BLD-Final | 10/13/2016 | 10/13/2016 | 10/13/2016 | P | PASS |
Tony Young
|
|
|
Garage access code is 0713. Please call with any questions. Thanks Phone #: ###-#### Inspection requested via web by Kim Winkle
|
DOC - Permit Finaled | 10/13/2016 | 10/13/2016 | 10/13/2016 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Energy code compliance | 7/8/2016 | 7/12/2016 | 7/12/2016 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kim Winkle
|
BLD-Framing/Rough-in | 7/5/2016 | 7/8/2016 | 7/8/2016 | A | PASS |
Jim Sly
|
|
|
Plans are near power panel. Call steve with questions at 850.8424. Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Wall Bracing | 6/15/2016 | 6/16/2016 | 6/16/2016 | P | PASS |
Jim Sly
|
|
|
Shear inspection please. Plans on site. Framer should still be on site. Thanks, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Footing | 6/2/2016 | 6/2/2016 | 6/2/2016 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-####
|
BLD-Foundation | 4/5/2016 | 4/6/2016 | 4/6/2016 | P | PART |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron// work in progress
|
BLD-Footing | 4/5/2016 | 4/5/2016 | 4/5/2016 | P | PASS |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Other | 3/31/2016 | 4/1/2016 | 4/1/2016 | P | CANC |
Tony Young
|
|
|
Hi--Need to schedule an Erosion Pre-Con meeting for Friday afternoon. Steve Hanson will be the contact -- ###-#### Phone #: ###-#### Inspection requested via web by Kim Winkle,,, scheduled eej on the esc permit
|
Inspection Record Card- Bld | | | 3/31/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/31/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/29/2016 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/29/2016 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2016 | | DONE |
|
|
|
called Steve to let know permit is ready and how much is owed-left message on his phone
|
Routing - PLAN CHECK | 3/25/2016 | | 3/29/2016 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/29/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/29/2016 | | DONE |
|
|
|
all requirements met
|
Plan assigned to (LEG) Tisha | 2/10/2016 | | 3/29/2016 | | DONE |
Tisha Gallop
|
|
|
2nd (1st) review 3/11; 1st review 2/23 (submitted on new lot, rerouted all over again)
|
Plan resubmittals received | | | 3/25/2016 | | DONE |
|
|
|
received two copies of sheets A0.0, A2.0, A4.0, A5.0- put on Tisha's desk
|
Routing - PLAN CHECK | | | 3/11/2016 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 2/23/2016 | | 2/24/2016 | | PASS |
Chad Schwendiman
|
|
|
|
Plan resubmittals received | | | 2/23/2016 | | DONE |
|
|
|
received (2) new site plans
change in address/parcel
|
Routing - PLANNING | 2/23/2016 | | 2/23/2016 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 2/23/2016 | | 2/23/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/23/2016 | | 2/23/2016 | | PASS |
Jennifer Bruner
|
|
|
|
1st review completed | | | 2/22/2016 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/18/2016 | | 2/22/2016 | | FAIL |
Tisha Gallop
|
|
|
no review done; submitted on correct lot, reroute started 2/23
|
Plan resubmittals received | | | 2/19/2016 | | DONE |
|
|
|
received two copies of sheet A0.0- gave to Tisha and put with plans
|
Routing - MECHANICAL | 2/12/2016 | | 2/18/2016 | | FAIL |
Troy James
|
|
|
contacted ultimate heating
May need a revised site plan submitted
|
Routing - PLANNING | 2/11/2016 | | 2/12/2016 | | FAIL |
Colleen T Carroll
|
|
|
Need a site plan reduction that matches plan.
|
Routing - Addressing | 2/10/2016 | | 2/11/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 2/11/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/10/2016 | | DONE |
|
|
|
|
Intake Approval | | | 2/10/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/10/2016 | | DONE |
|
|
|
|
Application received | | 2/9/2016 | | | |
|
|
|
|