Third Notice | | 6/20/2016 | 7/11/2016 | | DONE |
|
|
|
|
Second Notice | | 5/21/2016 | 6/15/2016 | | DONE |
|
|
|
|
First Notice | 5/4/2016 | 5/4/2016 | 5/11/2016 | | DONE |
Jim Storey
|
|
|
Mailed 5-12-16
|
BLD-Final | 5/3/2016 | 5/4/2016 | 5/4/2016 | P | PASS |
Jim Storey
|
|
|
Please call Jared @ ###-#### 1/2 hour prior to inspection, thanks. Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
DOC - Permit Finaled | 5/4/2016 | 5/4/2016 | 5/4/2016 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 5/3/2016 | 5/4/2016 | 5/4/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, final life fire safety inspection passed/complete.
|
BLD-Framing/Rough-in | 4/13/2016 | 4/14/2016 | 4/14/2016 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Concrete | 4/7/2016 | 4/8/2016 | 4/8/2016 | P | PASS |
Jim Storey
|
|
|
Grout is scheduled for 2pm. CMU 4''-8''8" Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Foundation | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Footing | 3/28/2016 | 3/29/2016 | 3/29/2016 | P | PART |
Jim Storey
|
|
|
Concrete is scheduled to pour at 2pm. Phone #: ###-#### Inspection requested via web by Jared Waggoner need engineers aproval copy of emt in footting
|
Issue PAID IN FULL permit | | | 3/25/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/25/2016 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/23/2016 | 3/28/2016 | 3/23/2016 | | PASS |
Cindy M. Gould
|
|
|
Under threshold no fees required
|
Plan assigned to (AJS) | 2/25/2016 | 2/25/2016 | 3/22/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 TI - ePlanReview - Chevron Carwash
|
Routing - PLAN CHECK | 2/25/2016 | | 3/22/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 3/22/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 3/22/2016 | | 3/22/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 3/22/2016 | | 3/22/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/22/2016 | | DONE |
Christina Prado
|
|
|
***ALL MET*** Need ACHD, RP, GC Form & Revised Certificate of Value for issuance
|
Routing - FIRE | 2/25/2016 | 2/25/2016 | 2/29/2016 | | PASS |
Scott Arellano
|
|
|
No separate comments attached.
|
Routing - Erosion and Sediment | 2/25/2016 | | 2/29/2016 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. ESC general permit conditions apply to prevent stormwater pollution associated with construction. Levl 3 exterior TI. Need to designate an RP upon permit issuance.
|
Routing - Design Review | 2/25/2016 | | 2/29/2016 | | PASS |
Josh Wilson
|
|
|
Ok per DRH16-00035
|
Routing - Addressing | 2/25/2016 | | 2/25/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 2/25/2016 | | 2/25/2016 | | PASS |
Rachael Beierle
|
|
|
|
Pending Assignment by JCB | 2/25/2016 | | 2/25/2016 | | DONE |
Jason Blais
|
|
|
|
Routing - PLUMBING | 2/25/2016 | | 2/25/2016 | | PASS |
Bill VanDegrift
|
|
|
no plumbing
|
Intake Approval | | | 2/24/2016 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen and plan review fees paid.
|
Intake Approval | | | 2/18/2016 | | FAIL |
|
|
|
The site specific fire flow letter is required
Provide either an erosions and sediment control waiver letter or an erosion and sediment control plan.
If the additional or newly enclosed are is to be heated an envelope compliance for the area will be required.
Is interior lighting being provided if so please provide a lighting schedule.
Indicate and provide an equipment schedule.
|
Application received | | | 2/17/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 17 2016 12:47PM
|