Permit Information
Permit NumberBLD16-00228
StatusFinaled
Name ESI
Site Address 2755 S BEVERLY ST Unit: 103
Project NameIdaho Cheer
Customer Number 
ePlanReviewYes
Description
(IDAHO CHEER)(SUITE 103) 1st time tenant build out of a new 5,000 sq. ft. exercise facility tenant in an existing empty warehouse space. Non separated use. Original building constructed under BLD14-01651. Scope of work to include 2 new ADA compliant restrooms, ADA compliant drinking fountain, non bearing partition walls to create office, lobby and mechanical room. The area above the office is not designed for any storage. Plumbing, mechanical and electrical permits are required. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 6/20/20166/29/2016 DONE
This permit finaled on the web by Penny Dennis
First Notice 5/12/20166/10/2016 DONE
Mailed 6-13-16
Permanent Occupancy  5/2/2016 DONE
BLD-Final4/29/20164/29/20164/29/2016PPASS
DetailsPhil Shearer
Call me Phil when you are ready thanks Phone #: ###-#### Inspection requested via web by Miles Hash
FIRE-Final Inspection4/28/20164/29/20164/29/2016APASS
DetailsTroy Cobbley
Life safety passed. No matting or foam of any kind was in the space at the time of inspection.
BLD-Ceiling Grid Inspection4/25/20164/25/20164/25/2016PPASS
DetailsPhil Shearer
call before not on site all day thanks Phil Phone #: ###-#### Inspection requested via web by Miles Hash
BLD-Framing/Rough-in4/1/20164/4/20164/4/2016APASS
DetailsPhil Shearer
call before, part time on site thanks Phone #: ###-#### Inspection requested via web by Miles Hash
Issue PAID IN FULL permit  3/9/2016 DONE
Print Occupancy Form  3/9/2016 DONE
Plan assigned to (AJS)2/3/20162/3/20163/7/2016 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Level 3 TI - ePlanReview - Idaho Cheer
Routing - PLAN CHECK3/3/2016 3/7/2016 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  3/7/2016 DONE
Permit Ready to Issue  3/7/2016 DONE
DetailsChristina Prado
***ALL MET*** Needs GC Form & Revised Certificate of value for issuance
Routing - FIRE3/3/20163/3/20163/3/2016 PASS
DetailsAdele J Schaffeld-Griffin
Revised report attached to case.
Routing - PLANNING3/2/2016 3/2/2016 PASS
DetailsSusan Riggs
1st review completed  3/2/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK2/3/2016 3/2/2016 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE2/3/20162/3/20162/5/2016 FAIL
DetailsScott Arellano
Report attached to case and emailed to architect.
Routing - Addressing2/3/2016 2/3/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS2/3/2016 2/3/2016 PASS
DetailsJennifer Bruner
Pending Assignment by JCB2/3/2016 2/3/2016 DONE
DetailsJason Blais
Routing PW Sewer Rating2/3/2016 2/3/2016 PASS
DetailsJennifer Bruner
Intake Approval  2/1/2016 PASS
DetailsJason Blais
Prescreen approved by Tim Woodard and plan review fees paid.
Application received  1/26/2016 DONE
Application submitted via PDS Online on Jan 26 2016 2:08PM
Routing - PLANNING2/3/2016   FAIL
DetailsSusan Riggs
Susan Riggs - CUP15-00090
I can pass this on March 2, 2016 after the Council hearing.