Permit Information
Permit NumberBLD16-00423
StatusFinaled
Name WINSPEAR CONSTRUCTION LLC
Site Address 714 E HEARTHSTONE DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Permit is for replacing an existing retaining wall only. A variance has been provided allowing reconstruction. All work to be done according to Engineering, plans, notes and local codes. **BJM**A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference9/1/20169/2/20169/2/2016ADONE
DetailsJim Storey
Tony, not sure why this is still open but you came up for inspections. If you could call me when you are going up I will meet you there. I tried for today but your out of office. See you tomorrow. Phone #: ###-#### Inspection requested via web by jordan winspear
BLD-Conference9/1/20169/1/20169/1/2016PDONE
DetailsJim Storey
Inspection requested via web by jordan winspear
DOC - Permit Finaled9/1/20169/1/20169/1/2016PPASS
DetailsJim Storey
BLD-Foundation5/9/20165/11/20165/11/2016APART
DetailsTony Young
Jordan; Phone #: ###-####,, work in progress
BLD-Footing5/9/20165/10/20165/10/2016APASS
DetailsTony Young
Jordan; Phone #: ###-####
BLD-Footing5/9/20165/9/20165/10/2016PPEND
DetailsTony Young
Jordan; Phone #: ###-####,, need soils report approval from JT
PubWorks Subgrade Approval5/10/20165/10/20165/10/2016 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the wall footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
OVERRIDE  4/27/2016  
OVERRIDE  4/27/2016  
Permit Ready to Issue  4/27/2016 DONE
All Met
Inspection Record Card- Bld  4/27/2016 DONE
Telephone call  4/27/2016 DONE
called Jordan to let know permit is ready-we removed the other contact so Jordan is the only contact on this permit
Issue PAID IN FULL permit  4/27/2016 DONE
Plan assigned to (BJM)2/12/20162/12/20164/26/2016 DONE
DetailsBrian McGowan
Planning Failed it due to 6' tall walls in front setback
Routing - PLAN CHECK4/26/2016 4/26/2016 PASS
DetailsBrian McGowan
Routing PW Grading-Hillside4/26/2016 4/26/2016 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Case Summary (BLD)  4/26/2016 DONE
DetailsBrian McGowan
Inspection Record Card- Bld  4/26/2016 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  4/26/2016 DONE
DetailsBrian McGowan
Plan resubmittals received  4/22/2016 DONE
received (2) sets of structural engineering
Routing PW Grading-Hillside4/19/2016 4/19/2016 FAIL
DetailsJason C. Taylor
Retaining wall plans show ecology blocks but engineering has two designs (ecology & concrete). Which design is to be used? JCT ###-####
Routing - PLAN CHECK2/22/2016 4/14/2016 FAIL
DetailsBrian McGowan
Routing - PLANNING4/13/2016 4/14/2016 PASS
DetailsColleen T Carroll
Per CVA16-00013. For replacement of the existing railroadties wall only. No other wall or fence at other locations is approved.
Plan resubmittals received  2/22/2016 DONE
Two copies of Waiver Request for ESC, Structural Edge Engineering PPLC and L-100. Taken to Brian M
1st review completed  2/16/2016 FAIL
DetailsBrian McGowan
Planning failed it.
Routing - PLAN CHECK2/12/2016 2/16/2016 FAIL
DetailsBrian McGowan
Planning failed it.
Routing - PLANNING2/12/2016 2/12/2016 FAIL
DetailsDavid Moser
The retaining wall is 6 feet high in front setback and max height is 3 feet.
Plans ACCEPTED BY PLAN TECH  2/12/2016 DONE
Intake Approval  2/12/2016 PASS
DetailsJason C. Taylor
Routing - Erosion and Sediment2/12/2016 2/12/2016 PASS
DetailsEvan Jenkins
New Hillside Retaining Wall
Application received 2/12/2016