BLD-Final | 8/24/2016 | 8/25/2016 | 8/25/2016 | P | PASS |
Mike Jordan
|
|
|
Brandon Phone #: ###-####
|
DOC - Permit Finaled | 8/25/2016 | 8/25/2016 | 8/25/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 8/25/2016 | 8/25/2016 | 8/25/2016 | P | CANC |
Mike Jordan
|
|
|
Brandon Phone #: ###-####
|
BLD-Energy code compliance | 6/28/2016 | 6/29/2016 | 6/29/2016 | P | PART |
Tony Young
|
|
|
Brandon Phone #: ###-####,, north unit ok to cover
|
BLD-Framing/Rough-in | 6/28/2016 | 6/28/2016 | 6/28/2016 | P | PASS |
Jim Sly
|
|
|
would like call ahead; Brandon Phone #: ###-####
|
Plan Modification Accepted | | | 6/14/2016 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 6/14/2016 | | 6/14/2016 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Conference | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | DONE |
Jim Sly
|
|
|
Marcione Phone #: ###-####
|
BLD-Foundation | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | PASS |
Tony Young
|
|
|
Brandon Phone #: ###-####
|
BLD-Foundation | 4/1/2016 | 4/4/2016 | 4/4/2016 | A | PASS |
Tony Young
|
|
|
Brandon Phone #: ###-####
|
BLD-Foundation | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | NR |
Tony Young
|
|
|
Brandon Phone #: ###-####
|
BLD-Footing | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PASS |
Tony Young
|
|
|
Brandon Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/28/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 3/9/2016 | | |
|
|
|
|
Plan assigned to (BJM) | 2/22/2016 | 2/22/2016 | 3/9/2016 | | DONE |
Brian McGowan
|
|
|
due 3/9 L2 townhouse (ref. 15-00690, 00689?)
|
Inspection Record Card- Bld | | | 3/9/2016 | | DONE |
|
|
|
|
Telephone call | | | 3/9/2016 | | DONE |
|
|
|
called Brandon to let know permit is ready
|
1st review completed | | | 3/9/2016 | | FAIL |
Brian McGowan
|
|
|
Failed, needed fire rated wall details.
|
Plan resubmittals received | | | 3/9/2016 | | DONE |
|
|
|
resubmittals for fire wall details
|
Routing - PLAN CHECK | 3/9/2016 | | 3/9/2016 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 3/9/2016 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/9/2016 | | DONE |
|
|
|
***requirements met****Need RP; one given expire 2013
|
Routing - PLAN CHECK | 2/22/2016 | | 3/9/2016 | | FAIL |
Brian McGowan
|
|
|
Failed, needed fire rated wall details.
|
Plan resubmittals received | | | 2/25/2016 | | DONE |
|
|
|
One copy manual j. taken to troy j
|
Routing - MECHANICAL | 2/25/2016 | | 2/25/2016 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 2/19/2016 | | 2/22/2016 | | FAIL |
Troy James
|
|
|
emailed applicant to bring in a manual j that is not condensed version. Cannot read report
|
Plan assigned to (LEG) Tisha | 2/17/2016 | | 2/22/2016 | | DEFR |
Tisha Gallop
|
|
|
ref. 15-00690, 00689
|
Routing - PLANNING | 2/17/2016 | | 2/19/2016 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 2/17/2016 | | 2/17/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/17/2016 | | 2/17/2016 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/17/2016 | | DONE |
|
|
|
|
Intake Approval | | | 2/17/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/17/2016 | | DONE |
|
|
|
|
Application received | | 2/17/2016 | | | |
|
|
|
|