Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD16-00376
StatusFinaled
Name SYRINGA CONSTRUCTION LLC
Site Address 7673 W GILLIS RD
Project Name 
Customer NumberBND15-00089
ePlanReviewNo
Description
***2/23/16 change in address/parcel*** Permit for the construction of a new 2,628 sq. ft., two story (first story 1,599 sq. ft., second story 1,029 sq. ft.) single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 256 sq. ft. of covered patio/porch and a 811 sq. ft. attached garage per the approved plans, engineering, ACCA report and any notations. R-1C zoning and setbacks per planning. //leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/13/201610/13/201610/13/2016PPASS
DetailsTony Young
Garage access code is 0713. Please call with any questions. Thanks Phone #: ###-#### Inspection requested via web by Kim Winkle
DOC - Permit Finaled10/13/201610/13/201610/13/2016PPASS
DetailsTony Young
c of o issued
BLD-Energy code compliance7/8/20167/12/20167/12/2016APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Kim Winkle
BLD-Framing/Rough-in7/5/20167/8/20167/8/2016APASS
DetailsJim Sly
Plans are near power panel. Call steve with questions at 850.8424. Phone #: ###-#### Inspection requested via web by steve hanson
BLD-Wall Bracing6/15/20166/16/20166/16/2016PPASS
DetailsJim Sly
Shear inspection please. Plans on site. Framer should still be on site. Thanks, steve Phone #: ###-#### Inspection requested via web by steve hanson
BLD-Footing6/2/20166/2/20166/2/2016PPASS
DetailsTony Young
Dan Phone #: ###-####
BLD-Foundation4/5/20164/6/20164/6/2016PPART
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron// work in progress
BLD-Footing4/5/20164/5/20164/5/2016PPASS
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Other3/31/20164/1/20164/1/2016PCANC
DetailsTony Young
Hi--Need to schedule an Erosion Pre-Con meeting for Friday afternoon. Steve Hanson will be the contact -- ###-#### Phone #: ###-#### Inspection requested via web by Kim Winkle,,, scheduled eej on the esc permit
Inspection Record Card- Bld  3/31/2016 DONE
Issue PAID IN FULL permit  3/31/2016 DONE
OVERRIDE  3/29/2016  
Inspection Record Card- Bld  3/29/2016 DONE
Telephone call  3/29/2016 DONE
called Steve to let know permit is ready and how much is owed-left message on his phone
Routing - PLAN CHECK3/25/2016 3/29/2016 PASS
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  3/29/2016 DONE
Case Summary (BLD)  3/29/2016 DONE
Permit Ready to Issue  3/29/2016 DONE
all requirements met
Plan assigned to (LEG) Tisha2/10/2016 3/29/2016 DONE
DetailsTisha Gallop
2nd (1st) review 3/11; 1st review 2/23 (submitted on new lot, rerouted all over again)
Plan resubmittals received  3/25/2016 DONE
received two copies of sheets A0.0, A2.0, A4.0, A5.0- put on Tisha's desk
Routing - PLAN CHECK  3/11/2016 FAIL
DetailsTisha Gallop
Routing - MECHANICAL2/23/2016 2/24/2016 PASS
DetailsChad Schwendiman
Plan resubmittals received  2/23/2016 DONE
received (2) new site plans
change in address/parcel
Routing - PLANNING2/23/2016 2/23/2016 PASS
DetailsColleen T Carroll
Routing - Addressing2/23/2016 2/23/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS2/23/2016 2/23/2016 PASS
DetailsJennifer Bruner
1st review completed  2/22/2016 FAIL
Routing - PLAN CHECK2/18/2016 2/22/2016 FAIL
DetailsTisha Gallop
no review done; submitted on correct lot, reroute started 2/23
Plan resubmittals received  2/19/2016 DONE
received two copies of sheet A0.0- gave to Tisha and put with plans
Routing - MECHANICAL2/12/2016 2/18/2016 FAIL
DetailsTroy James
contacted ultimate heating
May need a revised site plan submitted
Routing - PLANNING2/11/2016 2/12/2016 FAIL
DetailsColleen T Carroll
Need a site plan reduction that matches plan.
Routing - Addressing2/10/2016 2/11/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS  2/11/2016 PASS
Plans ACCEPTED BY PLAN TECH  2/10/2016 DONE
Intake Approval  2/10/2016 PASS
Recd Pcfee & Taken To Pln CK  2/10/2016 DONE
Application received 2/9/2016