Second Notice | | 4/22/2016 | 6/15/2016 | | DONE |
|
|
|
Mailed 5-13-16
|
First Notice | | 3/19/2016 | 4/12/2016 | | DONE |
|
|
|
|
BLD-Final | 3/8/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Mike Jordan
|
|
|
Mark Phone #: ###-####. All issues resolved. Ok for perm cc.
|
Permanent Occupancy | | | 3/9/2016 | | DONE |
|
|
|
|
BLD-Final | 3/8/2016 | 3/8/2016 | 3/8/2016 | P | PART |
Mike Jordan
|
|
|
OK for temp occ. Flushing mechanism on on toilet not on turning radius side. Plungers not yet installed in floor to lock doors in the open position.
|
BLD-Final | 3/4/2016 | 3/8/2016 | 3/8/2016 | A | CANC |
Mike Jordan
|
|
|
Mark Phone #: ###-####. mOved to pm.
|
FIRE-Final Inspection | 3/7/2016 | 3/7/2016 | 3/7/2016 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Main exit doors not installed yet
|
FIRE-Final Inspection | 3/4/2016 | 3/7/2016 | 3/7/2016 | A | FAIL |
Troy Cobbley
|
|
|
Provide fire extinguisher as discussed. Per contractor the office door is not being installed. Main exit doors and storefront glass is not on site yet. Smoke evac. system test passed
|
BLD-Framing/Rough-in | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | PART |
Mike Jordan
|
|
|
Mark Phone #: ###-####. Interior steel stud framed wall for restroom ok. Pending plumbing rough in inspection. Noted that wall already one sided with sheet rock when I arrived on site.
|
BLD-Wall cover | 2/17/2016 | 2/18/2016 | 2/18/2016 | A | PASS |
Mike Jordan
|
|
|
Mark Phone #: ###-####
|
Permit Ready to Issue | | | 2/10/2016 | | DONE |
|
|
|
All Requirements Met GC turned in Application/Plans
|
Print Occupancy Form | | | 2/10/2016 | | DONE |
|
|
|
|
Telephone call | | | 2/10/2016 | | DONE |
|
|
|
called Jerrod to let know permit is ready and how much is owed
|
Issue PAID IN FULL permit | | | 2/10/2016 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 1/29/2016 | 1/29/2016 | 2/9/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/1/2016 | | 2/9/2016 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 2/9/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/9/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/9/2016 | | DONE |
|
|
|
|
Routing - Addressing | 1/29/2016 | | 2/1/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/1/2016 | | 2/1/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/29/2016 | | DONE |
|
|
|
|
Intake Approval | | | 1/29/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/29/2016 | | DONE |
|
|
|
|
Application received | | 1/29/2016 | | | |
|
|
|
|