Letter of compliance/Occupancy | | | 4/17/2018 | | DONE |
|
|
|
emailed to Todd Haylett per his request
|
BLD-Final | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | PASS |
Tony Young
|
|
|
Todd Phone #: ###-####
|
DOC - Permit Finaled | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/2/2016 | 12/2/2016 | 12/2/2016 | | PEND |
Tony Young
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/10/2016 | | DONE |
Christina Prado
|
|
|
Status updated to reflect accurate results, Plan Mod was accepted 6/29 for mechanical review only - no structural review was needed. Change status to ISS per DAF
|
BLD-Framing/Rough-in | 7/21/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
Phil Shearer
|
|
|
Todd Phone #: ###-####
|
BLD-Energy code compliance | 7/21/2016 | 7/21/2016 | 7/21/2016 | P | PASS |
Phil Shearer
|
|
|
Todd Phone #: ###-####
|
BLD-Framing/Rough-in | 7/14/2016 | 7/15/2016 | 7/15/2016 | A | PASS |
Phil Shearer
|
|
|
Todd Phone #: ###-####
|
Plan Modification Accepted | | | 6/29/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 6/29/2016 | | 6/29/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 6/17/2016 | 6/20/2016 | 6/20/2016 | A | PASS |
Mike Jordan
|
|
|
Todd Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 5/25/2016 | | DONE |
|
|
|
|
BLD-Conference | 5/23/2016 | 5/23/2016 | 5/23/2016 | A | PASS |
Tony Young
|
|
|
Todd; Phone #: ###-####,, ?s on portal frame, ok
|
BLD-Foundation | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | PASS |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 3/28/2016 | 3/29/2016 | 3/29/2016 | A | PASS |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | NR |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
OVERRIDE | | | 3/28/2016 | | |
|
|
|
|
Telephone call | | | 3/28/2016 | | DONE |
|
|
|
Spoke with Todd informing him that his permit is ready and the fee amount that is due
|
Inspection Record Card- Bld | | | 3/28/2016 | | DONE |
|
|
|
|
Plan assigned to (DAF) | 3/21/2016 | 3/21/2016 | 3/25/2016 | | DONE |
David Ferguson
|
|
|
due 3/28
|
Plan assigned to (DAF) | 3/11/2016 | 3/11/2016 | 3/25/2016 | | PASS |
David Ferguson
|
|
|
Gave plans back to applicant to revise application and plans to reflect full scope of work. Original permit was for an addition. Applicant decided DEMO entire house and change foundation from slab on grade to raised floor. Also, he added sq. ft. to addition. Needs Manual J for entirely new house and will have to be routed to several departments as though new construction.
|
Routing - PLAN CHECK | 3/22/2016 | | 3/25/2016 | | PASS |
David Ferguson
|
|
|
|
Plan resubmittals received | | | 3/25/2016 | | DONE |
|
|
|
received two copies of sheet 3 of 10- pu twith plans on Dave's desk
|
Case Summary (BLD) | | | 3/25/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLANNING | 3/22/2016 | | 3/22/2016 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | 3/21/2016 | | 3/22/2016 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 3/22/2106 | | 3/22/2016 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/21/2016 | | DONE |
|
|
|
|
Routing - Addressing | 3/21/2016 | | 3/21/2016 | | PASS |
Laura Hunter
|
|
|
|
Plan Modification Accepted | | | 3/11/2016 | | DONE |
|
|
|
plan mod received 2 sets of sheets 3 of 10, 4 of 10 & 6 of 10-took to Dave F
|
OVERRIDE | | | 2/11/2016 | | |
|
|
|
|
Routing Walk-In (Zoning) | 2/11/2016 | 2/11/2016 | 2/11/2016 | A | DONE |
Leon Letson
|
|
|
|
Routing Walk-In (BLD) | 2/11/2016 | 2/11/2016 | 2/11/2016 | A | PASS |
David Ferguson
|
|
|
Need ESC approval
|
Plan assigned to (DAF) | 2/11/2016 | 2/11/2016 | 2/11/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 2/11/2016 | | 2/11/2016 | | PASS |
David Ferguson
|
|
|
|
1st review completed | | | 2/11/2016 | | DONE |
David Ferguson
|
|
|
|
Inspection Record Card- Bld | | | 2/11/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/11/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/11/2016 | | DONE |
|
|
|
\requirements met
|
Intake Approval | | | 2/11/2016 | | PASS |
David Ferguson
|
|
|
|
CHANGE ISSUED DATE | | | 2/11/2016 | | DONE |
Jason Blais
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2016 | | DONE |
David Ferguson
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/11/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | 2/11/2016 | | | |
|
|
|
|
Application received | | 2/11/2016 | | | |
|
|
|
reset the app date to 2/11 not 3/21/16
|