BLD-Final | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PASS |
Tony Young
|
|
|
Plumbing final inspection today in the am and BLD final in pm Phone #: ###-#### Inspection requested via web by greg bauer
|
DOC - Permit Finaled | 8/3/2016 | 8/3/2016 | 8/3/2016 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 6/20/2016 | 6/21/2016 | 6/22/2016 | P | NR |
Tony Young
|
|
|
David Phone #: ###-####
|
BLD-Energy code compliance | 4/5/2016 | 4/5/2016 | 4/5/2016 | P | PASS |
Tony Young
|
|
|
Inspection requested via web by greg bauer
|
BLD-Framing/Rough-in | 4/4/2016 | 4/5/2016 | 4/5/2016 | A | PASS |
Tony Young
|
|
|
Inspection requested via web by greg bauer
|
BLD-Framing/Rough-in | 3/31/2016 | 4/4/2016 | 4/4/2016 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer,, ok to insulate
|
BLD-Footing | 2/29/2016 | 3/1/2016 | 3/1/2016 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer
|
Routing Walk-In (BLD) | 2/3/2016 | 2/3/2016 | 2/3/2016 | P | PASS |
David Ferguson
|
|
|
|
Plan assigned to (DAF) | 2/3/2016 | 2/3/2016 | 2/3/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 2/3/2016 | | 2/3/2016 | | PASS |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 2/3/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 2/3/2016 | | DONE |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/3/2016 | | DONE |
David Ferguson
|
|
|
|
Permit Ready to Issue | | | 2/3/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/3/2016 | | DONE |
|
|
|
|
Meeting | | | 2/3/2016 | | DONE |
|
|
|
as per Colleen no review needed
|
1st review completed | | | 2/3/2016 | | DONE |
David Ferguson
|
|
|
|
Application received | | 2/3/2016 | | | |
|
|
|
|