BLD-Final | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PASS |
Tony Young
|
|
|
Please call ahead for access - Troy Phone #: ###-####
|
DOC - Permit Finaled | 9/29/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Tony Young
|
|
|
|
PubWorks Occupancy Approval | 9/28/2016 | 9/28/2016 | 9/28/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 9/15/2016 | 9/16/2016 | 9/16/2016 | P | FAIL |
Tony Young
|
|
|
Troy Phone #: ###-####,, c/n posted,, hillside,, carbon/smoke det., tempered glass within 24" of door
|
BLD-Final | 9/14/2016 | 9/15/2016 | 9/15/2016 | P | CANC |
Tony Young
|
|
|
Troy Phone #: ###-####
|
BLD-Final | 9/12/2016 | 9/13/2016 | 9/14/2016 | A | NR |
Dave Hannah
|
|
|
Troy Phone #: ###-####
|
BLD-Energy code compliance | 6/24/2016 | 6/27/2016 | 6/27/2016 | A | PASS |
Tony Young
|
|
|
Troy Phone #: ###-####
|
BLD-Framing/Rough-in | 6/22/2016 | 6/23/2016 | 6/23/2016 | A | PASS |
Jim Sly
|
|
|
Troy Phone #: ###-####
|
BLD-Foundation | 5/4/2016 | 5/4/2016 | 5/4/2016 | P | PASS |
Jim Sly
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | PASS |
Jim Storey
|
|
|
Ryan Phone #: ###-####
|
PubWorks Subgrade Approval | 5/2/2016 | 5/2/2016 | 5/2/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 4/27/2016 | 4/28/2016 | 4/28/2016 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####,, late,,, all set up but no soils approval yet
|
BLD-Footing | 4/27/2016 | 4/27/2016 | 4/27/2016 | P | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####,, need soils report 1st
|
BLD-Footing | 4/26/2016 | 4/27/2016 | 4/27/2016 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 4/25/2016 | 4/26/2016 | 4/26/2016 | P | CANC |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/13/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 4/12/2016 | | |
|
|
|
|
Plan assigned to (DAF) | 3/11/2016 | 3/11/2016 | 4/12/2016 | | DONE |
David Ferguson
|
|
|
due 3/30 L2 hillside - JT failed - Plans have multiple issues and are missing info.
|
Routing - PLAN CHECK | 4/12/2016 | | 4/12/2016 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/12/2016 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing PW Grading-Hillside | 4/6/2016 | | 4/7/2016 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
1st review completed | | | 3/30/2016 | | FAIL |
David Ferguson
|
|
|
|
Routing - PLANNING | 3/30/2016 | | 3/30/2016 | | PASS |
Sue Cummings
|
|
|
Received more plans 3/9 Thanks!
|
Routing - PLANNING | 3/9/2016 | | 3/30/2016 | | FAIL |
Sue Cummings
|
|
|
Need full set of plans, specifically floor plans.
|
Routing - PLAN CHECK | 3/9/2016 | | 3/30/2016 | | FAIL |
David Ferguson
|
|
|
Multiple issues - plans are very vague
|
Routing - Erosion and Sediment | 3/9/2016 | | 3/14/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Permit for the construction of a new 3045 sq. ft., two story (first story 2332 sq. ft., second story 713 sq. ft.) single family dwelling with 5 bedrooms, 3.5 bathrooms, approximately *** sq. ft. of covered patio/porch and a 968 sq. ft. attached garage.
|
Routing PW Grading-Hillside | 3/9/2016 | | 3/11/2016 | | FAIL |
Jason C. Taylor
|
|
|
Need scaled grading plan submitted. JCT
|
Plan assigned to (LEG) Tisha | 3/9/2016 | | 3/11/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 3/9/2016 | | 3/10/2016 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 3/9/2016 | 3/9/2016 | 3/9/2016 | | PASS |
Scott Arellano
|
|
|
FD vehicle access approved. This property requires a 30 foot defensible space in accordance with BMC 7-01-69 section 4920 and is subject to Fire Department inspection.
|
Routing - Addressing | 3/9/2016 | | 3/9/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/9/2016 | | 3/9/2016 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 3/9/2016 | | FAIL |
Christina Prado
|
|
|
Need foundation plan stamped, second story framing & WUI updates
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/9/2016 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/9/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 2/10/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 10 2016 4:07PM
|