BLD-Final | 2/6/2017 | 2/6/2017 | 2/6/2017 | P | PASS |
Dave Hannah
|
|
|
sean Phone #: ###-####
|
DOC - Permit Finaled | 2/6/2017 | 2/6/2017 | 2/6/2017 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 2/2/2017 | 2/2/2017 | 2/2/2017 | | PASS |
Ted Vanegas
|
|
|
|
Application received | | 2/8/2016 | 2/2/2017 | | DONE |
|
|
|
|
BLD-Final | 1/31/2017 | 1/31/2017 | 1/31/2017 | P | FAIL |
Dave Hannah
|
|
|
justin Phone #: ###-#### needs zoning and tempered glass back bathroom
|
Plan Modification Accepted | | | 1/27/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/27/2017 | | 1/27/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Energy code compliance | 8/23/2016 | 8/23/2016 | 8/23/2016 | P | PASS |
Dave Hannah
|
|
|
Rob Phone #: ###-####
|
BLD-Energy code compliance | 8/18/2016 | 8/19/2016 | 8/19/2016 | A | PART |
Phil Shearer
|
|
|
Bob Phone #: ###-####. Air seal good ok to insulate
|
BLD-Framing/Rough-in | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | PASS |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Wall Bracing | 7/28/2016 | 7/29/2016 | 7/29/2016 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 5/24/2016 | 5/24/2016 | 5/24/2016 | P | PASS |
Phil Shearer
|
|
|
Wal // Chris Phone #: ###-####
|
BLD-Footing | 5/24/2016 | 5/24/2016 | 5/24/2016 | P | PASS |
Dave Hannah
|
|
|
chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/24/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/21/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 3/15/2016 | 3/15/2016 | 3/21/2016 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 3/15/2016 | | 3/21/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | 3/17/2016 | | 3/21/2016 | | PASS |
Rachael Beierle
|
|
|
|
Case Summary (BLD) | | | 3/21/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/21/2016 | | DONE |
|
|
|
All requirements met
|
Telephone call | | | 3/21/2016 | | DONE |
|
|
|
notified customer that permit is ready
|
Routing - PLANNING | 3/17/2016 | | 3/17/2016 | | PASS |
Matthew A Halitsky
|
|
|
|
Routing - MECHANICAL | 3/17/2016 | | 3/17/2016 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 3/15/2016 | | DONE |
|
|
|
received (2) sets of resubmittals with a new manual D&J, Calculations, & structural plans for single story ONLY with no basement
|
OVERRIDE | | | 2/18/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 2/11/2016 | 2/11/2016 | 2/18/2016 | | DONE |
Brian McGowan
|
|
|
due 2/22
|
1st review completed | | | 2/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 2/18/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/18/2016 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 2/18/2016 | | DONE |
|
|
|
All Met
|
Inspection Record Card- Bld | | | 2/18/2016 | | DONE |
|
|
|
|
Telephone call | | | 2/18/2016 | | DONE |
|
|
|
called Mary to let know permit is ready and how much is owed
|
Routing - PLAN CHECK | 2/16/2016 | | 2/18/2016 | | PASS |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 2/12/2016 | | 2/16/2016 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/8/2016 | 2/11/2016 | 2/12/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 2/7/2016 | | 2/12/2016 | | PASS |
Matthew A Halitsky
|
|
|
|
Plan assigned to (LEG) Tisha | 2/8/2016 | | 2/11/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - Addressing | 2/8/2016 | | 2/8/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 2/8/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/8/2016 | | DONE |
|
|
|
|
Intake Approval | | | 2/8/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/8/2016 | | DONE |
|
|
|
|