Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD16-00472
StatusFinaled
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 2260 S COLE RD Unit: 150
Project NameDB Schenker Suite 150
Customer Number 
ePlanReviewYes
Description
(DB SCHENKER- Suite 130, 140 and 150) This permit is to combine three existing warehouse tenant space(130,140,and 150) to make a total 15,270 sq. ft. warehouse and an 896 sq. ft. office space. Note: the architect has reclassified building to a type IIIB building. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select interior nonbearing demising wall to access adjacent tenant spaces, new door opening between adjacent office spaces, new ADA compliant drinking fountain, adding an accessible height cabinet at office, adding fire retardant treated plywood to the exterior side of the south/east end windows of the building, adding an interior chain link fence cage, new lighting fixtures at warehouse area and electrical work. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  7/21/2016 DONE
Case Summary (BLD)  7/21/2016 DONE
Case Summary (BLD)  7/21/2016 DONE
Second Notice 4/22/20165/10/2016 DONE
This permit finaled on the web by Brian McCoy
First Notice 4/3/20164/12/2016 DONE
Mailed 4-13-16
BLD-Final3/23/20163/23/20163/24/2016PPASS
DetailsPhil Shearer
would like call ahead; Jamie Phone #: ###-####
Permanent Occupancy  3/24/2016 DONE
Meeting  3/23/2016 DONE
DetailsCarl D Madsen
This permit was changed to reflect combining bld16-0393 and 394 into one space.
(F) Reprint permit  3/23/2016 DONE
Reprint permit to send Kevin a copy of the permit.
BLD-Final3/18/20163/21/20163/21/2016PNR
DetailsJim Sly
Please call 20-30 mins ahead for access - Late afternoon - Jamie Phone #: ###-####
See fires previous note.
FIRE-Final Inspection3/18/20163/21/20163/21/2016PPASS
DetailsTroy Cobbley
Life safety passed. The wrong suite number is listed for the permit. Contractor is to have this corrected with the plan reviewer prior to a building inspection.
Plan assigned to (JG)2/18/20162/18/20163/4/2016 PASS
DetailsJavier Guzman
1st review completed, 3/02 L2 DB Schenker ePlan
Routing - PLAN CHECK3/4/2016 3/4/2016 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  3/4/2016 DONE
Permit Ready to Issue  3/4/2016 DONE
DetailsChristina Prado
***MET*** Need GC Form & Revised certificate of value for issuance
Issue PAID IN FULL permit  3/4/2016 DONE
Print Occupancy Form  3/4/2016 DONE
1st review completed  2/24/2016 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK2/18/2016 2/24/2016 FAIL
DetailsJavier Guzman
ePlan
Meeting  2/23/2016 DONE
Paper plans were mailed in 2-2-16 with no application. Called Bob Cobak and informed him that I wouldn't be able to start this without an app. he stated that they were still working on it and would get in mailed in. Received an email, 2-19, from Cliff Shick; in the email it showed a permit number. Looked at the permit and notice it was applied for online. Spoke with Javier, 2-22, infoming him what happened with the paper plans and he said they would need to be voided since the plans online only had one person left to review them.
Routing - FIRE2/18/20162/18/20162/18/2016 PASS
DetailsKatie Marron
Comments attached to case.
Intake Approval  2/18/2016 PASS
DetailsDavid Ferguson
Routing - Addressing2/18/2016 2/18/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS2/18/2016 2/18/2016 PASS
DetailsRachael Beierle
Application received  2/16/2016 DONE
Application submitted via PDS Online on Feb 16 2016 4:31PM