BLD-Final | 10/26/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Mike Jordan
|
|
|
Please give me 15 minutes lead time. Thanks. Phone #: ###-#### Inspection requested via web by Scott Zierler
|
DOC - Permit Finaled | 10/31/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Mike Jordan
|
|
|
Inspected attic area for truss enngineering, and firewall. ok. cert. of occ. issued.
|
BLD-Final | 10/26/2017 | 10/26/2017 | 10/26/2017 | P | NR |
Mike Jordan
|
|
|
Garage code is 0813. Final Elevation cert is on record, approved 9/27/17.
Thanks Scott Phone #: ###-#### Inspection requested via web by Scott Zierler. Will reschedule.
|
BLD-Final | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | NR |
Brandon Shaw
|
|
|
Need Elevation Cert. approved by Public Works.
|
Routing PW Flood Plain | 9/27/2017 | | 9/27/2017 | | PASS |
Jason C. Taylor
|
|
|
Two Elevation Certificates will be required; one prior to receiving a framing inspection, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####
|
Elevation Cert Rec'd-Final | | | 9/27/2017 | | DONE |
|
|
|
|
BLD-Energy code compliance | 5/15/2017 | 5/15/2017 | 5/15/2017 | P | PEND |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler House almost 1/2 covered with dry wall at time of inspection, cover at own risk.
|
BLD-Framing/Rough-in | 5/12/2017 | 5/15/2017 | 5/15/2017 | A | PEND |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Zierler At time of inspection, house wrap and sliding in place. Insulation and half of all interior covered with dry wall. Continue at own risk.
|
BLD-Energy code compliance | 5/11/2017 | 5/12/2017 | 5/12/2017 | A | FAIL |
Jim Storey
|
|
|
Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler no framing or fire wall insp. resch. for mike
|
BLD-Wall Bracing | 3/21/2017 | 3/21/2017 | 3/21/2017 | P | PASS |
Mike Jordan
|
|
|
Reinspection Phone #: ###-#### Inspection requested via web by Scott Zierler
|
BLD-Wall Bracing | 3/17/2017 | 3/17/2017 | 3/17/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 3/17/2017 | 3/17/2017 | 3/17/2017 | A | CANC |
Mike Jordan
|
|
|
Plans will be with the framer. Thanks Mike! Phone #: ###-#### Inspection requested via web by Scott Zierler. Moved to pm.
|
BLD-Foundation | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 10/11/2016 | 10/12/2016 | 10/12/2016 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 10/11/2016 | 10/11/2016 | 10/11/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 10/11/2016 | 10/11/2016 | 10/11/2016 | A | CANC |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. moved to pm.
|
Issue PAID IN FULL permit | | | 8/22/2016 | | DONE |
|
|
|
|
Place hold on job | 8/19/2016 | | 8/22/2016 | | DONE |
Carlos Velazquez
|
|
|
DO NOT ISSUE WITHOUT BLD16-00413
|
OVERRIDE | | | 8/19/2016 | | |
|
|
|
|
Plan assigned to (DAF) | 2/22/2016 | 2/22/2016 | 8/19/2016 | | DONE |
David Ferguson
|
|
|
due 3/4 L2 Townhouse - Jim W. failed for flood cert.
|
Routing PW Flood Plain | 8/19/2016 | | 8/19/2016 | | PASS |
Jim Wyllie
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/19/2016 | | DONE |
|
|
|
All Met
|
Inspection Record Card- Bld | | | 8/19/2016 | | DONE |
|
|
|
|
Telephone call | | | 8/19/2016 | | DONE |
|
|
|
called Pat to let know permits are ready and how much is owed-left message on his phone
|
Elevation Cert Rec'd-Prelim | | | 8/16/2016 | | DONE |
|
|
|
|
Extend Review Timeline | | | 8/12/2016 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
1st review completed | | | 2/29/2016 | | DONE |
David Ferguson
|
|
|
|
Case Summary (BLD) | | | 2/29/2016 | | DONE |
David Ferguson
|
|
|
|
Routing - PLAN CHECK | 2/19/2016 | | 2/29/2016 | | PASS |
David Ferguson
|
|
|
|
Plan assigned to (LEG) Tisha | 2/12/2016 | | 2/22/2016 | | DEFR |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 2/18/2016 | | 2/19/2016 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/18/2016 | | 2/18/2016 | | PASS |
Celine Acord
|
|
|
|
Routing PW Flood Plain | 2/12/2016 | | 2/18/2016 | | FAIL |
Jim Wyllie
|
|
|
Elevation Certificate is wrong. Add input for items A7, A9, C1, and C2a. Item B6 is wrong. Correct date is 2-13-2003.
Jim Wyllie / ###-####
|
Routing - Addressing | 2/12/2016 | | 2/12/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 2/12/2016 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/12/2016 | | DONE |
|
|
|
|
Intake Approval | | | 2/12/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/12/2016 | | DONE |
|
|
|
|
Application received | | 2/11/2016 | | | |
|
|
|
|