First Notice | 5/2/2016 | 5/2/2016 | 5/11/2016 | | DONE |
Jim Storey
|
|
|
Mailed 5-12-16
|
BLD-Final | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-####per the aproved plan
|
DOC - Permit Finaled | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PASS |
Jim Storey
|
|
|
per the aproved plan
|
FIRE-Final Inspection | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Other | 4/19/2016 | 4/20/2016 | 4/20/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-####. 1st layer of sheetrock
|
BLD-Framing/Rough-in | 4/15/2016 | 4/18/2016 | 4/18/2016 | A | PASS |
Phil Shearer
|
|
|
Rick Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/8/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/8/2016 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/19/2016 | 2/19/2016 | 3/30/2016 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - Paper - Vista Ave. Apts. Mezzanine
|
Routing - PLAN CHECK | 3/28/2016 | | 3/30/2016 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 3/30/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/30/2016 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Inspection Record Card- Bld | | | 3/30/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/30/2016 | | DONE |
|
|
|
need GC and rev cert of val
|
Telephone call | | | 3/30/2016 | | DONE |
|
|
|
called Dana Kauffman to let know permit is ready and that we need the GC and rev cert of val
|
Routing - FIRE | 3/24/2016 | 3/24/2016 | 3/28/2016 | | PASS |
Katie Marron
|
|
|
Revised comments attached to plans.
|
Routing - PLAN CHECK | 3/10/2016 | | 3/24/2016 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 3/18/2016 | | DONE |
|
|
|
resubmittal received 2 copies of sheets A0.1 & A1.1-tood to Carl M
|
Route to Impact Fee Review | 3/10/2016 | 3/13/2016 | 3/10/2016 | | PASS |
Stephanie Jensen
|
|
|
|
1st review completed | | | 3/10/2016 | | FAIL |
|
|
|
Failed Plan Check and Fire.
|
Routing - FIRE | 3/9/2016 | | 3/10/2016 | | FAIL |
Scott Arellano
|
|
|
Report attached to plans.
|
Routing - PLAN CHECK | 2/19/2016 | | 3/9/2016 | | FAIL |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 3/7/2016 | | DONE |
|
|
|
|
Pending Assignment by JCB | 2/18/2016 | | 2/19/2016 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 2/18/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 18 2016 11:17AM
|
Plans ACCEPTED BY PLAN TECH | | | 2/18/2016 | | DONE |
|
|
|
|
Intake Approval | | | 2/18/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/18/2016 | | DONE |
|
|
|
|