016 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 2/16/2016 | | DONE |
|
|
|
|
Routing PW Environmental | 1/22/2016 | | 2/16/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLAN CHECK | 1/22/2016 | | 2/16/2016 | | PASS |
Javier Guzman
|
|
|
|
Plan assigned to (JG) | 1/22/2016 | 1/22/2016 | 2/10/2016 | | DEFR |
Javier Guzman
|
|
|
2/18 L3 NxEdge ePlan
|
Routing - FIRE | 1/22/2016 | 1/22/2016 | 2/4/2016 | | PASS |
Scott Arellano
|
|
|
Comments attached to case.
|
Routing - MECHANICAL | 1/22/2016 | | 1/29/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/22/2016 | | 1/27/2016 | | FAIL |
Bill VanDegrift
|
|
|
provide an r.p. for the hose bibs in the production area
|
Routing - Erosion and Sediment | 1/22/2016 | | 1/25/2016 | | PASS |
Evan Jenkins
|
|
|
(NXEDGE) Remodel of a 6,256 sq. ft. area within an existing tenant building per approved plans. Work to include building two demising walls separating the spaces, change the use of the new space to manufacturing, remove portions of concrete floors and install new areas of concrete floors, new interior walls and new equipment and fixtures required for the manufacturing process.
|
Routing - Addressing | 1/22/2016 | | 1/22/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 1/22/2016 | | 1/22/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 1/22/2016 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard.
|
Pending Assignment by JCB | 1/22/2016 | | 1/22/2016 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 1/20/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 20 2016 2:27PM
|