Permit Information
Permit NumberBLD16-00473
StatusFinaled
Name MIKE BROWN
Site Address 1401 W IDAHO ST
Project NameThe WaterCooler
Customer Number 
ePlanReviewYes
Description
**Project Management-Angie Brosious**7/13/17 Temporary occupancy issued for pods 1 & 2 only (phase 1)** (1401 IDAHO – FORMER WATER COOLER BUILDING SITE - LIVE-WORK UNITS AND DWELLING UNITS) (DRH15-00461) (CAR15-00030) (CUP15-00083) (4-21-17 PLAN MODIFICATION TO STIFFEN THE FLOOR SYSTEM AT A CANTILEVERED STEEL BEAM AND AT THE CANTILEVERED WOOD FLOOR JOISTS SUPPORTED BY THAT BEAM TO REDUCE THE DEFLECTION OF THE FLOOR SYSTEM. WORK INCLUDES WELDING A WT STEEL SHAPED BEAM [i.e. A “T” CUT FROM A “W” SHAPED BEAM] TO THE BOTTOM FLANGE OF THE STEEL BEAM AND INSTALLING TWO WOOD KICKERS FOR EACH FLOOR JOIST. THE KICKERS WILL BE ORIENTED PERPENDICULAR TO THE STEEL BEAM AND WILL EXTEND AT A 45 DEGREE ANGLE FROM THE BOTTOM OF THE NEW BEAM UPWARD TO THE SIDE OF THE WOOD JOIST IT IS INTENDED TO STIFFEN. EACH KICKER WILL BE ORIENTED PARALLEL TO THE JOIST IT SERVES AND WILL BE NAILED TO THE SIDE OF THAT JOIST.) The NFPA 13R fire sprinkler system is used for the R-2 Occupancy. To construct a 34,716 square foot apartment building (11,502 square feet 1st story, 11,609 square feet 2nd story, and 11,605 square feet 3rd story). The 2nd and 3rd stories will have 15 single story dwelling units each. The 1st story will have 6 one story live-work units each having a mezzanine and 1 single story Type A dwelling unit without a mezzanine. All 1st story units are required to comply as Type B dwelling units. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood bearing walls, wood exterior walls, wood floors, wood roof, exterior doors, exterior windows, exterior tongue & grove cedar siding wall finish, exterior stucco wall finish, exterior stucco soffits, roof coverings, interior doors, millwork, and finishes. Special Inspection is required for concrete, welding, bolting, soils, wind resistance, seismic resistance, and for fire-stopping. Engineered fill is required. Seven foot tall green walls will be provided at grade. Deferred submittals include engineered wood trusses. This permit does not establish a Certificate of Occupancy for the commercial shell space. A separate permit is required to establish occupancy for that space. Before a live-work unit is allowed to be used for any commercial use, a separate permit is required to establish occupancy for that unit. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/26/20177/26/20177/26/2017PPASS
DetailsTony Young
Pete Phone #: ###-####,, all ok now
Permanent Occupancy  7/26/2017 DONE
PubWorks Occupancy Approval7/25/20177/25/20177/25/2017 DONE
DetailsTiffany Lowery
Zoning Approval7/21/20177/21/20177/21/2017 DONE
DetailsAndrea Tuning
BLD-Final7/13/20177/13/20177/13/2017PPART
DetailsTony Young
Pete Phone #: ###-####,, pod 1 and 2 ok for temp occupancy
FIRE-Final Inspection7/12/20177/13/20177/13/2017APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags and knox box is in place by fire riser room, building fire safety and evacuation plan documents will be placed in units when construction is complete. Final life fire safety inspection passed/complete.
Temporary Occupancy7/13/201710/11/20177/13/2017 DONE
DetailsTisha Gallop
Per Angie Brosious ok to issue TCO for pods 1 & 2 without any sign off from ACHD
PubWorks Temp Occupancy Appr7/13/20177/13/20177/13/2017 DONE
DetailsTiffany Lowery
BLD-Conference7/10/20177/11/20177/11/2017APART
DetailsTony Young
Pete Phone #: ###-####,, pod 1 and 2 walk through,, door lables,, hardware,, address,, other misc.
BLD-Energy code compliance6/6/20176/6/20176/6/2017PPASS
DetailsDave Hannah
Retail space insulation Phone #: ###-#### Inspection requested via web by Bob Ledford
BLD-Framing/Rough-in6/6/20176/6/20176/6/2017PPASS
DetailsDave Hannah
Pod #3 Live Work, framing at demising wall Phone #: ###-#### Inspection requested via web by Bob Ledford
BLD-Framing/Rough-in6/2/20176/5/20176/6/2017PPART
DetailsDave Hannah
Retail space at ground level northeast corner, including demising wall with Live work space #6 pod 3 Phone #: ###-#### Inspection requested via web by Bob Ledford ok to insulate work/tenent side
BLD-Energy code compliance6/1/20176/2/20176/2/2017PPASS
DetailsJim Sly
PM Live work #6, Pod #3, energy code. Phone #: ###-#### Inspection requested via web by Bob Ledford
BLD-Framing/Rough-in6/1/20176/2/20176/2/2017APART
DetailsJim Sly
AM Live work #6, Pod #3, framing Phone #: ###-#### Inspection requested via web by Bob Ledford
All OK except......East wall.
BLD-Framing/Rough-in5/26/20175/26/20175/26/2017PPASS
DetailsTony Young
Pete-garage Phone #: ###-####,, ok to insulate
BLD-Energy code compliance5/26/20175/26/20175/26/2017PPASS
DetailsTony Young
Pete-2nd floor Phone #: ###-####
BLD-Energy code compliance5/24/20175/25/20175/25/2017APASS
DetailsTony Young
Pete Phone #: ###-####
BLD-Wall cover5/24/20175/25/20175/25/2017APASS
DetailsTony Young
2nd floor // Pete Phone #: ###-####,, soffits east side
BLD-Framing/Rough-in5/23/20175/24/20175/24/2017APASS
DetailsTony Young
2nd floor // Pete Phone #: ###-####
BLD-Framing/Rough-in5/23/20175/23/20175/23/2017APART
DetailsDave Hannah
Pete Phone #: ###-####, Pod 3, 2nd and 3rd floors ok to insulate 3rd fl pod 3
BLD-Framing/Rough-in5/19/20175/22/20175/23/2017ANR
DetailsTony Young
Pete Phone #: ###-####
FIRE-Conference5/19/20175/22/20175/22/2017PDONE
DetailsJim Page
Fire conference complete
BLD-Energy code compliance5/16/20175/17/20175/17/2017APASS
DetailsTony Young
Pete Phone #: ###-####
BLD-Framing/Rough-in5/15/20175/15/20175/15/2017PPART
DetailsDave Hannah
Pete Phone #: ###-#### ok to insulate 1st floor pod 4
BLD-Energy code compliance5/11/20175/11/20175/11/2017PPASS
DetailsBrandon Shaw
As late in the afternoon as possible // Pete Phone #: ###-####
Second story, second pod
BLD-Framing/Rough-in5/9/20175/10/20175/10/2017PPASS
DetailsTony Young
Pete-2nd floor Phone #: ###-####,, ok to insulate pending trades
BLD-Energy code compliance5/9/20175/9/20175/9/2017PPART
DetailsDave Hannah
Pete Phone #: ###-#### third fl pod 4 ok
BLD-Framing/Rough-in5/5/20175/8/20175/8/2017APASS
DetailsDave Hannah
pete Phone #: ###-#### third floor pod 4 ok to insulate
FIRE-Conference4/28/20175/1/20175/1/2017APART
DetailsJim Page
Fire conference complete, awaiting answer from fire sprinkler plan reviewer for acceptance of proposed method to prevent pipe from freezing over top of breezeway.
BLD-Energy code compliance4/26/20174/27/20174/27/2017APASS
DetailsTony Young
Pete Phone #: ###-####,, soffit areas on exterior beyond support beams on north/east ok to cover
BLD-Framing/Rough-in4/24/20174/24/20174/24/2017PPART
DetailsTony Young
Pete Phone #: ###-####,, ok to insulate soffit areas,, letter from engineer to plan review
BLD-Framing/Rough-in4/21/20174/24/20174/24/2017APART
DetailsTony Young
Pete Phone #: ###-####,, soffit areas,, ok pending approval from engineer
OVERRIDE  4/21/2017  
Plan assigned to (CJW)4/5/20174/5/20174/21/2017 PASS
DetailsCarl Westfall
1st plan mod - 1401 Idaho - old watercooler site
CHANGE STATUS TO (ISS)  4/21/2017 DONE
Plan Mod
Plan Reviewer's activity  4/21/2017 DONE
Plan modification approved and sent to the permits desk.
Permit Ready to Issue  4/21/2017 DONE
DO NOT REISSUE PLAN MOD
Routing Off Site - STRUCTURAL4/5/2017 4/21/2017 PASS
DetailsCarl Westfall
Jared Bauder (CH2MHill)
(F) Reprint permit  4/21/2017 DONE
BLD-Energy code compliance4/12/20174/13/20174/13/2017APART
DetailsTony Young
Energy // Pete Phone #: ###-####,, same areas as frame,, electric room, east soffit on pod 3 ok
BLD-Framing/Rough-in4/10/20174/10/20174/10/2017PPART
DetailsMike Jordan
Pete-pod 2 and electric room and exterior facet in pod 4 Phone #: ###-#### Ok to insulate electrical room, need to complete column wraps. framing at pod soffits ok, ok to insulate.
BLD-Energy code compliance4/6/20174/7/20174/7/2017PPASS
DetailsTony Young
Pete-pod 2-1st floor Phone #: ###-####
BLD-Framing/Rough-in4/4/20174/5/20174/5/2017PPASS
DetailsTony Young
Pete-1st floor Phone #: ###-####, ok to insulate
BLD-Energy code compliance4/4/20174/5/20174/5/2017APASS
DetailsTony Young
Pete-2nd floor Phone #: ###-####
Plan Modification Accepted  4/5/2017 DONE
DetailsChristina Prado
Plan Mod to modify to cantilever beam framing-POD # 3
Routing - PLAN CHECK4/5/2017 4/5/2017 DONE
DetailsCarl Westfall
Routed to the Consultant Structural Engineer to review the 1st plan mod.
BLD-Energy code compliance4/3/20174/4/20174/4/2017APASS
DetailsTony Young
pete Phone #: ###-####,, room ok as noted before
BLD-Energy code compliance3/31/20174/3/20174/3/2017APASS
DetailsMike Jordan
Deek Phone #: ###-####. POd #2 3rd floor ok, except for unit #306.
BLD-Framing/Rough-in3/28/20173/28/20173/28/2017PDONE
DetailsMike Jordan
Phone #: ###-####. Ok to insualte.
BLD-Framing/Rough-in3/27/20173/27/20173/27/2017PPART
DetailsTony Young
Pete Phone #: ###-####,, upper level ok,, ok to insulate,, pod 2
BLD-Wall Bracing3/17/20173/17/20173/17/2017PPART
DetailsTony Young
Shear // Pete Phone #: ###-####,, exterior shear ok
BLD-Framing/Rough-in3/15/20173/15/20173/15/2017PPART
DetailsTony Young
Pete Phone #: ###-####,, roof nailing,, self certified
BLD-Blower Door Test Results3/8/20173/9/20173/9/2017APASS
DetailsTony Young
Pete-soffit and drop ceiling Phone #: ###-####,, pod 1
BLD-Energy code compliance3/7/20173/7/20173/7/2017PPASS
DetailsTony Young
Pete Phone #: ###-####,, pod 1 storage room riser room,, garage,, 1st floor ok
BLD-Framing/Rough-in3/2/20173/3/20173/3/2017APASS
DetailsTony Young
1st Floor.... Late morning // Pete Phone #: ###-####,, 1st floor on pod 1 ok to insulate,, need to verify if straps are needed and if headers on front wall are needed
BLD-Energy code compliance3/2/20173/2/20173/2/2017PPASS
DetailsTony Young
Second floor - Pete Phone #: ###-####
BLD-Framing/Rough-in2/28/20173/1/20173/1/2017APASS
DetailsTony Young
Pod 1 - 2nd floor, Pete Phone #: ###-####//
ok to insulate
BLD-Wall Bracing2/27/20172/28/20172/28/2017PPART
DetailsTony Young
Pod 3 - Pete Phone #: ###-####,,
BLD-Other2/24/20172/27/20172/27/2017PPART
DetailsTony Young
Late, please for Insulation over fire sprinkler - Pete Phone #: ###-####,, ok pending sprinkler permit tenting pass,, 3rd floor west pod
BLD-Energy code compliance2/24/20172/27/20172/27/2017ANR
DetailsTony Young
Pete Phone #: ###-####,, pod 1,, upper level
BLD-Energy code compliance2/24/20172/27/20172/27/2017ANR
DetailsTony Young
Pete Phone #: ###-####
BLD-Energy code compliance2/24/20172/24/20172/24/2017PNR
DetailsTony Young
Pete Phone #: ###-####,, needs fire pass
BLD-Framing/Rough-in2/22/20172/23/20172/23/2017PPART
DetailsTony Young
As last as possible // Pete Phone #: ###-####,, pod 1 3rd floor ok to insulate
BLD-Wall Bracing2/13/20172/14/20172/14/2017PPART
DetailsTony Young
Pete Phone #: ###-####,, pod 1 interior shear ok and 2nd level on pod 3 ok to stand interior wall
BLD-Conference1/31/20172/1/20172/1/2017APEND
DetailsTony Young
Pete Phone #: ###-####,, ?s about split occupancy
FIRE-Conference1/31/20172/1/20172/1/2017ADONE
DetailsJim Page
Fire conference complete
BLD-Conference1/30/20171/31/20171/31/2017PCANC
DetailsDave Hannah
Pete Phone #: ###-####
FIRE-Conference1/30/20171/31/20171/31/2017PCANC
DetailsJim Page
Conference rescheduled for 01FEB2017
BLD-Wall Bracing1/9/20171/9/20171/9/2017PPART
DetailsTony Young
Joe// please call before Phone #: ###-####,, exterior shear nailing,, ok with minor fixes
BLD-Framing/Rough-in12/20/201612/21/201612/21/2016PNR
DetailsTony Young
Joe Phone #: ###-####,, walk through only
BLD-Wall Bracing12/20/201612/21/201612/21/2016PPART
DetailsTony Young
Joe Phone #: ###-####,, work in progress on grid 4,, 4th floor,, ok
BLD-Conference12/7/201612/12/201612/15/2016APEND
DetailsTony Young
Joe Phone #: ###-####,, firewall continuation ?,, see plan review
BLD-Conference12/6/201612/7/201612/7/2016APEND
DetailsTony Young
Joe Phone #: ###-####,, firewall continuation ?,, see plan review,,
BLD-Framing/Rough-in12/5/201612/6/201612/6/2016PPART
DetailsTony Young
Joe Phone #: ###-####,, upper shear wall same as last lower,, ok,, wip
BLD-Wall Bracing10/24/201610/24/201610/24/2016PPART
DetailsTony Young
Joe// 3pm works best Phone #: ###-####,, line 7 shear nailing ok
BLD-Wall Bracing10/17/201610/18/201610/18/2016PPART
DetailsTony Young
Pat Phone #: ###-####,, met with Nate the frame foreman,, grid 1-4 and west side of 4-7 shear ok,, fire blocks via insulation between walls in place
BLD-Foundation10/5/201610/6/201610/6/2016APART
DetailsDave Hannah
Joe Phone #: ###-#### planters
BLD-Foundation9/21/20169/22/20169/22/2016APASS
DetailsMike Jordan
Joe-stem wall-pour time 12:30 Phone #: ###-####. Gridlines 8.3 to 12 and E to H.
BLD-Footing9/13/20169/15/20169/15/2016APEND
DetailsDave Hannah
Concrete at 10AM - Joe Phone #: ###-#### ok after mti signs off
BLD-Concrete9/8/20169/8/20169/8/2016PPEND
DetailsTony Young
Concrete at 4am // Joe Phone #: ###-####,, north area slab and interior slab footings,, special inspector will be on site,, work in progress
BLD-Footing8/30/20169/1/20169/1/2016PNR
DetailsPhil Shearer
concret slab wand struc footings-pour time Friday 4:00 AM Phone #: ###-####
BLD-Concrete8/25/20168/26/20168/26/2016APART
DetailsTony Young
11:00am pour; Joe Phone #: ###-####
BLD-Footing8/19/20168/22/20168/22/2016APEND
DetailsTony Young
Joe-concrete footing placement-pour time 1:00 Phone #: ###-####
BLD-Concrete8/18/20168/19/20168/19/2016APASS
DetailsJim Storey
Concrete at 1230 // Joe Phone #: ###-#### walls grid line 4-7 ok
BLD-Concrete8/11/20168/15/20168/15/2016APART
DetailsTony Young
Joe Phone #: ###-####-pour time 12:30,, special inspection pending
BLD-Foundation8/11/20168/12/20168/12/2016APEND
DetailsTony Young
Joe Phone #: ###-####,, special inspector on site
BLD-Footing8/3/20168/5/20168/5/2016PPASS
DetailsPhil Shearer
Joe Phone #: ###-####
Print Occupancy Form  6/10/2016 DONE
Issue PAID IN FULL permit  6/10/2016 DONE
OVERRIDE  5/11/2016  
Plan assigned to (CJW)2/23/20162/23/20165/11/2016 PASS
DetailsCarl Westfall
(1st done) 1401 W. IDAHO ST (OLD WATERCOOLER SITE) (Mar 22 - 25 days) - New
Routing - PLAN CHECK5/2/2016 5/11/2016 PASS
DetailsCarl Westfall
Location of van accessible parking spaces relative to accessible entrances was approved by Jason Blais, Building Official.
PLANS/APPL TAKEN TO FRONT DESK  5/11/2016 DONE
Permit Ready to Issue  5/11/2016 DONE
DetailsChristina Prado
As of 5/24/16, only ACHD is needed for issuance// C_P

Need ACHD, RP, GC Form & Revised Certificate of Value for issuance
Routing - Addressing5/2/2016 5/3/2016 PASS
DetailsLaura Hunter
Suite numbers transfered.
Routing - PLAN CHECK4/28/2016 5/2/2016 FAIL
DetailsCarl Westfall
The accessible parking space being on the shortest accessible route to accessible entrances has not been resolved.
Routing - Design Review5/2/2016 5/2/2016 PASS
DetailsAndrea Tuning
Plan resubmittals received  4/28/2016 DONE
Plan resubmittals requested  4/26/2016 DONE
Routing Off Site - STRUCTURAL4/19/2016 4/26/2016 PASS
DetailsCarl Westfall
Jared Bauder (CH2MHill)
Routing - PLANNING Land Div4/19/2016 4/20/2016 PASS
DetailsTodd Tucker
Routing PW Drainage4/19/2016 4/20/2016 PASS
DetailsBrian Murphy
Routing - PLANNING4/19/2016 4/19/2016 PASS
DetailsCody Riddle
Parcels have been consolidated as required.
Routing - PLAN CHECK4/13/2016 4/19/2016 FAIL
DetailsCarl Westfall
Some items still not resolved.
Routing - Design Review4/19/2016 4/19/2016 FAIL
DetailsAndrea Tuning
The applicant is required to provide two accesible parking spaces. One is required to be van accessible.
Routing - Addressing4/19/2016 4/19/2016 PASS
DetailsLaura Hunter
Plan resubmittals received  4/13/2016 DONE
Plans Examiner was out sick after 12:00 Noon on the 13th (Wednesday) until Monday the 18th. The resubmittal came in at about 2:16 on the 13th. That's the reason it sat so long before being routed as well as about 20 sheets that were not given the correct file name for propert versioning.
Route to Impact Fee Review3/28/20163/31/20163/31/2016 PASS
DetailsCindy M. Gould
1st review completed  3/28/2016 DONE
Plan resubmittals requested  3/28/2016 DONE
Routing PW Sewer Rating2/24/2016 3/28/2016 PASS
DetailsRachael Beierle
Was this review completed? CJW
Routing - PLAN CHECK2/23/2016 3/19/2016 FAIL
DetailsCarl Westfall
Routing Off Site - STRUCTURAL2/23/2016 3/2/2016 FAIL
DetailsCarl Westfall
Jared Bauder (CH2MHill)
Routing - Addressing2/23/2016 3/2/2016 FAIL
DetailsLaura Hunter
Parcels need consolidated.
Routing - PLUMBING2/23/2016 3/1/2016 PASS
DetailsDaryl Spivey
per plans and ISPC
Routing - MECHANICAL2/23/2016 2/29/2016 PASS
DetailsTroy James
Routing - FIRE2/23/20162/23/20162/26/2016 PASS
DetailsKatie Marron
Attached comments to plans.
Routing PW Drainage2/24/2016 2/25/2016 FAIL
DetailsBrian Murphy
need o and m agreement
Routing PW Sewer Design2/24/2016 2/25/2016 PASS
DetailsKyle S. Rosenmeyer
Routing PW Solid Waste2/24/2016 2/25/2016 PASS
DetailsMegan Durrell
Routing PW Geothermal2/24/2016 2/24/2016 PASS
DetailsJon R. Gunnerson
Not connecting to geothermal heating district. JG 2/24/16
Routing - PUBLIC WORKS2/23/2016 2/24/2016 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment2/23/2016 2/24/2016 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)

**Project Management-Angie Brosious**1: 3-story, slab-on-grade, wood framed mixed-use structure with 7 live/work apartment units, 30 upper floor apartment units, and a small retail shell space on the corner. Project includes all related site work, landscaping and mechanical, plumbing and electrical work.
Routing - PLANNING2/23/2016 2/24/2016 FAIL
DetailsCody Riddle
Site specific condition 2b from the conditional use permit required completion of a parcel consolidation prior to issuance. Emailed architect and owner today of the requirement. CER 2/24/16
Routing - PLANNING Land Div2/23/2016 2/24/2016 FAIL
DetailsTodd Tucker
The two parcels must be combined prior to issuance of a building permit.
Routing - Design Review2/23/2016 2/24/2016 FAIL
DetailsAndrea Tuning
The applicant did not submit:
bicycle parking plan showing 48 parking spaces.
transformers in appropriate locations.
cutsheets for all pedestrian scale light fixtures.
window details showing the required 2-inch reveal.
interior landscape planters that are 8-feet (measured inside of curb to inside of curb).
landscape plan.
mechanical screen details.
light poles in appropriate locations.
Pending Assignment by TLW2/23/2016 2/23/2016 DONE
DetailsTim L. Woodard
Intake Approval  2/17/2016 PASS
Application received  2/16/2016 DONE
Application submitted via PDS Online on Feb 16 2016 5:32PM
First Notice 8/5/2017