Plan Reviewer's activity | | | 3/21/2018 | | DONE |
|
|
|
Took drawings to records
|
Third Notice | | 4/16/2017 | 5/10/2017 | | DONE |
|
|
|
Mailed 5-11
|
Second Notice | | 3/19/2017 | 4/11/2017 | | DONE |
|
|
|
Mailed 4-12-17
|
First Notice | 2/15/2017 | 2/15/2017 | 3/9/2017 | | DONE |
Jim Storey
|
|
|
put in mail 3-10-17
|
BLD-Final | 2/15/2017 | 2/15/2017 | 2/15/2017 | P | PASS |
Jim Storey
|
|
|
Robert Phone #: ###-####
|
DOC - Permit Finaled | 2/15/2017 | 2/15/2017 | 2/15/2017 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 2/13/2017 | 2/14/2017 | 2/14/2017 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection passed/complete
|
Zoning Approval | 2/6/2017 | 2/6/2017 | 2/6/2017 | | PASS |
Sarah Schafer
|
|
|
|
BLD-Final | 1/30/2017 | 1/31/2017 | 1/31/2017 | P | NR |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 11/21/2016 | 11/22/2016 | 11/22/2016 | A | PASS |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | PART |
Jim Storey
|
|
|
Bob Phone #: ###-#### ft ok wip
|
BLD-Framing/Rough-in | 10/31/2016 | 10/31/2016 | 10/31/2016 | P | PASS |
Jim Storey
|
|
|
Robert Phone #: ###-####
|
BLD-Framing/Rough-in | 10/24/2016 | 10/25/2016 | 10/25/2016 | A | PASS |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
Inspection Record Card- Bld | | | 9/20/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/20/2016 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 2/2/2016 | 2/2/2016 | 9/19/2016 | | PASS |
Carl Westfall
|
|
|
(1st done) EASTGATE SHOPPING CENTER FACADE (Feb 22 - 15 days)
|
Routing - Design Review | 9/15/2016 | | 9/19/2016 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 9/19/2016 | | 9/19/2016 | | DONE |
Carl Westfall
|
|
|
Routing completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/19/2016 | | DONE |
|
|
|
need GC and Rev Cert of Val
|
Inspection Record Card- Bld | | | 9/19/2016 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2016 | | DONE |
|
|
|
Spoke with Doug informing him that this permit is ready to be picked up and that the GC needs to fill out the 302 and 306 forms
|
Routing - PLAN CHECK | 9/13/2016 | | 9/15/2016 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 9/12/2016 | | DONE |
|
|
|
Two copies of Structural Edge Engineering PLLC, Two copies of sheets A0.0, A0.1, A2.2, A2.3, A4.1, A4.2 and A5.0 Taken to Carl W
|
Plan Reviewer's activity | | | 8/22/2016 | | DONE |
|
|
|
Project on hold after receiving the following Email.
Carl,
Doug resubmitted revised plans last week and unfortunately I'll be revising the design one more time. Existing conditions make impractical to remove the exiting trusses.
Please set the plans aside when you receive them or stop your review if you have already begun.
Thanks,
Kevin
|
Routing - PLANNING | 8/17/2016 | | 8/18/2016 | | PASS |
Josh Wilson
|
|
|
Exterior changes ok
|
Routing - PLAN CHECK | 8/10/2016 | | 8/17/2016 | | PASS |
Carl Westfall
|
|
|
Drawings approved
|
Plan resubmittals received | | | 8/15/2016 | | DONE |
|
|
|
received two copies of Plan review report and sheets A0.0, A0.1, A2.2, A2.3, A4.0, A4.1, A4.2, A5.0- put on Carl's desk
|
Routing - PLANNING | 8/9/2016 | | 8/10/2016 | | PASS |
Josh Wilson
|
|
|
|
Plan resubmittals requested | | | 8/9/2016 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/29/2016 | | 8/9/2016 | | FAIL |
Carl Westfall
|
|
|
Resubmittal came in late on Friday afternoon just before being gone for a week. Plan review report Emailed to the Architect.
|
Plan resubmittals received | | | 7/29/2016 | | DONE |
|
|
|
resubmittals received 2 sets of struc calcs and 2 each of sheets A0.0,A0.1, A2.2, A2.3, A4.0, A4.1, A4.2 & A5.0-took to Carl W
|
1st review completed | | | 2/22/2016 | | DONE |
|
|
|
Failed IBC
|
Plan resubmittals requested | | | 2/22/2016 | | DONE |
|
|
|
Send to Fire for the resubmittal review
|
Routing - PLAN CHECK | 2/3/2016 | | 2/22/2016 | | FAIL |
Carl Westfall
|
|
|
Revisions required to the drawings.
|
Routing - Addressing | 2/2/2016 | | 2/3/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/2/2016 | | 2/3/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLANNING | 2/3/2016 | | 2/3/2016 | | PASS |
Josh Wilson
|
|
|
|
Plan Reviewer's activity | | | 2/2/2016 | | PASS |
|
|
|
Plan intake approved
|
Plans ACCEPTED BY PLAN TECH | | | 2/2/2016 | | DONE |
|
|
|
|
Intake Approval | | | 2/2/2016 | | PASS |
Carl Westfall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/2/2016 | | DONE |
|
|
|
|
Application received | | 2/2/2016 | | | |
|
|
|
|